调试方案 commissioning (中英文双语版)

调试方案 commissioning (中英文双语版)
调试方案 commissioning (中英文双语版)

3.14 Single-machine commissioning, system commissioning and joint commissioning

3.14 单机调试、系统调试、联动调试

3.1

4.1 Overall plan of commissioning

3.1

4.1 调试总体策划

Commissioning work is divided into three stages, which is shown in the figure 3.14.1-1.

调试工作分为三个阶段,见图3.14.1-1。

Figure 3.14.1-1 Commissioning work

图3.14.1-1 调试工作

Commissioning work of the project mainly includes implementation and management of commissioning of HVAC works, commissioning of electrical works, commissioning of plumbing as well as commissioning of fire fighting works.

本工程系调试工作主要包括通风空调工程调试、电气工程调试、给排水及消防工程调试实施及管理工作。

1. Commissioning indispensable conditions are shown in the table 3.14.1-1.

1、调试具备条件见表3.14.1-1。

Table 3.14.1-1 Commissioning indispensable conditions

表3.14.1-1 调试具备条件

No.序号Name of

system

系统名称

Preparatory work before commissioning

调试前的准备工作

1 Electrical

system

电气系统

Installation of electrical equipment is completed. Laying of bridge, medium

& low voltage cables and busbar is completed; wiring of secondary control

cables is right as per drawings. Installation of power and lighting

switchboard is completed; installation and wiring of power equipment are

completed; appearance check is qualified. Wiring of various lamps is

completed. Wiring of various switch panels is completed.

电气设备安装完毕。桥架及中、低压电缆、母线敷设完毕,二次控制电缆按

图纸接线正确。动力、照明配电盘安装完毕,动力设备安装、接线完毕,外

观检查合格。各种灯具接线完成,各种开关面板接线完毕。

2 HVAC system

通风空调系统

Stable power supply for air conditioning ventilating equipment, duct purging

is qualified. Stable power supply for air conditioning water system, system

flushing is qualified; hydraulic pressure of the system meets requirements;

valve is turned on and turned off normally.

空调风系统设备供电稳定,风管吹扫合格。空调水系统设备供电稳定,系统

冲洗合格;系统水压满足要求,阀门启闭正常。

3

System of

plumbing as

well as fire

fighting

给排水及

消防系统

Connection of equipment and pipeline is correct, it shall check

completeness before equipment operates, hydraulic pressure test of pipe

system and circulating flushing work of system have been completed.

设备和管道连接准确,设备运行前应进行完整性检查,管道系统水压试验与

系统循环清洗工作已经完毕。

2. Organization measures of commissioning

2、调试的组织措施

(1)Organization chart of commissioning is shown in the figure 3.14.1-2.

(1)调试的组织机构见图3.14.1-2。

Figure 3.14.1-2 Chart of commissioning organization

图3.14.1-2 调试组织机构图

(2)Responsibilities of main personnel for project commissioning are shown in the table 3.14.1-2.

(2)项目调试主要人员职责见表3.14.1-2。

Table 3.14.1-2 Responsibilities of main personnel for project commissioning

表3.14.1-2 项目调试主要人员职责

No. 序号Post

职务

Acting

personnel

担任人员

Responsibilities

职责

1 Team leader

组长

Project

manager

项目经理

Be responsible for establishment of commissioning

organization, preparation of resources used in

commissioning, establishment and implementation of

commissioning working system, coordination between

MEP and other subcontractor at the stage of joint

commissioning.

负责调试机构的建立,调试需用资源的配备;负责调试工

作制度的建立实施,联动调试阶段机电与其他分包间的协

调。

2 Deputy team Technical Be responsible for compilation and submission of

No. 序号

Post

职务

Acting

personnel

担任人员

Responsibilities

职责

leader

副组长

director of the

project

项目技术

负责人

organization commissioning method statement,

coordination and communication with related parties as

well as management, coordination and cooperation in

various commissioning work between the Owner ABB,

Lend Lease Company and relevant director of the

supervision unit and all other subcontractors; analyze

and summarize commissioning result.

负责组织调试方案的编制和报审,与外部相关方的协调与

沟通,与业主ABB、联实公司及监理单位相关负责人和其

他各分包单位各项调试工作的管理、协调与配合。对调试

结果进行分析和技术总结。

3 Group leader of

all disciplines

专业

小组长

Professional

engineer of

commissioning

调试专业

工程师

Be responsible for compilation of commissioning method

statement and standard operation procedures for this

area; safety and technical disclosure about

commissioning work of this area; make solutions for

difficult problems discovered in commissioning in the

area of this discipline; ensure safety and reliability of

instruments used in the commissioning of this area;

implement the commissioning schedule of the area,

organizing to collate commissioning materials and issuing

commissioning report.

