2012 Camelot Close out Report

2012 Camelot Close out Report
2012 Camelot Close out Report

Close Out Report

Doc. No. : ERT/COR

Camelot CA Platform

Camelot CA Pipelines

Camelot CB Pipelines Decommissioning Programmes

Close Out Report

14 AUGUST 2013

Issued by:

Energy Resource Technology (UK) Limited

Helix House

Kirkton Drive

Dyce

Aberdeen

AB21 0BG

Contact:

Oliver Willis

Projects Director

owillis@https://www.360docs.net/doc/2b8853307.html,

01224 351 803

Close Out Report

Doc. No. : ERT/COR ABBREVIATIONS USED

BoD Basis of Design

Alpha

CA Camelot

Bravo

CB Camelot

DECC Department of Energy and Climate Change

DP Dynamically

Positioned

DSV Dive Support Vessel

Agency

EA Environment

EIA Environmental Impact Assessment

EMT Environment Management Team

ERT Energy Resource Technology (UK) Limited

ES Environmental

Statement

HLV Heavy Lift Vessel

HSE Health and Safety Executive

M meter

MCAA Marine and Costal Access Act

NFFO National Federation of Fishermen’s Organisations NORM Naturally Occurring Radioactive Material

OBM Oil Based Mud

PPM Parts Per Million

ROV Remote Operated Vehicle

RPS Radiation Protection Supervisor

Close Out Report

Doc. No. : ERT/COR

CONTENTS

1.0 INTRODUCTION (4)

2.0 DECOMMISSIONING PROGRAMME OUTCOME (5)

3.0 DEBRIS CLEARANCE (11)

4.0 POST DECOMMISSIONING SURVEYS (12)

5.0 VARIATIONS (13)

6.0 COSTS (14)

Appendix 1 - Clean Seabed Certificate – Camelot A Location (15)

Appendix 2 - Camelot Wellhead and Mattress Removal report (Ref. 11937/001/PJR) (17)

Close Out Report

Doc. No. : ERT/COR

1.0 INTRODUCTION

The last gas production from the Camelot CA platform was June 2009. Following a review of all the options it was decided to decommission the field and the formal cessation of production was approved by DECC in February 2011.

This document contains the close-out report for the combined decommissioning programmes as approved by the Secretary of State on 13 July 2012 for the Camelot CA platform, the Camelot CA pipelines and Camelot CB pipelines.

Energy Resource Technology (UK) Limited on behalf of the holders of the relevant section 29 notices issued by the Department of Energy and Climate Change (DECC) are pleased to confirm that the three Camelot decommissioning programmes have been completed as approved by the Secretary of State. The three section 29 holders are Energy Resource Technology (UK) Limited (ERT), ERT Camelot Limited and Apache Beryl I Limited (Apache) (all herein after referred to as the Holders). Apache were formerly known as Mobil North Sea LLC (Mobil).

This close out report is issued in line with the DECC decommissioning guidance notes and is intended to satisfy DECC and the relevant stakeholders that the approved programmes have been carried out. There were three main elements to the overall decommissioning plan;

?Abandonment of the CA Installation

o Removal to shore of the topsides and jacket, with all wells decommissioned and conductors and piles cut to 3m below seabed.

?Abandonment of the CA Pipelines

o Survey of the pipelines to be left in situ, cleaning, seawater flooding and disconnection, removal of spool pieces, grout bags and mattresses ?Abandonment of the CB Pipelines

o Survey of the pipelines to be left in situ, removal of grout bags and mattresses

The acceptance of this close-out report by DECC as evidenced by inclusion on the DECC website marks the completion of the project.

Close Out Report

Doc. No. : ERT/COR

2.0 DECOMMISSIONING PROGRAMME OUTCOME

Pipelines

In January 2011 notification was made to the HSE under the Pipeline Safety Regulations 1996 that decommissioning of the pipelines was to commence over the summer 2011.

In March 2011 the four pipelines were surveyed using a pipe tracker and seabed profiler mounted on an ROV. This survey recorded the position of the pipelines and the seabed as well as checking for debris. During this survey no debris was recorded.

In March 2012 the Camelot gas export pipeline was flooded with seawater from the Camelot platform in preparation for the pipeline pigging and flushing. With the pipeline flooded a Dynamically Positioned (DP) workboat was mobilised to the Camelot location with a filtration spread rigged up on the workboat deck. A flexible hose was connected between the DP workboat and the platform allowing the Camelot gas export pipeline to be pigged and flushed from the host platform using un-treated seawater. Flushing continued until the level of oil in the water being flushed out of the pipeline dropped to 24 Parts Per Million (ppm). All the fluids flushed from the pipeline were filtered on the workboat to reduce the level of oil in the flushing water discharged to sea to below 30ppm. Due to the efficiency of the filtration system and flushing programme the total weigh of hydrocarbon discharged was only a fraction of that allowed in the approved permit conditions. This also avoided the use of any chemical treatments in the pipeline which was left filled with raw seawater. With this flushing complete the pipelines were then ready to be disconnected.

Well Abandonment

In April 2011 equipment was mobilised to the platform to allow for the preliminary suspension of the six gas production wells. This was to allow any gas to be vented and the wells killed. This was to reduce the risk for the subsequent platform operations required for the final well plugging and topside decommissioning preparation.

In January 2012 the well decommissioning Basis of Design (BoD) was agreed with our independent well examiner and the HSE. Also in January a survey vessel was mobilised to survey the Camelot location to confirm it was suitable for a jack up work boat and to complete the pre-decommissioning environmental survey of the actual Camelot area. The environmental survey was to inform the EIA, the Environmental Statement (ES) and the MCAA licence application.

In February 2012 a jack up work boat was mobilised to the Camelot location and bridge linked to the Camelot platform. This was to support both the well decommissioning operations and the preliminary preparatory work on safety critical elements. As mentioned in the decommissioning programmes well decommissioning is regulated under a separate field licencing and consent regime and so could commence ahead of the formal approval of the actual decommissioning programmes.

At the end of April 2012 the jack-up unit departed the Camelot location having assisted the Camelot platform successfully plug the six gas production wells to the requirements outlined in the Oil and Gas UK guidelines. This included removing all cables from the permanent cement plugs and flushing and recovery of the Oil Based Mud (OBM) from behind the original casings. This work was carried out in accordance with the ERT well examination scheme and verified by our independent well examiner who issued the final certification for each well without reservation. The

Close Out Report

Doc. No. : ERT/COR

HSE were provided with a weekly well operations report during the work and copies of the final well status and the examination certification which they received without comment.

Platform Removal

In June 2011 the Camelot export pipeline was blown down and isolated at the host platform to reduce the risk to personnel working on the platform.

In June 2011 the HSE confirmed that they were satisfied with the case for health and safety submitted for the decommissioning phase of the Camelot operations by ERT as the Camelot platform duty holder. This decommissioning safety case updated the Camelot operations safety case which was in place until that time.

During the second half of 2011 engineering work was undertaken to establish the decommissioning options and the well plugging strategy. This was done through a comparative assessment process which reviewed all the options identified. Work was also started on the Environmental Impact Assessment (EIA) for the decommissioning operations. At this stage consultation was carried out with various parties including DECC on the development of the decommission plans for the platform and four pipelines.

In November 2011 an application was submitted to DECC for a Marine and Costal Access Act (MCAA) permit for the platform removal and associated activities.

The February 2012 environmental survey found no evidence of any drill cuttings in any of the sample locations in the Camelot area. This confirms that the cuttings were distributed widely during the original drilling by the strong local current. With no cutting pile detected at the Camelot area the provisions of OSPAR Recommendation 2006/5 on the Management Regime for Offshore Cuttings Piles do not apply. No sighting of marine mammals was reported during the survey work. During the well decommissioning in March 2012 some low level Naturally Occurring Radioactive Material (NORM) was detected inside one of the production control chokes when it was removed from one of the wells. The onsite ERT Radiation Protection Supervisor (RPS) secured this NORM material as required by the ERT local rules for control of radioactive materials. At this time a formal application was made to the Environment Agency (EA) for the permit required to manage this NORM under the Environmental Permitting (England & Wales) Regulations 2010.

With the jack-up alongside Camelot it was possible to take the Camelot helideck out of service temporally to allow the first two sets of lifting pad-eyes to be re-instated under the helideck and this was completed in April 2012. These pad-eyes were inspected and certified for the full topside weight using the same design and materials as were used for the original installation lifts.

In April 2012 the public consultation on the decommissioning plans closed with no comments received from either the public or the designated parties consulted.

In May 2012 an application was made to the Environment Agency (EA) in both the UK and the Netherlands for the trans-frontier shipment of waste permit required to deliver the topside and jacket to the Netherlands for dismantling, recycling and disposal. This was in line with the EU and OEDC regulations on waste shipments.

In May 2012 the Environment Agency (EA) approved the ERT permit required to manage the NORM under the Environmental Permitting (England & Wales) Regulations 2010. The low level NORM had been deposited by the reservoir water brought to surface with the produced gas.