负责本区域调试方案和作业指导书的编制;本专业本区域

调试工作的安全、施工技术交底;负责本专业本区域调试

过程中发现疑难问题的解决方案;负责本专业本区域调试

所使用的仪器、仪表的安全和可靠性;负责本专业本区域

调试进度计划的落实,组织整理调试资料并出具调试报告。

4 Group leader of

resource

guarantee

资源保障小组长

Material

guarantee

personnel

物资保障人员

Be responsible for providing commissioning materials.

负责提供调试所需物资。

5

Group leader of

emergency

handling

应急处理小组长

Professional

engineer

专业工程师

Be responsible for handling emergencies occurred in the

process of commissioning.

负责调试过程中出现应急情况的处理。

(3)Instrument and equipment used in commissioning are shown in “5.2 Guarantee

measures for input of construction machinery equipment”.

(3)调试所使用的仪器设备详见“7.2 施工机械设备投入保证措施”。

3. Commissioning process is shown in the figure 3.1

4.1-3.

3、调试流程见图3.14.1-3。

Figure 3.14.1-3 Commissioning process chart

图3.14.1-3 调试流程图

3.1

4.2 Single-machine commissioning

3.1

4.2 单机调试

1. Main contents and requirements of single-machine commissioning of all disciplines are shown in the table 3.14.2-1.

1、各专业单机调试的主要内容和要求见表3.14.2-1。

Table 3.14.2-1 Contents and requirements of

single-machine commissioning and system commissioning

表3.14.2-1 单机调试和系统调试内容和要求

No.序号Name of

discipline

专业名称

Contents of single-machine

commissioning

单机调试内容

Commissioning requirements

调试的要求

1 Electrical

system

project

电气系统

工程

power cable, low voltage breaker,

meters, UPSs, current transformers,

SPD, power/lighting distribution

panels, AC motors.

电力电缆、低压断路器、表、UPS、

电流互感器、避雷器、动力/照明配电

箱、交流电动机。

Performances of electrical device

meet requirements of design and

production process.

电气装置的性能满足设计和生产工艺

要求。

2 Project of

HVAC

system

空调通风

系统工程

Single-machine commissioning of air

conditioning equipment (fan, air

conditioning unit, water pump, FCU)

and smoke control unit; balance of

HVAC system, water balance of air

conditioning water system;

measurement of environmental

temperature, humidity and noise; test

of forced draft, blast capacity and

wind pressure of smoke control

system.

空调设备(风机、空调机组、水泵、FCU)

防排烟机组单机调试;空调风系统平

衡、空调水系统水量平衡;环境温度、

湿度、噪声测量;正压送风、防排烟系

统风量、风压测试。

Deviations of total blast capacity and

water flow of air conditioning unit

meet requirements of the

specification; indoor temperature,

relative humidity and noise meet

requirements of design and

specifications.

总风量、空调机组水流量偏差满足规范

要求;室内温度、相对湿度及噪声满足

设计及规范要求。

3

Project of

plumbing

and fire

fighting

system

给排水及

消防系统

工程

Single machine commissioning of

domestic water supply pump, fire

pump and drainage pump;

commissioning of water supply

system, drainage (rainwater) system

and firefighting water system.

生活给水泵、消防水泵、排水泵等设备

单机调试;给水系统、排水(雨水) 系

统、消防水系统调试。

Flow and pressure of water supply

and firefighting water system meet

use requirements. Smooth drainage,

non-leakage, installation of water

pump and valve comply with

requirements.

给水、消防水系统流量及压力等满足使

用要求,排水顺畅、无渗漏,水泵、水

阀安装符合要求。

2. Method of single-machine commissioning of main equipment:

2、主要设备的单机调试方法:

(1)Power cable: 1)measure insulating resistance; 2)DC voltage withstand test and measurement of leakage current; 3)AC voltage withstand test; 4)measure ratio of resistance of metallic shield layer and conductor resistance; 5)check phase positions of two ends of cable line; 6)cross interconnection system test.

(1)电力电缆:1)测量绝缘电阻;2)直流耐压试验及泄漏电流测量;3)交流耐压试验;4)测量金属屏蔽层电阻和导体电阻比;5)检查电缆线路两端的相位;6)交叉互联系统试验。

(2)Low voltage breaker: 1)measure insulating resistance; 2)breaking-closing test; 3)adjustment of switch setting values.

(2)低压断路器:1)测试绝缘电阻;2)分合闸试验;3)开关整定值的调整。

(3)Meter: conduct precision calibration for instrument on the plate cabinet by using standard meter.

(3)表:用标准表对盘柜上的仪表进行精度校验。

(4)Current transformer: 1)measure insulating resistance of the winding; 2)check wiring group and polarity; 3)error measurement.

(4)电流互感器:1)测量绕组的绝缘电阻;2)检查接线组别和极性;3)误差测量。

(5)SPD: commissioning as per technical specification of the manufacturer.

(5)避雷器:按生产厂家技术说明进行调试。

(6)Power/lighting switchboard:

(6)动力/照明配电盘:

1)Check insulation of switch and primary & secondary circuit in the power supply loop in the cabinet by using 1000V or 500V tramegger; insulating resistance complies with requirements of the specification;

1)采用1000V或500V兆欧表对箱内供电回路开关,一次、二次线路进行绝缘检查,绝缘电阻符合规范要求;

2)Check air switch in the cabinet by using universal meter, whether its switching off and switching on are normal or not; check whether connection of primary circuit and secondary circuit complies with design requirements or not; whether the connection of wire, cable, guide line and terminal is solid or not.

2)用万用表检查柜箱内空气开关,其开关分、合闸是否正常;检查一次、二次线路

接线符合设计要求;电线、电缆、导线和端子连接是否紧固;

3)Shall calibrate precision of amperemeter or voltmeter on the switchboard.

3)应对配电盘上电流表或电压表进行精度校验。

(7)AC motor: check of motor insulation, measure DC resistance of the winding; check the correctness of stator winding and its connection; check and test of control system of the motor; if it is normal through check, the motor shall be operated for two hours with no load; use thermodetector to measure temperature of stator winding of the bearing of the motor, check whether the temperature rise in motor is normal or not.

(7)交流电动机:电动机绝缘检查,绕组的直流电阻测量,检查定子绕组及其连接的正确性,电动机控制系统检查试验,检查正常后电动机空载运行2小时,用测温仪测量电动机轴承定子绕组等部位的温度,检查电机温升是否正常。

(8)Fan: rotate the impeller by hands, observe whether there are jamming and collision phenomenon or not; start fan, check whether there is friction, abnormal vibration and noise between impeller and enclosure or not; check whether rotating direction is consistent with the direction marked on the enclosure or not. After the fan operates stably, measure starting current, operation current, vibration, revolving speed, noise and bearing temperature of the fan;

(8)风机:用手盘动叶轮,观察有无卡阻及碰擦现象;风机点动,检查叶轮与机壳有无摩擦、有无异常振动及声响;检查运转方向是否与机壳标注方向一致。风机启动运转平稳后,测量风机起动电流,运转电流、振动、转速、噪声及轴承温度。

3.1

4.3 System commissioning

3.1

4.3 系统调试

1. Commissioning of electrical system work

1、电气系统工程的调试

(1)Commissioning process of electrical system work

(1)电气系统工程调试流程

Figure 3.14.3-11 Commissioning process of electrical system work

图3.14.3-1 电气系统工程调试流程

(2)Commissioning contents of electric transformation and distribution system (2)变配电系统调试内容:

1)Sanitation clearing: clear sundries on site away, clean all equipment.

1)卫生清理:清理现场杂物,将所有设备打扫干净。

2)Comprehensively check equipment:

2)设备进行全面检查:

①Check whether connecting bolts of equipment and components including busbar, transformer, arrester, capacitor and transformer are prepared and fastened or not;

①检查母线、互感器、避雷器、电容器、变压器等设备元件的连接螺栓是否按要配齐上紧;

②Check whether the grounding of auxiliary equipment such as low voltage cabinet complies with design requirements or not;

②检查低压柜等的附属设备的接地是否设置符合设计要求;

③Check whether all operating mechanisms are flexible or not; whether there is not blockage phenomenon or not;

③检查所有操动机构是否动作灵活,无阻滞现象;

④Check whether interlocks and interacting mechanisms of switch cabinets of all loads rotate flexibly and reliably or not;

④检查所有负荷开关柜的联锁、互动机构是否转动灵活、可靠;

⑤Temporary power supply in all distribution boxes shall be dismantled; its original design circuit shall be recovered;

⑤所有配电柜中的临时电源应全部拆除,并恢复其原设计线路;

⑥Insulation of all equipment and circuits complies with requirements of the specification;

⑥各设备、回路绝缘符合规范要求;

⑦System test can be conducted after all single inspection of components in all electrical devices is qualified, calibration of all instrument is qualified, all integrated relay protection has been set and adjusted, wiring of all primary loops and secondary loops is connected.