Close Out Report

Doc. No. : ERT/COR

In June 2012 an abrasive cutting system was mobilised to the Camelot platform to cut the six plugged wells 3m below the seabed. Due to local tidal scouring around the base of the jacket it was considered prudent to make a deeper cut so all the wells were actually cut 5m below the natural seabed. With the wells cut a test lift was carried out on each to make sure that they were all free of the seabed for final lift out by the Heavy Lift Vessel (HLV). The successful abrasive cutting operations achieved the objective of avoiding the use explosives.

In June 2012 the HSE confirmed that they were satisfied with the case for health and safety submitted by ERT as duty holder for the dismantling operations required to remove the Camelot platform. This dismantling safety case then replaced the decommissioning safety case which had been approved earlier.

With the abrasive cutting system demobilised a welding team began work on the platform to re-instate the final two sets of lifting pad-eyes. This work was complete in July 2012 when the pad-eyes were inspected and certified for use.

In July 2012 the trans-frontier shipment of waste permit was approved by both the EA in the UK and the environment agency of the Netherlands. This was to allow the shipment of the topside and jacket to the Netherlands for dismantling, recycling and disposal.

In July 2012 the Environmental Management Team (EMT) at DECC issued a licence under the Marine and Costal Access Act 2009 (MCAA) for the platform removal and associated activities. This licence also met the needs of the Marine Works (Environmental Impact Assessment) Regulations 2007 (As Amended).

In July 2012 DECC issued the approval from the Secretary of State for the three Camelot decommissioning programmes. These were the decommissioning programmes for the Camelot CA platform, the Camelot CA pipelines and the Camelot CB pipelines.

In July 2012 the HLV mobilised to the Camelot location and commenced the final removal operations. The first items removed were the six well conductors previously cut 5m below the natural seabed. Also removed were the seawater intake caisson and the produced water discharge caisson. During the conductor removal activities work platforms were built around the top of the jacket legs allowing the topside to be cut free of the jacket. With the heavy lift rigging connected to the re-instated pad-eyes the

topside was lifted clear. The total load

including rigging was found to be 1,220

tons which was well within the maximum

estimated load of 1,492 tons used for the

lifting design calculations. The topside

was placed immediately onto a transport

barge and sea-fastened along with the

conductors and caissons. With the sea-

fastening complete the transport barge

departed for the Netherlands.

With the topside removed work platforms

were established on the jacket to allow for

the cutting and removal of the leg

extensions and placement of the abrasive cutting tool into each of the legs for cutting. Each leg was cut at least 3m below the natural seabed. As each leg was cut a rigging arrangement was attached to the top of the jacket allowing the HLV to lift the jacket clear of the seabed immediately

Close Out Report

Doc. No. : ERT/COR

after the final cut. The total jacket load including rigging was found to be 600 tons which was well within the maximum estimated load of 914 tons used for the lifting design calculations. The HLV lifted the jacket up until the bottom of the cut legs was level with the bottom of the HLV hull. The jacket was then sea-fastened to the fixation points on the HLV hull so it could be transported to shore on the HLV hook.

While the jacket was being sea fastened an

ROV survey was done of the seabed. The

ROV survey found that the area around the

jacket location has been scoured out to a

depth of around 5m below the natural

seabed but even at this depth there was only

one hole visible where a leg had been cut.

As this hole was below the scour level it was

filling naturally with sand moving on the

seabed. The ROV survey also found no

trace of the well conductors confirming that

they were cut below the scour depth other

than the 30” conductor of well A1. As the A1

conductor was not tied back to surface the

abrasive cutting jet was unable to penetrate the conductor wall so it was not cut and remained in place. The A1 conductor was sitting about 2m above the natural seabed so did not present an immediate hazard to marine activities ahead of the final removal.

Having completed operations at the former Camelot location the HLV sailed to the Netherlands and placed the jacket structure onto the

quayside of the dismantling facility. The HLV

then picked up the topside from the transport

barge and place this on the quayside next to

the jacket. The use of the HLV in port allowed

the unloading to be done without the assistance

of any heavy lift self-propelled trailers.

During all the offshore operations required for

the decommissioning programmes there were

no spills or accidental releases of any

hydrocarbons into the environment.

In August 2012 the UK Hydro-graphic office, the Marine and Coastguard Agency, Trinity House and the HSE were all informed of the removal of the Camelot platform and the associated navigation aids displayed from the platform. This was to allow the navigation charts to be update as required. CDA Deal was also informed of the platform removal so that the Kingfisher FishSAFE Information Service could be updated to show the A1 conductor as a suspended well ahead of the final removal.

In October 2012 the survey vessel that was used in January 2012 was re-mobilised to complete the first post-decommissioning environmental survey of the actual Camelot area. This environmental survey is intended to be a base line which can then be used for comparison with next environmental survey currently planned for October 2014.

Close Out Report

Doc. No. : ERT/COR

The Environmental survey showed there to be no areas of environmental significance or value to nature conservation in the transect areas. The data showed that the seabed almost entirely consists of uninterrupted features that are consistent with fine sediments such as slightly gravelly sands or sands. The only area where there are any features that show there to be materials other than sand is in and around the previous platform location where there are man made rock dump features.

In March 2013 a DSV was mobilised

to the Camelot location to cut and

remove the A1 Conductor that

remained in place. At the same time

the divers swept the area and

removed the few small items of debris

found. With the remaining conductor

cut the Camelot platform location and

the Camelot pipeline routes were

then ready for the final trawl sweep.

Mattress removal

As preparation for the CA jacket removal and pipeline flushing operations a DSV was mobilised to conduct spool removal in April 2012. Following the as found survey it was identified that there were only 5 no. mattresses at the tie-in location as opposed to the expected 7 no. Of these, 2 no. mattresses (and a grout bag) were recovered, with 3 no. mattresses left in situ, buried to a depth in excess 0.5m within the rock dump area.

During the same DSV campaign in April 2012 a survey was taken of the old Camelot B location to verify pipeline burial. During this survey 4 no. of the reported original 10 no. mattresses present were recovered. The remaining 6 no. (if present) had been buried to a depth well in excess of the 0.5m probe investigation. At the same time, a survey of the tie in area at the host platform identified 4 no. concrete mattresses which were recovered.

Following the A1 conductor removal and further

surveys it was identified that from the original

field installation that there could still have been

up to 22 no. frond mattresses along the

PL878/879 routes. Following consultation with

DECC, in June 2013 it was decided to mobilise

an ROV Support vessel c/w hydraulic grapple

spread to locate and recover these mattresses,

along with a further attempt to locate and recover

the buried 6 no. concrete mattresses left in-situ

at the CB location.

The locations and pipelines were all positively

identified but despite several attempts with the

grapple, no concrete mattresses were found,

despite an investigation depth of c.1m into the

seabed.

Close Out Report

Doc. No. : ERT/COR ? 9 Grabs at NW location - Fronds only recovered

? 3 Grabs at Mid location - Fronds only recovered

? 8 Grabs at SE location - nothing recovered

The full June 2013 mattress recovery report is included in Appendix 2.

Close Out Report

Doc. No. : ERT/COR

3.0 DEBRIS CLEARANCE

Following discussions with the National Federation of Fishermen's Organisations (NFFO) a fishing vessel was mobilised in April 2013 to the Camelot location to conduct trawl sweeping operations within the 500m zone that was established around the Camelot platform. In June 2013 another vessel was mobilised to conduct 100m pipeline corridor sweeps along the lengths of the buried lines. Having completed the trawl sweeps to the satisfaction of the skippers the NFFO have provided Certificate of Clean Seabed (appendix 1) confirming that the area at time of the sweeps was found to be clear of any obstruction or debris that could be attributed to the Camelot development.

In April 2013 CDA Deal were informed of the removal of the A1 conductor at the Camelot location and the successful trawl sweep confirming that the former location was free of hazard. This will allow the Camelot location to be removed from the Kingfisher FishSAFE Information Service.

Close Out Report

Doc. No. : ERT/COR

4.0 POST DECOMMISSIONING SURVEYS

In 2014 which is two years after the decommissioning was completed the Holders will undertake a second post-decommissioning environmental seabed sampling survey to verify the levels of any contamination and assess the level of biological activity in the area. The results of this survey will be compared with the first post-decommissioning environmental survey which was done in October 2012. Comparing the results of the two surveys should allow the Holders and DECC to evaluate the site remediation process.

Also in 2014 the Holders will undertake the first post-decommissioning pipeline burial survey to verify the location of the pipelines relative to the seabed. The results of this survey will be compared with pipeline survey done in March 2011 and this should allow the Holders and DECC to evaluate the stability of the pipelines and the effectiveness of the self-burial process. This survey will also include the cut piles.

The final post decommissioning survey will be a further repeat pipeline survey four years after the decommissioning activity which will be 2016. Once again this survey will record the location of all pipelines for comparison with both the original baseline survey from 2011 and first post-decommissioning pipeline survey in 2014. This survey will also check that the cut piles of the CA platform remain sufficiently buried.

All survey results will be discussed and agreed with DECC and further studies or pipeline surveys may be carried out if considered appropriate by the Holders and DECC.

Close Out Report

Doc. No. : ERT/COR

5.0 VARIATIONS

The Holders can confirm that the decommissioning programme was executed as approved by the Secretary of State without any significant variations.

During the decommissioning activity the filtration system captured a total of 108kg of hydrocarbons from the export pipeline and 32kg of hydrocarbons from the topside piping. As a dry gas field this small level of hydrocarbons is to be expected.

During the jacket dismantling onshore almost 10 tons of anodes were recovered and recycled.

The NORM contamination found in the topside piping was sent for laboratory testing and this determined that the activity level was low enough to allow for disposal directly to conventional land fill. Although the land fill option was available it was agreed that the best option was to send the materials to Germany where they could be smelted down and re-cycled. As the scale inside the piping was very thin it has been estimated that the total weight of NORM material is less than 1 ton.

With the platform unloaded the dismantling contractor made the area safe and first began the process of cleaning and removing the NORM contaminated pipe and process equipment. Of the fourteen areas found to be contaminated laboratory test measurements confirmed that the actual contamination was so low that twelve were exempt from all legislation and notification. The remaining two results were slightly higher and so required notification but were still low enough to be exempt from any licencing requirement. The NORM level was also low enough to be exempt from the need to measure the exact quantities recovered. Although the NORM contamination was shown to be low enough for disposal directly to land fill it was agreed that the best option was to send the materials to Germany where they could be smelted down and re-cycled.

With the NORM contamination removed the dismantling contractor then completed the dismantling, re-cycling and disposal operations all in accordance with the approved trans-frontier shipment of waste permit. As part of this re-cycling process a detailed inventory of materials was developed and a rigorous segregation system was put in place to maximise the recovery of materials. Based on the detailed inventory listing the dismantling contractor expects to re-cycle in excess of 95% of the total weight of the topside and jacket combined.

Following the removal of the platform, there was a time based variation to the agreed plan, with an eight month delay before the A1 conductor stump was recovered. This in turn led to the delay in completing mattress recovery works (refer to Appendix 2) and the final seabed clearance trawl sweep.

Close Out Report

Doc. No. : ERT/COR

6.0 COSTS

This section reviews the decommissioning costs to date and compares them with the original estimates included in the decommissioning programme. This comparison excludes any potential future costs.

Camelot CA platform

Platform and Jacket Preparation and Removal.

Original estimate £5 million to £6 million. Actual cost £6.3 million.

Platform and Jacket Recycling.

Original estimate £0 million (scrap value). Actual cost £1.5 million.

Six Platform Well Abandonments.

Original estimate £6.9 million to £7.5 million. Actual cost £7.5 million.

Engineering and Studies.

Original estimate £0.5 million to £1 million. Actual cost £1.0 million.

Platform total.

Original estimate £12.4 million to £14.5 million. Actual cost £16.3 million.

Camelot CA and CB pipelines

Pipeline Infrastructure Decommissioning in situ.

Original estimate £2 million to £5.5 million. Actual cost £3.9 million.

Engineering and Studies.

Original estimate £0.5 million to £1.0 million. Actual cost £0.8 million.

Pipeline total.

Original estimate £2.5 million to £6.5 million. Actual cost £4.7 million.

Overall Total

Original estimate £14.9 million to £21 million. Actual cost £21 million.

The key difference between the original estimate and actual costs was the impact of the NORM processing on the platform re-cycling cost. Originally it was estimated that the scrap value of the various steel components would cover the full dismantling cost. Unfortunately the NORM contamination in the pipework and process equipment made this re-cycling more complex and impacted on the cost. Even though subsequent testing showed that the NORM contamination was below the allowable limits and not hazardous the handling procedures and management of site operations had to be reorganised on the basis that the contamination was a hazard risk.

Doc. No. : ERT/COR

Appendix 1 - Clean Seabed Certificate – Camelot A Location

Close Out Report

Doc. No. : ERT/COR

National Federation of Fishermen’s Organisations.

30 Monkgate

York

YO31 7PF

Tel: 01904 635 432

Fax: 01904 635 431

e-mail: apiggott@https://www.360docs.net/doc/2b8853307.html,

Web: https://www.360docs.net/doc/2b8853307.html,

29th July 2013.

To whom it may concern

Decommissioned Camelot Platform & Infrastructure pipe lines

TRAWL SWEEP Confirmation letter

The Grimsby based Trawler Fruitful Harvest GY 991 operating under NFFO membership conducted the following activities at the Decommissioned Camelot Platform Well location commencing 19th April 2013.

1.20th April a series of intense bi-directional sweeps over known Camelot 500 metre Zone with the objective of

clearing seabed debris or identifying seabed snags within that zone. ( see plotter tracks)

2.21st April 2013 a secondary series of bidirectional sweeps over the Camelot 500 metre zone location with the

objective of demonstrating the area to be free of debris or hazard following the decommissioning programme was conducted.

3.8th June 2013 – 12th June 2013 a series of intense bi-directional sweeps over known Camelot pipelines was

conducted ( see plotter tracks) with the objective of ensuring no seabed snags along the said pipeline rout.

A significant number of passes were made across the area. (see attached plotter data) with Standard Southern North Sea Anchor Seine trawl equipment was used to conduct the sweeps.

The method used was to ensure continuous contact with the seabed to determine whether there were any major obstructions which might present a major snag for future fishing activities. The trawl net was seen as a means of gathering any items of debris located in the area.

Following completion of the sweep programme the skipper of Fuitful Harvest GY991 has reported to NFFO the following:

a) No debris was recovered on either operation (500mtr zone & pipeline).

b) One minor snag was experienced during the Camelot 500mtr zone sweeps.

c) The snag was encountered while towing gear in a NE direction at 12.00hrs on 20/04/13 at position 52-56.5750N

002-09.091E. No damage to the trawl was caused but shredding of ropes was encountered ( see pictures). No

object could be marked on sounder but black marks along damaged rope may indicate a cutting pile (see pictures) Based upon feedback provided by the skipper, the Federation accepts that the decommissioned Camelot site 500m safety zone was found to be clear of debris and any major obstruction. The Camelot associated pipeline was also clear of any significant seabed obstruction.

Signed

Alan Piggott

A Piggott

General Manager

Doc. No. : ERT/COR

Appendix 2 - Camelot Wellhead and Mattress Removal report (Ref. 11937/001/PJR)

REVISION RECORD:

PROCEDURE REVISION RECORD:

CONTENTS

1.0INTRODUCTION (4)

1.1FIELD LAYOUT (4)

1.2SCOPE OF WORK (5)

1.3EQUIPMENT (6)

2.0MATTRESS RECOVERY OPERATIONS (8)

2.1AS FOUND SURVEY (8)

2.2SE MATTRESS LOCATION (8)

2.3NW MATTRESS LOCATION (10)

2.4MID MATTRESS LOCATION (13)

3.0WELLHEAD RECOVERY OPERATIONS (16)

4.0APPENDICES (21)

4.1SEABED CLEARANCE CERTIFICATE (21)

5.0DRAWINGS (22)

2012年北京中考数学试卷(含答案)

2012年中考数学卷精析版——北京卷 (本试卷满分120分,考试时间120分钟) 一、选择题(本题共32分,每小题4分)下面各题均有四个选项,其中只有一个是符合题意的. 3.(2012北京市4分)正十边形的每个外角等于【】 A.18?B.36?C.45?D.60? 【答案】B。 【考点】多边形外角性质。 【分析】根据外角和等于3600的性质,得正十边形的每个外角等于3600÷10=360。故选B。4.(2012北京市4分)下图是某个几何体的三视图,该几何体是【】 A.长方体B.正方体C.圆柱D.三棱柱 【答案】D。 【考点】由三视图判断几何体。

【分析】主视图、左视图、俯视图是分别从物体正面、左面和上面看,所得到的图形,由于主视图和左视图为矩形,可得为柱体,俯视图为三角形可得为三棱柱。故选D。 5.(2012北京市4分)班主任王老师将6份奖品分别放在6个完全相同的不透明礼盒中,准备将它们奖给小英等6位获“爱集体标兵”称号的同学.这些奖品中3份是学习文具,2份是科普读物,1份是科技馆通票.小英同学从中随机取一份奖品,恰好取到科普读物的概率是【】 A.1 6 B. 1 3 C. 1 2 D. 2 3 【答案】B。 【考点】概率。 【分析】根据概率的求法,找准两点:①全部等可能情况的总数;②符合条件的情况数目;二者的比值就是其发生的概率。本题全部等可能情况的总数6,取到科普读物的情况是2。∴取到科普读物的概率是 21 63 =。故选B。 6.(2012北京市4分)如图,直线AB,CD交于点O,射线OM平分∠AOD,若∠BOD=760,则∠BOM 等于【】 A.38?B.104?C.142?D.144? 【答案】C。 【考点】角平分线定义,对顶角的性质,补角的定义。 【分析】由∠BOD=760,根据对顶角相等的性质,得∠AOC=760,根据补角的定义,得∠BOC=1040。 由射线OM平分∠AOD,根据角平分线定义,∠COM=380。 ∴∠BOM=∠COM+∠BOC=1420。故选C。 7.(2012北京市4分)某课外小组的同学们在社会实践活动中调查了20户家庭某月的用电量,如下表所示: 用电量(度)120 140 160 180 200 户数 2 3 6 7 2 则这20户家庭该月用电量的众数和中位数分别是【】 A.180,160 B.160,180 C.160,160 D.180,180 【答案】A。 【考点】众数,中位数。 【分析】众数是在一组数据中,出现次数最多的数据,这组数据中,出现次数最多的是180,故这组