⑦系统试验在全部电气配置元件检查各单体检验合格;各配置仪表校验合格;各综合继电保护按照要求整定完毕,各一次回路、二次回路接线全部连接好后方可进行。

3)System test:

3)系统试验:

①Check whether indicating and monitoring elements, operation & control elements of all plate faces, cabinet faces and panel faces of the system are enough or not, whether they are damaged or not; if any damage, it shall be supplemented or replaced with electrical elements with the same model in time;

①检查该系统中所有盘面、柜面、板面的指示、监视元件及操作、控制元件是否配备齐全,有无损坏现象,如有及时用同型号的电气元件补齐或更换;

②Confirm that closing and opening switches, energy storage switch, power switch, control switch and power switch of all plate faces, cabinet faces and panel faces of the system are located in opening position;

②确认系统中所有盘面、柜面、板面的分合闸开关、储能开关、电源切换开关、控制开关、电源开关处于分闸位置;

③It shall conduct simulation test of interlocking and double switching in accordance with design requirements if the system is a electric transformer and distribution system which is supplying power for two circuits, operating in sections and backup of each other.

③对于系统为两路供电、分段运行、互为备用的变配电系统,应按其设计要求进行

互锁互投的模拟试验。

4)Test of temperature protection device, high temperature alarm of transformer and over-temperature trip

4)温度保护装置试验变压器高温报警和超温跳闸。

(3)Commissioning of power/lighting system

(3)动力/照明系统的调试

Commissioning contents are shown in the table 3.14.3-1.

调试内容见表3.14.3-1。

Table 3.14.3-1 Commissioning contents of power/lighting distribution system

表3.14.3-1 动力/照明配电系统调试内容

No. 序号Item

项目

Commissioning contents of power system

动力系统调试内容

1 Check before

commissioning

调试前检查

(1)Check whether various power/lighting switchboards have cut off

power supply or not.

(1)检查各种动力/照明配电盘是否已全部切断电源。

(2)Recheck whether the test of components of all power/lighting

accessories such as busbar, cable, motor and lamps is qualified or not

and whether its wiring is correct or not.

(2)再检查各动力/照明配件组成部分如:母线、电缆、电动机、灯具等,

是否测试合格及接线准确。

2 Commissioning

of

power/lighting

switchboard

动力/照明配电

盘调试

(1)Divide the project into various independent commissioning areas as

per system and areas controlled by switchboard.

将本工程按系统、按配电盘控制的区域分成各自独立的调试区域。

(2)All power/lighting switchboards adopt temporary power supply to

conduct closing and opening test for main switch and separating switch of

the switchboard, check whether closing and opening of all switchboard

switches are normal or not.

(2)所有动力/照明配电盘,采用临时电源对配电盘总开关、分开关进行分

合闸试验,检查各配电盘开关分合是否正常。

3 Commissioning

of overall

power

transmission

总体送电调试

(1)After sub-system in different areas of all sections have finished

commissioning, it shall conduct overall power transmission operation

commissioning, it shall cut off switches of power/lighting control panel in

different areas; and then supply power for power /lighting main line

cables.

(1)所有分段分区域分系统调试完后,进行总体送电运行调试,先切断各

区的动力/照明控制盘开关;然后对动力/照明主干线电缆送电。

(2)Conduct switchover commissioning for the dual power system to

guarantee switchover of dual power system is normal.

(2)对双电源系统做切换调试,确保双电源系统切换正常。

4 Commissioning

records

调试记录

Make commissioning records when commissioning.

在调试的同时作好调试记录。

(4)Commissioning contents of lightning protection and grounding system are shown in the table 3.14.3-2.