推进社会管理创新工作方案

推进社会管理创新 工作方案

推进社会管理创新工作方案 社会管理创新是提升社会建设效能、效率的重要途径,是维护社会和谐稳定的必然要求,是新形势下加快科学发展的重大课题。为推进城西街道办事处社会管理创新,根据平发()33号文件《中共平遥县委、县政府推进社会管理创新工作实施方案》的精神,结合我街道办的实际,特制定本方案。 一、指导思想 以科学发展观为统领,以建立与社会主义市场经济体制相适应的社会管理体系为目标,高举邓小平理论和“三个代表”重要思想伟大旗帜,按照“最大限度激发社会活力、最大限度增加和谐因素、最大限度减少不和谐因素”的总要求,根据县委、县政府关于推进社会管理创新工作的安排部署,围绕“旅游名城”这一特色,进一步创新社会服务理念,提高社会管理能力和水平,促进社会管理科学、高效,为平遥的经济社会转型跨越发展营造良好的社会氛围。 二、工作目标和任务 以项目建设为统领,按照科学化、系统化、规范化要求,经过网格建设、平台建设、体系建设、制度建设,全面推进古城社会管理创新。在现有条件下,充分运用现代信息网络技术,经过整合资源、协同工作,实现无缝隙、无盲点的政民互动的管理模式,创立既充满活力又和谐稳定的社会环境。 三、创新举措及职责分工

贯彻中央和省市精神,按照县政府的安排部署,结合我街办实际,以“三级网格”承载、“五大致系”建设为主要抓手,综合施措,突出重点,全面推进社会管理创新工作。 (一)“三级网格”承载。由街办牵头负责,各社区居委会、各有关单位具体组织实施,全面推行“三级网格化”管理模式。 1、一级网格。即街办级网格。组建成立社会管理服务中心。主要对“三级网格”建设及运行提出指导性意见,对重大事项进行综合协调、办理和处理,对系统进行升级维护,对下级网格进行考核、评估、监督与管理,做好与县级网格的对接工作。 2、二级网格。即社区居委会网格。每个社区居委会为一个网格,共6个网格。各社区居委会主任为该区域网格建设的第一责任人,根据工作需要,配备相应的工作人员,具体负责本区域网格化管理的指导、监督和考评等日常工作。 3、三级网格。即基础网格。按照“网格区划、整体覆盖、精细管理”的原则,以社区居委会所辖范围为基础,综合地理布局、道路走向、工作量等因素划分基础网格。按照户数300-500户、人口1000-1500人左右设置。基础网格边界必须明确,确保不遗漏、不交叉。 (二)“五大致系”建设。经过五大致系建设,全面推进11项重点工作。 1、推进基层组织建设创新

考博导师联系邮件模板

关于联系导师:下面列出我联系导师的几封邮件,供大家参考: (1)先给老师发了一封自荐信,说希望报考他的研究生,把自己的情况简要说明了一下 考博自荐信 尊敬的x老师: 您好! 我叫**,来自**,是华中科技大学化学与化工学院化学工程专业2012级的硕士研究生,我非常希望2015年6月毕业后能够在您的教导下攻读博士研究生学位。 教育背景: 2007.09-2011.06 华中科技大学化学与化工学院化学工程与工艺本科2012.09-2015.06 华中科技大学化学与化工学院化学工程硕士硕士阶段主要从事强化传质传热新技术研究和化工工艺过程开发,以及植物有效成分提取、分离工艺方向的研究。师从硕士生导师**。在**的谆谆教导之下,一方面阅读了不少与课题相关的外文文献,使我的专业知识眼界变得更为开阔,另一方面对模型的建立及编程有了一定的基础。 通过在网上对您的了解,知道**您主要研究传热过程及其强化;萃取过程及其强化;化工热力学;植物有效成分提取、分离工艺;反应与分离耦合过程;化工过程的模拟及安全设计策略。对我来说,传热过程及其强化的研究是我一直想要从事的领域(如蒸发式空冷器传热模型的建立、过程强化的措施等),非常希望能够在您的指导下在该领域取得一定成果。硕士期间,共参与过3个项目,分别为: 1、新型表面蒸发式空冷器研制开发与工业应用 2、金银花中提取绿原酸和黄酮类 3、武汉80万吨乙烯润滑油使用质量监测分析

取得的成果: 1、********** 2、********** 假如我有幸能到您的门下深造学习、攻读博士学位,我相信凭借着您的教导和我对化工的热爱,我一定会在化学工程方面有长足的发展。 实在抱歉占用了您这么长时间,当您在读这封信的时候,我正处于热切的期盼之中,非常渴望能早日聆听您的教诲! 此致 敬礼! 自荐人:** 2016年08月09日 (2)导师第二天就回复了邮件 **同学:您好! 欢迎报考。 如方便,请提供一份简历(包括大学期间情况、近照等)。 祝:好! (3)然后我继续给老师回邮件 **老师,您好! 按照您的要求,我已经做好了简历,并附上了两张个人生活照! 祝老师工作顺利!

【解析版】2013年北京市中考数学试卷及答案

北京市2013年中考数学试卷 一、选择题(本题共32分,每小题4分。下列各题均有四个选项,其中只有一个是符合题意的。 1.(4分)(2013?北京)在《关于促进城市南部地区加快发展第二阶段行动计划(2013﹣2015)》中,北京市提出了共计约3960亿元的投资计划,将3960用科学记数法表示应为()A.39.6×102B.3.96×103C.3.96×104D.0.396×104 考点:科学记数法—表示较大的数. 分析:科学记数法的表示形式为a×10n的形式,其中1≤|a|<10,n为整数.确定n的值时,要看把原数变成a时,小数点移动了多少位,n的绝对值与小数点移动的位数相同.当原数绝对值>1时,n是正数;当原数的绝对值<1时,n是负数. 解答:解:将3960用科学记数法表示为3.96×103. 故选B. 点评:此题考查科学记数法的表示方法.科学记数法的表示形式为a×10n的形式,其中1≤|a|<10,n为整数,表示时关键要正确确定a的值以及n的值. 2.(4分)(2013?北京)﹣的倒数是() A.B.C. ﹣D. ﹣ 考点:倒数. 分析:根据倒数的定义:若两个数的乘积是1,我们就称这两个数互为倒数. 解答: 解:∵(﹣)×(﹣)=1, ∴﹣的倒数是﹣. 故选D. 点评:本题主要考查倒数的定义,要求熟练掌握.需要注意的是: 倒数的性质:负数的倒数还是负数,正数的倒数是正数,0没有倒数. 倒数的定义:若两个数的乘积是1,我们就称这两个数互为倒数. 3.(4分)(2013?北京)在一个不透明的口袋中装有5个完全相同的小球,把它们分别标号为1,2,3,4,5,从中随机摸出一个小球,其标号大于2的概率为()A.B.C.D. 考点:概率公式. 分析:根据随机事件概率大小的求法,找准两点:①符合条件的情况数目,②全部情况的总数,二者的比值就是其发生的概率的大小. 解答:解:根据题意可得:大于2的有3,4,5三个球,共5个球, 任意摸出1个,摸到大于2的概率是.

考研写给导师的邮件 考研给导师发邮件

考研写给导师的邮件-考研给导师发 邮件 考研邮件联系导师模版 尊敬的曹教授,您好! 我是XXX,男,XXXX人,XX大学09级XXXX专业学生,我是从湖南大学机械与运载工程学院网上得到您的Email。我于2016年1月参加全国硕士研究生考试,参照近年的复试分数线,我可能有机会参加湖大的复试,故冒昧的提前和您联系。 我在本科学习期间曾搜到过老师的一些文章,对老师在车身设计方面颇感兴趣。在看了老师的一些资料后,对您在该领域的建树非常崇敬,很希望能够成为老师您的研究生、得到老师的指点。 对自己,我进行了仔细的思考和评估。我认为自己大学四年所学的知识以及所掌握的实验技能能够胜任协助您研究的任务。本科期间我都认真学习各课程知识,具有扎实的理论基础和较强的

动手能力;其次,我的英语能力还可以,已通过国家六级;另外,我的科研兴趣相当浓厚,曾参加过湖南省第五届大学生机械创新设计大赛,获得优秀奖以及校级一等奖;最后,我性格开朗,态度端正,做事踏实认真。 我诚挚地希望能成为您的学生,接受您的指导。当然,我会努力准备复试,争取高分通过,以弥补初试的失利,这样才有资格成为老师您的学生。我认为自己最大的优点就是端正的态度,理性的思维,相信自己能够完成老师交给的课题。 非常感谢您抽出宝贵的时间阅读我的自荐信,期待能够加入您的科研团队。敬候您的佳音。 祝您身体健康,工作顺利! 此致 敬礼 XXX 2016年2月21日 尊敬的湖南大学李教授:

您好!我是XXX,XX大学XX教授的学生,就读汽车专业,报考了贵校车辆工程专业学位的研究生。众所周知,湖南大学是中南地区实力最强的高校之一,而车辆工程更是全国各高校中的佼佼者,面对考研压力与年剧增的情况下,要考上贵校的研究生着实难上加难;在初试成绩公布后,参照近年的复试分数线,我有望能进入贵校的研招复试,故冒昧提前和您联系,多有打扰请老师见谅。 同时,在本校XX授和贵校研究生学长学姐的帮助指导下了解了您的科研方向。我对您的研究的方向:整车性能分析和优化、汽车气动噪声分析和优化与汽车CAE技术等都很感兴趣。在大学期间,我参加了机械创新设计大赛、湖南农业大学大学生创新性实验计划项目和“求真杯”,使自己在这方面的能力得到了培养,会操作激光雕刻机等实验室常用设备,有一定的科研能力和专业素养。本着一颗求知的心,倘若能够有幸

社会管理创新工作实施方案正式版

Some problems that have appeared or can be expected to come up with a solution to the problem, and through the record of the terms, effective supervision and implementation.社会管理创新工作实施方 案正式版

社会管理创新工作实施方案正式版 下载提示:此方案资料适用于某些已经出现的或者可以预期的问题,不足,缺陷,需求等,所提出的 一个解决问题的方案,并通过明文或条款的记录,加以有效的监督与执行,确保能达到预期的效果。 文档可以直接使用,也可根据实际需要修订后使用。 根据《中共xx市委、xx市人民政府关于推进社会管理创新工作的决定》和《xx 市社会管理创新工作方案》的具体要求,为切实做好社会管理创新工作,结合本单位工作实际,特制定本方案。 一、指导思想。坚持以邓小平理论和“三个代表”重要思想为指导,始终坚持“以人为本、服务为先”,深入贯彻落实科学发展观,紧紧围绕我市灾后重建和重返县域经济“十强”的战略目标,立足经济社会协调发展,深入探索社会服务管理新机制,全面提升社会管理能力水平,为

促进xx经济社会在更高层次上又好又快发展作贡献。 二、目标任务。根据市委、市政府的安排部署,积极配合各牵头单位和其他部门建立、健全社会服务管理机制。在招商引资工作基础上,进一步做好为投资企业的服务工作,通过优质的服务,促进社会管理的管理更新、思路创新和体制机制革新。 三、主要措施。 (一)继续加强社会主义精神文明建设。以建设社会主义核心价值体系为根本,加强理想信念教育、爱国主义教育和诚信教育、感恩教育等,通过参与市文明办组织的各项活动,广泛宣传,以提高职

2012年北京中考数学真题试卷(附答案)

2012年北京市高级中等学校招生考试 数 学 试 卷 学校 姓名 准考证号 一、选择题(本题共32分,每小题4分) 下面各题均有四个选项,其中只有一个是符合题意的. 1. 9-的相反数是 A .19 - B .19 C .9- D .9 2. 首届中国(北京)国际服务贸易交易会(京交会)于2012年6月1日闭幕,本届京交 会期间签订的项目成交总金额达60 110 000 000美元,将60 110 000 000用科学记数法表示应为 A .96.01110? B .960.1110? C .106.01110? D .110.601110? 3. 正十边形的每个外角等于 A .18? B .36? C .45? D .60? 4. 右图是某个几何体的三视图,该几何体是 A .长方体 B .正方体 C .圆柱 D .三棱柱 5. 班主任王老师将6份奖品分别放在6个完全相同的不透明礼盒中,准备将它们奖给小英 等6位获“爱集体标兵”称号的同学.这些奖品中3份是学习文具,2份是科普读物,1份是科技馆通票.小英同学从中随机取一份奖品,恰好取到科普读物的概率是 A . 1 6 B .13 C . 12 D . 23 6. 如图,直线AB ,CD 交于点O ,射线OM 平分AOC ∠,若76BOD ∠=?,则B O M ∠等于 A .38? B .104? C .142? D .144? 7. 某课外小组的同学们在社会实践活动中调查了20户家庭某月的用电量,如下表所示:

A.180,160 B.160,180 C.160,160 D.180,180 8.小翔在如图1所示的场地上匀速跑步,他从点A出发,沿箭头所示方向经过点B跑到点C,共用时30秒.他的教练选择了一个固定的位置观察小翔的跑步过程.设小翔跑步的时间为t(单位:秒),他与教练的距离为y(单位:米),表示y与t的函数关系的图象大致如图2所示,则这个固定位置可能是图1中的 A.点M B.点N C.点P D.点Q 二、填空题(本题共16分,每小题4分) 9.分解因式:269 mn mn m ++=. 10.若关于x的方程220 x x m --=有两个相等的实数根,则m的值是.11.如图,小明同学用自制的直角三角形纸板DEF测量树的高度 AB,他调整自己的位置,设法使斜边DF保持水平,并且边 DE与点B在同一直线上.已知纸板的两条直角边 40cm DE=,20cm EF=,测得边DF离地面的高度 1.5m AC=,8m CD=,则树高AB=m. 12.在平面直角坐标系xOy中,我们把横、纵坐标都是 整数的点叫做整点.已知点() 04 A,,点B是x轴 正半轴上的整点,记AOB △内部(不包括边界)的 整点个数为m.当3 m=时,点B的横坐标的所有 可能值是;当点B的横坐标为4n(n为 正整数)时,m=(用含n的代数式表示.) 三、解答题(本题共30分,每小题5分) 13.计算:() 1 01 π32sin45 8- ?? -?- ? ?? . 14.解不等式组: 43 42 1. x x x x -> ? ? +<-? ,

跟导师发邮件范文

跟导师发邮件范文 篇一:如何给导师写邮件--例文 尊敬的xx老师: 您好! 我叫xx,是兰州理工大学材料科学与工程学院08级本科生,专业是xxxx。我获得了本校20XX年推荐优秀应届本科毕业生免试攻读硕士学位研究生的资格,因此想进入贵校进行研究生学习。 我了解到您的研究方向是xxxxxxx。在本校老师讲解xxx时,我就对其很感兴趣,并认识到该焊接方法具有很大的发展前景。并从网上以及学长学姐得知您在该领域做了深入研究,因此非常希望成为您的研究生,在您的指导下进行深入学习。 以下是我的学习情况: 1、大学前三年的平均学分绩90,居专业第一(1/xx),综合测评成绩居专业第二(2/xx)。在20XX——20XX学年获得国家奖学金(2/xx)、校一等奖学金及校三好学生称号;在20XX——20XX学年获得国家励志奖学金、校一等奖学金及校三好学生称号。 2、在计算机方面,我通过了全国计算机二级、三级,并利用课余时间学习AutocAD、cAxA、solidworks绘图软件、photoshop图像处理软件,并系统深入的学习office等常用文档处理工具。 3、在英语方面,通过了四级(xx)、六级(xx),具备了一定的英语

听、说、读、写能力。 如果能有幸成为老师的研究生,我将踏实努力的完成您下达的任务。以下是我硕士期间的学习和研究计划: (一)专业知识的学习 1、扎实地学习专业知识,积极动手做实验,将知识和实践结合起来; 2、广泛阅读相关书籍,扩大自己在该领域的知识面。 (二)应用知识的学习 1、积极协助导师完成其科研和其他课题项目,扎实培养科学研究与创新能力; 2、加强英语特别是材料加工工程专业英语方面的自主学习,达到能自如地阅读、翻译专业相关英文学术论著,并力争自主进行英文论文的写作; 3、不断地学习需要的知识和技能。 学习计划会根据老师的具体要求以及自我认识的提高而做调整,以上只是初步计划。 我个人的特点: 1、喜欢制定明确的目标,并有很强的规划意识,并且在生活学习中朝着目标坚定不移的实施; 2、对自己要求严格,但我并不是一味的读书,也爱看看其他书籍(如经济、法律等),也注意学习与娱乐相结合; 3、喜欢独立思考,不懂的地方及时向老师寻求解答。 接下来,我将好好准备复试,冒昧的问老师,面试时主要考察哪些知