(4)防雷接地系统调试内容见表3.14.3-2。

Table 3.14.3-2 Commissioning of grounding resistance and equipotential grounding system

表3.14.3-2 接地电阻及等电位接地系统调试

No. 序号Name of

system

系统名称

Type

种类

Commissioning content

调试内容

1 Lightning

protection

system

防雷系统

Flank thunder prevention, direct

lightning prevention, inductive

thunder prevention

防侧击雷、防直击雷、防感应雷

(1)Test of grounding resistance.

(1)接地电阻测试。

(2)Commissioning of surge protective

device.

(2)浪涌保护器调试。

Electromagnetic pulse

prevention (overvoltage

protection)

防电磁脉冲(过电压保护)

2 Grounding

system

接地系统

Medium voltage and low voltage

power supply grounding system

中压、低压供电接地系统

Neutral ground system of

generator发电机中性点接地系统

Grounding system of telecom

and computer equipment

电信及计算机设备接地系统

Weak current system grounding

弱电系统接地

3

Equipotenti

al

connection

等电位连接

Various transformer substation

room, auxiliary room of

equipment, metal pipe and metal

matter

各变配电房、设备机房辅助用房、

金属管道及金属物

(1)Calibration of wire resistance;

(1)线阻校验;

(2)Single-point measurement

(2)单点测量。

(6)Commissioning of automatic fire alarm system

(6)火灾自动报警系统调试

1)System overview

1)系统概述

Automatic fire alarm system of the project is centralized alarm system. The system

is composed of the following parts: automatic fire alarm system, linkage command control system, gas fire extinguishing control system, elevator monitoring system, fire emergency broadcasting system, telephone system special used for firefighting control, electrical fire monitoring system, firefighting power monitoring system, firefighting door monitoring system, emergency lighting and firefighting system grounding.

本项目火灾自动报警系统为集中报警系统。系统由以下几部分组成:火灾自动报警系

统、消防联动控制系统、气体灭火控制系统、电梯监视系统、消防应急广播系统、消防专用电话系统、电气火灾监控系统、消防电源监控系统、防火门监控系统、应急照明及消防系统接地。

2)Commissioning contents are shown in the table 3.14.3-3.

2)调试内容见表3.14.3-3。

Table 3.14.3-3 Commissioning contents of automatic fire alarm system

表3.14.3-3 火灾自动报警系统调试内容

No. 序号Item

项目

Commissioning contents

调试内容

1 Commissioning

conditions

调试条件

Commissioning of fire emergency lighting evacuation and indication

system shall be conducted after system construction has been

completed. It shall compile commissioning procedures and work as per

commissioning procedure before commissioning.

消防应急照明疏散指示系统的调试,应在系统施工结束后进行。调试前应

编制调试程序,并按调试程序工作。

2 Preparation before

commissioning

调试前准备

Model, specification, quantity, spare parts and accessories of

equipment shall be inspected as per design requirements.

设备的规格、型号、数量、备品、备件应按设计要求检验。

3 Loop check

回路检查

Connect and open single loop, test situation of power on and

communication of every loop.

分次逐一连接开通单条回路,测试每个回路的通电、通讯情况。

4 Equipment check

设备检查

Emergency lighting controller and emergency lighting switchboard shall

conduct single machine power on check respectively.

应急照明控制器,应急照明配电盘分别进行单机通电检查。

5

Check of

identification lamp

of emergency fire

fighting

应急消防

标志灯检查

Check whether installation positions of all emergency fire identification

lamps and arrow indication directions of mark information comply with

actual evacuation direction or not.

检查所有应急消防标志灯安装位置和标志信息上的箭头指示方向是否与

实体疏散方向相符。

6

Check of light

stream direction

光流导向检查

Transfer identification lamps that shall form oriented light stream into

emergency working state, its light stream direction is the same to

evacuation direction of the design.

使顺序闪亮形成导向光流的标志灯转入应急工作状态,其光流导向与设计

的疏散方向相同。

7

Power supply

conversion test

电源转换试验

Cut off emergency switchboard one by one, whether the switchboard

has been transferred into emergency working state within 5s.

逐个切断应急配电盘,该配电盘是否在5s内转入应急工作状态。

8 Linkage test

联动试验

Check whether fire emergency lighting and evacuation indicating

system have been transferred into corresponding working state within

No. 序号Item

项目

Commissioning contents

调试内容

5s and send linkage feedback signal after inputting simulation signal.

消防应急照明和疏散指示系统,在模拟信号输入后,是否在5s内转入相

对应的工作状态,并发出联动反馈信号。

9 Test of component

parameters

元器件参数检测

Check whether various technical indexes of centralized power supply of

emergency lighting comply with product requirements under the

condition of emergency state or when master power supply operates.

检查在主电工作和应急工作状态下,应急照明集中电源各项技术指标是否

符合产品要求。

10

Test of control

functions of

operation system

操作系统

控制功能检测

Check whether status indication of emergency lighting control and

shifting time are normal or not.

检查应急照明控制状态指示和转入时间是否正常。

11 Fault detection

故障检测

Check whether acoustic-optic failure signal of emergency lighting

controller and display at failure part are normal or not.

检查应急照明控制器声光故障信号及故障部位显示是否正常。

12 Detection of spare

power supply

备用电源检测

Check whether working time of standby power supply meets design

requirements or not.

检查备用电源的工作时间是否满足设计要求。

13 Detection of closing

main program

关闭主程序检测

Close master program of the controller, check whether the system is

transferred into emergency state as per the design requirement or not.

关闭控制器主程序,检查系统是否按设计要求转入应急工作状态。

2. Commissioning of the project of HVAC system

2、空调通风系统工程调试

(1)Commissioning process of the project of HVAC system is shown in the figure 3.14.3-2.

(1)空调通风系统工程调试流程见图3.14.3-2。

Figure 3.14.3-2 Commissioning process of HVAC system

图3.14.3-2 空调通风系统调试流程

(2)Commissioning method of HVAC system is shown in the table 3.14.3-4. (2)空调风系统的调试方法见表3.14.3-4。

Table 3.14.3-4 Commissioning method of HVAC system

表3.14.3-4 空调风系统调试方法

No. 序号Commissioning steps

调试步骤

Commissioning requirements

调试要求

(3)Commissioning of air conditioning water system

(3)空调水系统的调试

Air conditioning water system shall conduct flow balance and commissioning respectively based on single circulating system. Hydraulic balance regulation process of water system is shown in the figure 3.14.3-3.

空调水系统调试应该以单个循环系统分别进行流量平衡及调试。水系统的水力平衡调节流程见图3.14.3-3。 1 Measure the rotating

speed and current of

fan of air conditioning

system.

空调系统风机转速及电

流的测定 Use clip-on ammeter to measure

operation current of the fan, use tachometer to measure rotating speed of the fan, inspect whether they comply with requirements or not. 钳形电流表测量风机的运行电流,用转速表测量风机的转速,检验是否满足要

求。

2 Test total blast capacity

of HVAC system and

pressure in all sections

of the unit.

通风空调系统总风量、机

组各段压力的测试 Confirm test position and quantity of

test points in accordance with requirements of the specification. Pressure test shall select micromanometer with proper range to test at all sections of the unit. 按规范要求确定测试位置及测点数量。

压力测试应选用适当量程

微压计在机组各段开孔测试。

3 Preliminary measurement of blast capacity of air inlet. 风口风量 的初测

Measurement of air inlet of air diffuser

adopts air hood, measurement of

grating air inlet and twist outlet adopts

hot-bulb anemograph or impeller

anemograph.

散流器风口测量用风量罩,

格栅风口、旋流风口测量用

热球风速仪或叶轮风速仪。

4 Air balance of air inlet

风口风量平衡 Use benchmark air inlet to debug balance of blast capacity of air

inlet;

风口风量的平衡用基准风口法调试; Deviation of blast capacity of air inlet after balance could not be

over ±15% of designed blast capacity.

平衡后风口风量偏差不得超过设计风量的±15%。

Figure 3.14.3-3 Balance of hydraulic system

图3.14.3-3 水力系统的平衡

(4)Test and adjustment of smoke control system are shown in the table 3.14.3-5. (4)防排烟系统的测试和调整见表3.14.3-5。

Table 3.14.3-5 Test and adjustment of smoke control system

表3.14.3-5 防排烟系统的测试调整

Contents 内容Commissioning requirements

调试要求

Commissioning of smoke control system

排烟系统的调试Test blast capacity of all outlets and then add together, total summation could not be lower than 90% of the stipulated valve.

测试各个风口的风量然后相加,所得的总和不得低于规定值的90%。

Commissioning of pressurization air supply system of staircase

楼梯间加压送风系统的调试Total blast capacity meets design requirements, start pressurized fan, and positive pressure value of the staircase shall comply with provisions of design and fire control. Positive pressure value shall guarantee pressure from corridor, front room and stair is distributed increasingly.