社会管理创新工作实施策略方案

社会管理创新工作实施策略方案 社会管理创新工作实施策略方案 根据《中共xx市委、xx市人民政府关于推进社会管理创新工作的决定》和《xx市社会管理创新工作方案》的具体要求,为切实做好社会管理创新工作,结合本单位工作实际,特制定本方案。 坚持以邓小平理论和“ ___”重要思想为指导,始终坚持“以人为本、服务为先”,深入贯彻落实科学发展观,紧紧围绕我市灾后重建和重返县域经济“十强”的战略目标,立足经济社会协调发展,深入探索社会服务管理新机制,全面提升社会管理能力水平,为促进xx经济社会在更高层次上又好又快发展作贡献。 根据市委、市政府的安排部署,积极配合各牵头单位和其他部门建立、健全社会服务管理机制。在招商引资工作基础上,进一步做好为投资企业的'服务工作,通过优质的服务,促进社会管理的管理更新、思路创新和体制机制革新。 (一)继续加强社会主义精神文明建设。 以建设社会主义核心价值体系为根本,加强理想信念教育、爱国主义教育和诚信教育、感恩教育等,通过参与市文明办组织的各项

活动,广泛宣传,以提高职工及群众的思想道德素质,并把精神文明建设的精髓贯彻到招商引资业务工作中去。 (二)协助完善 ___预防和化解机制。 稳定工作涉及到社会管理工作的各个方面,我们要推进科学决策、民主决策、依法决策,从源头上预防和减少矛盾发生,并建立健全社情民意调查机制,畅通群众表达渠道,有效维护人民群众合法权益。 (三)加强对经济组织和社会组织的服务管理。 努力探索新形势下对经济组织和社会组织服务管理的体制机制和方法手段,落实组织的内部安全稳定法人责任制及其社会责任,实现社会管理和公共服务全覆盖,推动在经济组织和社会组织中建立党团组织和工会组织,加强对贯彻法律法规的检查,加强对劳动者的人文关怀。 (四)通过招商引资业务工作,着力创新社会管理。 通过不断完善工作机制,打造“亲商、安商、富商”的招商引资软环境;加大对外宣传力度,包装优势项目;全力打造中国西部钣

加强和创新社会管理工作实施方案

加强和创新社会管理工作实施方案 为深入推进司法行政系统社会管理创新工作开展,根据区委、区政府关于加强和创新社会管理工作的总体要求和工作部署,结合司法行政工作实际,制定如下实施方案。 一、指导思想 以邓小平理论和“三个代表”重要思想为指导,深入贯彻落实科学发展观,牢牢把握“最大限度地激发社会创造活力、最大限度地增加和谐因素、最大限度地减少不和谐因素”的总体要求,以人民满意为最高标准,以解决群众“热点”、“难点”纠纷、创新社区矫正和安置帮教举措、拓展法律服务领域和推进依法治理进程为重点,充分发挥司法行政职能作用,全面提升司法行政工作社会管理创新的能力和水平,为“服务经济发展、打造平安古城、促进社会和谐”创造积极有利的环境。 二、工作目标 按照“一年打基础、两年上台阶、三年见成效”的要求,从人民群众最迫切的愿望出发,以解决影响社会和谐稳定的社会服务管理突出问题、薄弱环节和工作盲区为突破口,力争通过三年时间,建立健全社会管理相关制度,完善工作机制,创新工作体制,强化工作措施,实现人民调解、安置帮教和社区矫正、普法和依法治理、法律服务、法律援

助、公证等各项司法行政工作创新发展。三、基本原则——坚持科学发展的原则。把科学发展作为根本方针,以项目化、社会化理念加强和创新社会管理,实现社会发展与经济发展相协调。 ——坚持以人为本的原则。把以人为本作为出发点和落脚点,突出亲情化服务、人性化管理,不断实现好、维护好、发展好最广大人民的根本利益,使人民群众各项权益得到有效保障。 ——坚持固本强基的原则。把固本强基作为基本方略,大力加强基层基础工作,发展壮大基层组织,健全基层管理网络,创新基层社会管理体制机制,增强基层社会管理能力,夯实社会管理创新工作的根基。 ——坚持统筹协调的原则。把统筹协调作为重要方法,充分协调社会各方面的力量,统筹社会各种资源,统筹城乡区域,形成机制互联、功能互补、协作配合、齐抓共管的社会管理整体合力。 ——坚持民主参与的原则。把民主参与作为根本要求,扩大群众的有序参与,让人民群众参与到社会管理之中,形成推动社会和谐发展、保障社会安定有序的合力。 ——坚持依法治理的原则。把依法治理作为重要内容,增强法治意识,形成依法决策、依法行政、依法办事的正确导向,运用法律手段来规范和保障社会管理创新。

保研导师联系邮件模板

尊敬的*老师: 您好! 我是**,**大学**学院2006级**专业学生通过专业课老师和学长们的推荐介绍,我认真阅读了网页上的导师信息,了解相关情况,觉得自己对您的研究课题很感兴趣,非常希望能够有机会免试攻读您2010年的硕士研究生、得到老师的指点,所以就冒昧跟您联系了。以下是我的基本情况,请您过目。 三年以来,我认真学习各门课程,学绩点排名专业第一,专业课程和实验成绩均达到90分以上。同时我注重拓展自己的知识面,优化知识结构,具有了比较扎实的学习基础和较强的动手能力。所学主要课程有:***** 英语学习方面,我顺利通过了国家英语四六级考试,并通过六级口语考试,去年获得全国大学生英语竞赛三等奖,具有较好的英语学习能力。 科研兴趣培养方面,我参加了**,**学习了有关**的研究工作,在理论基础和实践能力方面得到了较大的提高。。此外,我参加过许多学术竞赛活动,如数学建模,节能减排竞赛,挑战杯等。在去年全国大学生数学建模竞赛中,我们组获得了河南省三等奖,节能减排作品获校级三等奖。 此外,我十分注重综合素质的培养,在**学院担任**期间锻炼了组织,管理和与人沟通的能力,多次参与组织了学院的团体比赛****并力争取得好的成绩,获得了老师和同学们的肯定。以上是我个人的一些基本情况,冒昧致信,恳请您海涵!非常感谢您能在百忙之中抽出时间阅信!学生期待您的回信。 祝老师身体健康!工作顺利! 学生:** 保研自荐信模板 ________________________________________ 保研自荐信怎么写?相信这是不少学子的疑问。为了令大家掌握如何写保研自荐信,以下整理了一则保研自荐信模板,仅供各位参考。 尊敬的教授: 您好!首先感谢您能够在百忙之中收阅我的自荐材料!以下是我的个人自我介绍:我叫张xx,是中国农业大学信息科学试验班一名04级学生,由于我们这个班级采用的是学分制教学管理模式,进一步完善选课制、导师制,这样我们可以在3年的时间里完成自己的本科学习任务。 两年的大学生活让我学到了许多,在知识的学习中,注重基础和实践的。我已经满足了学校保送免试研究生的资格,。我知道研究生必须选择好一个自己感兴趣的方向,当然还要有对这个领域的了解和认识而不仅仅成绩好。 我通过院领导和其他老师的推荐,我也在网上查了一下有关光电院的介绍,决定给您发这封邮件。我把自己的情况作一简要的说明,望您给予建议:想读您的研究生还应在哪个方面努力? 对于您的这个研究方向对数学的要求比较高,这一点我已经有准备。在《高等数学》.《线性代数》.《复变函数》.《离散数学》等基础课程学习中,夯实基础,进行拓展学习并取得了优异成绩。对于《英语》,四级以548分的成绩通过,六级虽成绩没出来,但对答案

2012年北京市中考数学及答案解析

2012年北京市高级中等学校招生考试数学 1A (满分:120分时间:120分钟) 第Ⅰ卷(选择题,共32分) 一、选择题(本题共32分,每小题4分) 下面各题均有四个选项,其中只有一个 ..是符合题意的. 1.-9的相反数是() A.-1 9B.1 9 C.-9 D.9 2.首届中国(北京)国际服务贸易交易会(京交会)于2012年6月1日闭幕,本届京交会期间签订的项目成交总金额达60110000000美元.将60110000000用科学记数法表示应为() A.6.011×109 B.60.11×109 C.6.011×1010 D.0.6011×1011 3.正十边形的每个外角等于() A.18° B.36° C.45° D.60° 4.如图是某个几何体的三视图,该几何体是() A.长方体 B.正方体 C.圆柱 D.三棱柱 5.班主任王老师将6份奖品分别放在6个完全相同的不透明礼盒中,准备将它们奖给小英等6位获“爱集体标兵”称号的同学.这些奖品中3份是学习文具,2份是科普读物,1份是科技馆通票.小英同学从中随机取一份奖品,恰好取到科普读物的概率是()

A.1 6B.1 3 C.1 2 D.2 3 6.如图,直线AB,CD交于点O,射线OM平分∠AOC,若∠BOD=76°,则∠BOM等于() A.38° B.104° C.142° D.144° 7.某课外小组的同学们在社会实践活动中调查了20户家庭某月的用电量,如下表所示: 用电量(度)120140160180200户数23672 则这20户家庭该月用电量的众数和中位数分别是() A.180,160 B.160,180 C.160,160 D.180,180 8.小翔在如图1所示的场地上匀速跑步,他从点A出发,沿箭头所示方向经过点B跑到点C, 共用时30秒.他的教练选择了一个固定的位置观察小翔的跑步过程.设小翔跑步的时间为t(单 位:秒),他与教练的距离为y(单位:米),表示y与t的函数关系的图象大致如图2所示,则这个固 定位置可能是图1中的() A.点M B.点N C.点P D.点Q 第Ⅱ卷(非选择题,共88分) 二、填空题(本题共16分,每小题4分) 9.分解因式:mn2+6mn+9m=.