总风量满足设计要求,开启加压风机,楼梯间的正压值应符合设计与消防的规定。正压值应满足走廊→前室→楼梯的压力呈递增分布。

(5)Determination of indoor temperature, relative humidity and noise of

air-conditioned room

(5)空调房间室内温度、相对湿度和噪声的测定

1)Commissioning of temperature and relative humidity in indoor air-conditioned room shall be conducted under designed conditions. Comfortable air-conditioned room shall choose the working area where people usually do activity. Number of test points of relative humidity and indoor temperature shall be confirmed as per the table 3.14.3-6.

1)室内空调房间的温度、相对湿度的调试应在设计条件下进行。舒适性空调房间应选择在人经常活动的范围为工作区。室内温度和相对湿度测点数见表3.14.3-6。

Table 3.14.3-6 Number of test points of temperature and humidity test

表3.14.3-6 湿、温度测点数

Fluctuation scope 波动范围Indoor area ≦50m2

室内面积≤50m2

Increase by every 20-50m2

每增加20-50m2

Δt=±0.5-±2℃

ΔRH=±5-±10%RH 5

Increase by 3-5

增加3-5

2)Noise determination: measurement method is shown in the figure 3.14.3-4.

2)噪音测定:测量方法参见图3.14.3-4。

Figure 3.14.3-4 Use sound level meter to measure noise

图3.14.3-4 声级计测量噪声

3. Commissioning of water supply & drainage and firefighting system

3、给排水及消防系统调试

Plumbing of the project includes pipe systems including indoor and outdoor plumbing, storm sewage system and fire fighting. Plumbing system includes production & domestic water supply system, rainwater recycle system, production & domestic sewage system and rainwater system; firefighting water system includes hydrant water supply system, sprinkler system and water fog system.

本项目给排水系统包括室内外给水排水、雨污水系统、消防等管道系统。给排水系统设有生活生产给水系统、雨水回用系统、生活生产污水系统、雨水系统;消防水系统包括消火栓给水系统、自动喷水灭火系统、水喷雾系统。

(1)Plumbing system

(1)给排水系统

1)Commissioning of plumbing system

1)给排水系统试运转

①Check protective measures of equipment lubrication, electrical wiring, electrical insulation and rotating parts in accordance with technical data; make preparations before commissioning;

①根据技术资料,检查设备润滑、电气接线、电气绝缘、转动部分的防护措施,做好试车前的准备工作;

②Equipment commissioning shall be conducted in accordance with technical data of equipment manufacturers; or ask technical personnel of manufacturers to instruct on site; it shall set up commissioning team to make commissioning work of equipment conduct orderly;

②设备的试车应根据设备厂家的技术资料进行,或要求厂家技术人员在现场进行指导。成立试车小组,使设备试车工作有序进行;

③Equipment commissioning shall be started at first, and then conduct single machine commissioning. In the process of commissioning, measure all technical parameters of the equipment; and make commissioning records as per the requirements.

③设备试车应先点动,然后进行单机试运转。试车当中,对设备的各项技术参数进行测量,并按要求做好试运转记录。

2)Commissioning of water supply system

2)给水系统调试

①Indoor and outdoor water supply pipes shall be flushed;

①室外、室内给水管道,应进行冲洗;

②Discharge pipe of water washing must be connected to reliable and smooth drainage network. Cross section of drainage pipes shall not be smaller than 60% of the cross section of flushed pipe.

②水冲洗的排放管必须接入可靠通畅的排水管网。排放管的截面不应小于被冲洗管截面的60%;

③Water flushing shall be conducted as per that the maximum flow that the pipe

inside may reach is not less than 1.5m/s;

③水冲洗应以管内可能达到的最大流量不小于1.5m/s的流速进行;

④The most unfavorable point static water pressure of hydrant at the end shall comply with design requirements.

④末端最不利点水压应满足设计要求。

3)Commissioning of drainage system

3)排水系统调试

①Operation of liquid level automatic control device complies with design requirements;

①液位自动控制装置动作符合设计要求;

②Check soil stack, timely handle leakage and parts where drainage is not smooth;

②检查排水立管,对渗漏和排水不畅处,进行及时处理;

③Check whether indoor drainage system, design requirement and most water distribution points opened at the same time reach rated flow or not;

检查室内排水系统,设计要求同时开放的最大的数量配水点是否达到额定流量;

④Start indoor drainage system as per 1/3 of water distribution points of water supply system, check whether all drainage points are smooth or not and whether connection parts have leakage or not;

④将室内排水系统,按给水系统的1/3配水点同时开放,检查各排水点是否畅通,接口处有无渗漏;

(2)Firefighting water system

(2)消防水系统

1)Commissioning of hydrant system

1)消火栓系统调试

①Commissioning method of indoor hydrant system is shown in the table 3.14.3-7.