环保所的创新工作方案

环保所的创新工作方案 导语:地球,是万物赖以生存的家园,是人类名副其实的母亲。过去的地球天空蔚蓝明净,群山青翠欲滴,河水清澈纯净,真是美丽壮观,和蔼可亲。可现在的地球呢?天空难寻昨日的蔚蓝,群山不见往日的青翠,河水流失昔日的清澈。与以前的地球相比,无疑是发生了翻天覆地的变化。以下是的资料,欢迎阅读参考。 根据乌审旗社管委办公室的要求,为确保我局社会管理创新工作的有序推进,取得成效,现特制定工作实施方案如下: 一、指导思想 以邓小平理论和“三个代表”重要思想为指导,深入贯彻落实科学发展观,紧紧围绕“跨越发展、富民强旗”的总体要求,着力解决影响我旗社会和谐稳定的源头性、根本性、基础性问题,构建“党委领导、政府负责、社会协同、公众参与”的社会建设和管理新格局,为我旗经济社会又好又快发展创造平安和谐稳定的社会环境。 二、工作目标 按照社会管理人性化,公共服务均等化、环保工作高效化的要求,切实把推进社会管理创新作为促进经济社会又好又快发展的保障工程、巩固党的执政地位的基础工程、维护广大人民群众根本利益的民心工程。通过深入研究社会管理规律,创新社会管理思路、方法和手段,进一步完善社会管理体系,提高社会管理效能,营造安全稳定的治安环境、公平竞争的经济环境、规范有序的法治环境、安居乐业的生活环境,为乌审旗跨越式发展打牢坚实基础。以全旗社会建设的

实际成效推动社会治安综合治理工作取得新进展,全面推进平安建设服务经济社会又好又快发展, 不仅使全旗的经济发展模式上升到一个新的层次,更使乌审旗迈向一条科学发展之路。 三、方法步骤 社会管理创新综合试点工作分准备动员、实施推进、查缺补漏和巩固提高四个阶段逐步推进。 第一阶段(20xx年5月30日—6月30日),制定方案,组织动员,成立工作领导小组,召开加强社会建设、创新社会管理工作动员大会,落实工作责任。 第二阶段(20xx年6月30日—7月30日),落实保障,实践探索。 第三阶段(20xx年7月30日—10月30日),攻坚克难,积极推进。针对加强社会建设、创新社会管理工作中的突出问题进行专题研究,有针对性地制定解决问题的方案,创新社会管理工作方法。 第四阶段(20xx年10月30日—12月30日),巩固完善,形成机制。认真分析研究新形势下加强社会建设、创新社会管理工作的规律特点,认真总结社会建设社会管理工作经验,建立健全长效机制,巩固试点工作成果。 四、试点工作组织保障和责任分工

联系导师邮件模板

考研成绩公布后联系导师的邮件模板 2015年考研成绩查询入口已陆续开通,个人认为一般在初试出分的时候联系导师比较合适。下面是小编搜集的几个模版,大家可以参考一下。需要注意,字也不能写得太少,那样显得很随意,更不能太多,那样导师根本没有时间看。把该说的都说清楚,就可以了。 模板(一) 尊敬的*老师:您好! 我叫***,是华中科技大学电子与信息工程系通信工程专业2004级本科生,通过贵所硕士招生信息介绍和师兄的推荐,我希望能够有机会免试攻读您2007年的硕士研究生,所以非常冒昧的给您写信。本科生期间我成绩优秀,三年来成绩一直名列班级第一,在全系也名列前茅(具体排名还未出来)。我刻苦学习,积极实践,在老师的精心培养以及大学良好的学术氛围的影响下,我在基础知识,设计实验,操作能力等方面积累了一定的经验,为读研打下坚实的基础。附件中是我的个人简历和大学三年来的学习成绩表,恳请您能多花几分钟看一看。我在网上查阅了您的有关资料,并看了些您发表的文章。我对您所研究的课题很感兴趣,所以非常希望能在您的课题组攻读我的硕士学位,我相信通过自己的努力,我能很好的完成硕士期间的任务。冒昧致信,恳请您海涵! 非常感谢您能在百忙之中抽出时间阅信! 祝身体健康! 工作愉快! 学生:*** 模板(二) 敬爱的宋老师: 您好! 我叫XXX,是XXX车辆工程2006级本科生。早在大二末我的科任老师(XXX老师)就向我介绍过您,说您在主动安全和汽车动力学CAE领域是我国学术带头人。当时我就下定决心一定要发奋努力、刻苦学习争取做您的学生!也一直追求着!本学期通过04级保送至贵院的两位学长介绍,更加坚定了我的信念。真诚地希望能免试攻读您2010级的硕士研究生,所以非常冒昧地给您写信,万分感激您在百忙之中来阅读我的邮件!谢谢!!! 进大学以来我就很刻苦学习、基础知识扎实,养成了较强的学习、科研及动手能力,期间我的成绩和综合能力都很优秀。①加权大一年级(2/452)(大一末以电气工程年级第二名转入车辆工程)、前五学期本专业(4/156),综合排名第一。②已获得多项学科竞赛及科技论文竞赛奖项(国际1项(美国国际数学建模竞赛二等奖)、国家及地区1项、省级3项、校级7项)且多次获得国家奖学金、校级甲等奖学金及三好学生称号,特别擅长数学建模、物理和力学。③在科研和社会实践方面都取得了优秀的成果,参与湖南大学节能赛车设计和机械创新设计大赛,科研项目获国家级SIT项目,在第十一届“挑战杯”全国大学生课外学术科技作品竞赛中其作品“基于快速成型石蜡基高强度渗入材料的研究及应用”在校级决赛中获二等奖(排名第二)。④社会实践论文在省级、校级多次获奖。附件中是我的简历、主要成果及摘要和前五学期的成绩分类汇总。恳请您能多用些时间阅览一下,再次表示最诚挚的感激!!!如果可以请问能否在暑假亲自去北京拜访您? 冒昧来信,敬请海涵。学生期待您的回信,谢谢!万分感激!!! 此致 敬礼 祝愿身体健康,工作顺利! 学生:XXX 模板(三) 老师,您好! 尊敬的田老师:您好! 我叫XXX,是XX大学XX学院XX专业2006级本科生。我

2012年北京市中考数学试题与答案

2012年北京市高级中等学校招生考试 数学试卷 学校姓名准考证号一、选择题(本题共32分,每小题4分) 下面各题均有四个选项,其中只有一个是符合题意的. 1.9-的相反数是 A. 1 9 -B. 1 9 C.9-D.9 2.首届中国(北京)国际服务贸易交易会(京交会)于2012年6月1日闭幕,本届京交会期间签订的项目成交总金额达60 110 000 000美元,将60 110 000 000用科学记数法表示应为 A.9 6.01110 ?B.9 60.1110 ?C.10 6.01110 ?D.11 0.601110 ?3.正十边形的每个外角等于 A.18?B.36? C.45?D.60? 4.右图是某个几何体的三视图,该几何体是 A.长方体 B.正方体 C.圆柱 D.三棱柱 5.班主任王老师将6份奖品分别放在6个完全相同的不透明礼盒中,准备将它们奖给小英等6位获“爱集体标兵”称号的同学.这些奖品中3份是学习文具,2份是科普读物,1份是科技馆通票.小英同学从中随机取一份奖品,恰好取到科普读物的概率是 A.1 6 B. 1 3 C. 1 2 D. 2 3 6.如图,直线AB,CD交于点O,射线OM平分AOC ∠,若76 BOD ∠=?, 则BOM ∠等于 A.38?B.104? C.142?D.144? 7.某课外小组的同学们在社会实践活动中调查了20户家庭某月的用电量,如下表所示:用电量(度)120 140 160 180 200 户数 2 3 6 7 2 则这20户家庭该月用电量的众数和中位数分别是 A.180,160 B.160,180 C.160,160 D.180,180

社区社会管理创新工作实施方案

肖家村社会管理创新工作实施方案 为大力推进社会管理创新,切实维护社会和谐稳定,推动我社区社会建设工作取得新进展、新成效。根据《建国街道社会管理创新工作实施方案》的要求,结合我社区实际,制定如下实施方案。 一、指导思想 坚持以邓小平理论和“三个代表”重要思想为指导,以创先争优活动为契机,探索社会服务管理新模式、新机制和新举措,全面提升社区社会服务管理水平,促进社区各项工作又好又快发展。 二、工作目标针对社会管理中影响社会和谐稳定的突出问题、薄弱环节和工作盲区,围绕社会矛盾化解,特殊人群服务管理、社会治安重点地区排查整治、综治维稳基层基础建设、“两新组织”服务管理等工作,探索社会管理创新工作,理顺工作体制,健全工作机制,强化工作措施,形成与社会主义市场经济体制相适应的社会管理体系,实现对流动人口、特殊群体和矛盾排查、化解的一体化、常态化规范化管理,促进经济社会又好又快发展,维护社会和谐稳定。 三、成立工作领导小组 为确保社会管理创新工作取得实效,我村成立由书记任组长,主任任副组长,村委会工作人员为成员的社会管理创新综合试点工作领导小组。

四、主要内容 (一)创新社会管理体系,切实提高社会建设和社会管理水平。 1、创新和加强科学化的社会服务管理体系。(1)建立社会管理、综合治理、矛盾化解、维护稳定四位一体的工作平台,实行集中办公。(2)在本社区综治维稳工作站的统一指挥下,按照其职责范围,负责相关工作开展。 2、创新和加强立体化的社会治安防控体系。 (1)制定治安重点地区整体发展规划,社区要把社会治安重点地区特别是流动人口居住集中地管理、基础设施建设、环境整治、公共服务纳入辖区社会发展整体规划,制定具体规划方案。 (2)建立社会治安重点地区,治安突出问题滚动排查整治机制。定期开展治安隐患大排查,摸清底数,分析梳理治安突出问题,制定整治方案。 (3)加强公共突发事件预防处置机制建设。建立完善应急处置队伍,防范处置预案和指挥机制。 (4)健全完善公共安全监管机制,健全完善安全制度、措施和监管机制,抓好辖区各类企业的安全生产工作,定期、不定期开展安全检查工作。 (二)创新和加强规范化的重点人员管理体系,规范建立各级人口管理体系。

复试选导师--教你如何联系导师(附邮件模板)

考研初试成绩即将公布了,大家都要准备联系导师的事情了,在这里,我给大家一些建议。粗略地说,主要包括4个方面:导师的经历、当下的工作状况、学术研究情况、师生相处情况。 导师的经历主要是指导师的籍贯、学习经历、工作经历;当下工作状况主要是指职称、是否兼有行政职务;学术研究情况是指导师出版的著作、发表的文章、在其研究领域的学术立场、学术研究风格;师生相处情况指导师对学生的态度、原则、要求以及日常交往情况,甚至导师生活中的某些个人喜好等等,这些情况主要从日常教学和师生交往(尤其是节庆日公共活动)中了解。 在这4个方面中,“经历和当下工作状况”是基本性的信息,而核心信息是“学术研究情况和师生相处情况”――前者关乎你的备考(尤其是复试)乃至将来读研后的学习,也是打开我们与导师沟通或关系之门的钥匙;后者则直接关乎导师处理与学生关系的原则与方式,其重要性也不言而喻。 如何获得这些导师的这些信息呢 途径一:通过学校的官方网站查询导师的简介

2014-2-19 16:06 上传 下载附件 (49.97 KB) 途径二:通过专业学术网站 学术网站或者图书馆搜寻导师的著作与文章。学习研究这些文章,以了解导师的学术研究情况。很多导师的课题论文较多发布到国外期刊,也要注意搜集~比如中国知网,点击链接-> https://www.360docs.net/doc/2b8853307.html,/kns/brief/default_result.aspx

途径三:直接与导师接触(注意方式方法!!) 如果你居住在所报考学校的城市,可以抽时间去听导师的课,甚至可以利用课后的时间争取与导师交流沟通,这是最直接地了解导师的好方法。比如可以去学校看相关公告,导师的讲座之类,如果导师让你复试的时候面谈,那么是最佳的接触机会。 途径四:通过你周围的人

社会管理创新项目方案

社会管理创新项目方案 一、项目名称 老子山镇法治建设进湖区系列活动 二、指导思想 以邓小平理论和“三个代表”重要思想为指导,深入贯彻落实科学发展观,认真贯彻落实省、市、县社会管理工作会议精神,创新社会服务管理理念、政策体系、体制机制和方法手段,全面提升社会管理创新的能力水平,切实解决影响社会和谐稳定的源头性、根本性、基本性问题,为实现我镇十二五目标,创建平安老子山,营造良好的社会环境和良好的发展环境 三、工作目标 通过开展社会管理创新工作,进一步建立健全党委领导、政府负责,社会协调、公众参与的社会管理格局,保持全镇社会稳定,群众安居乐业,实现我镇社会管理网络更加健全,服务更加到位,管理更加有序,信息更加通畅,基础更加扎实。 四、具体措施 1.加强组织领导。各行政村要把社会管理创新纳入全局工作之中,用抓经济建设的劲头抓社会管理创新工作,明确目标任务,周密制定方案,严密组织实施。要建立党支部、村委会领导、综治工作站牵头、相关责任人具体负责的领导机制,成立专门工作班子,明确专人负责,确保落到实处。 2.强化部门联动。各相关部门特别是镇综治委成员单位,既要履行好自身职责,又要加强协作配合,形成对社会管理齐抓共管的合

力。要结合开展综治联系点工作,深入基层加强督促指导,及时总结成功的经验,帮助解决存在的问题。 3.加大保障力度。要以抓项目建设的方法抓社会管理,将社会管理工作纳入经济社会发展总体规划,纳入本地的整体工作部署。这些规划和项目一经确定,必须逐一分解细化,把目标责任落实到具体部门、单位和责任人,确保取得预期的效果。要强化保障措施,加大人财物的投入,加强对经济薄弱村的扶持,确保有人干事、有钱办事。 4.注重典型示范。要注重典型的培育树立,加强典型宣传,充分发挥典型的示范带动作用。特别是对那些有效解决体制性、机制性、保障性问题的成功经验,要多渠道地做好学习推广工作,使之在创新社会管理工作中真正发挥示范引领作用。要着眼于满足群众需要、提高工作实效,注重规范建设,把握核心内涵,防止和克服形式主义。 5.抓好督查考核。要建立健全创新社会管理工作责任制和督促检查机制、考核奖惩机制,确保各项工作措施的落实。要把创新社会管理工作及其成效作为社会治安综合治理目标管理责任制考核的重要内容,适时组织专项督查,加大检查考核力度,及时通报有关情况,推动工作落实。 五、项目内容 1、法律知识进湖区讲座。 镇政法委牵头,协调组织镇综治办、信访办、派出所、司法所、法律服务所、工商所、计生办、农技推广中心等部门深入开展涉农涉渔法律知识进湖区宣传教育活动。 2、法治建设征文展

2019年联系导师的邮件范文

2019年联系导师的邮件范文 篇一:复试前联系导师的邮件怎么写? 复试前联系导师的邮件怎么写?复试前联系导师的邮件写作方式 第一次发邮件给老师,建议是既要介绍自己的基本状况,又要简明扼要。信中要介绍自己报考的专业方向,自己的分数,以及自己本科学的什么专业,本硕是否一致,以及对报考院系级导师的向往等等。也可以继续写,或者等老师回信后,介绍下自己本科时学习过的和专业相关的课程,以及对专业学习做过哪些准备,自己看过哪些关于报考专业方面的书和专著,同时表示自己这方面书看的太少,有待提高。同时对老师的回复表示感谢。以下是笔者在复试前给导师发的邮件,在这里给大家作参考(部分被省略): 第一次发邮件 X老师,您好: 我是今年报XX院系XX方向的学生。我的分数是英语XX,政治XX,数学XX,专业课XX,总分XXX分。我的本科是XXXXXX就读,专业XXX。因为我对XXX比较有着浓厚的兴趣,对XXX(目标院校)有着向往,所以在考研阶段选择XXX学院的XX学科。我也看过您的一些

学术论文与论著,对您的学术水平非常钦佩。不知道我这个分数是否有望进入复试,有幸成为您的学生呢? 报考学生XX20XX年XX月XX日 老师回信介绍了学校专业的具体情况,说跨专业没关系,并表示会帮助我问一下排名 X老师您好: 感谢老师的细心回答,通过老师的解读,我对于XX系有了更深层次的了解。我在本科期间也有选修XXX、XXX等相关专业方面的课程,因为我的本科学XX方面课程较少,我还XX大学等学XX学院的课做过旁听。以前就读过《XXX》、 《XXXX》等书籍。大学的时候有读过XXX先生的《XXXXXX》,XXX 先生的《XXXX》等书。最近一年还看XXXX出版社出版的XXXXXXX》,还有一些相关论文。深感XX方面的著作自己还读之甚少,希望有机会能得到老师您的指教。学生谢谢老师您的解答,您辛苦了,若有机会,非常希望能有有机会在未来能成为您的学生! 篇二:研究生联系导师的邮件模板华

相关文档
最新文档