3 室内消火栓系统调试方法见表3.14.3-7。

Table 3.14.3-7 Table of commissioning method of indoor hydrant system

表3.14.3-7 室内消火栓系统调试方法表

No. 序号Item

项目

Commissioning contents

调试内容

1 Test of water

source

Check whether volume of firefighting water tank and elevation comply with

design requirement or not; verify whether municipal firefighting water

(7)项目实施计划详细方案,安装、调试、验收的方案和措施

(7)项目实施计划详细方案,安装、调试、验收的方案和措施 一、施工条件准备 我公司将在中标通知书发布后三天内,组织最优良的工程方案设计人员和工程实施人员,严格按照该工程的招标设计要求及设计方案、施工组织方案的要求进行项目实施前期勘查和项目施工准备工作。前期准备结束后,将安装调试设计和规范提交项目负责人进行审核,考虑所有工作的衔接,经甲乙双方签字后确认的安装调试设计和规范作为该工程实施、验收等一系列过程的重要依据。 1、文件准备 指定施工图纸及方案,办理施工审批手续按工程进度提交工程分步自检单。具体如下: A、根据工程项目设计方案和图纸资料制定出完整的工程施工方案,包括工程施工计划、安 全文明施工保证书等文件。 B、到工程涉及部门办理工程配合协议书,主要包括供电、园林、绿化等。 C、准备随工程施工进度按步检查使用的工程质量分步验收单 2、材料准备 根据工程材料清单和分步进场设备清单,作好主要施工材料的准备和保管工作。 ●土建工程材料:包括机砖水泥、沙石。路基用无极混合材料、路面修补材料、木炭 等。 ●专用材料:包括控制器基础架、管道的接头、检查井口盖、各种混凝土基础钢筋网 等。 ●工具和机械:包括活搬手、水平尺、手推车、电焊机等。 ●安全施工设备:为保障施工安全,应在施工现场设置安全设备;施工现场绕行标志 牌、施工现场安全围挡设备等。 二、设备安装及调试 铺设光纤到各个安装点的机柜,各种软、硬件设备在出厂前调试完毕。我公司工程方案设计人员已对学校的安装点位进行了详细的勘察和分析,并绘制了非常周密的施工安装图纸。 1、基础施工、立杆安装 a)基础施工 ●立杆基础所需开挖的地井大小为:500*500*600 ●立杆位于每个被检测位置15m。将立杆和落地机柜安装在绿化带内,立杆底座和机 柜底座之间用直径50的PE管连接。

管理系统试运行方案

申报管理系统 试 运 行 方 案 二○二○年二月

目录 1、试运行目的 (3) 2、试运行管理机构 (5) 3、试运行的准备 (5) 4、试运行时间 (7) 5、试运行制度 (7)

申报管理系统已全面完成,并于2020年2月已经开发部署完成,另一方面,调试工作方面已经基本完成调试,其按照建设程序,系统已经具备进入试运行的条件,按项目进度管理阶段来看,系统可以进入试运行阶段,以检验系统长期运行的稳定性、可靠性和实际应用的效果。并在试运行中,建立健全运行操作和系统维护规范,为系统投入实际运行和完善提供实际运行数据和依据。 试运行包括资金申报门户网站及后台管理系统,数据记录试运行。 一、试运行目的 试运行目的通过既定时间段的试运行,全面考察项目建设成果。并通过试运行发现项目存在的问题,从而进一步完善项目建设内容,确保项目顺利通过竣工验收并平稳地移交给运行管理单位。 通过实际运行中系统功能与性能的全面考核,来检验系统在长期运行中的整体稳定性和可靠性。 (一)系统功能、性能与稳定性考核 1.系统功能及性能的实际应用考核; 2.系统应用软件、软件支撑平台的长期稳定性和可靠性; 3.系统主要硬件设备、辅助设备的长期稳定性和可靠性;

4.数据通信系统的长期稳定性和可靠性; 5.检测数据的长期准确性和完整性; 6.系统长期安全性能; 7.网络连接的可靠性。 (二)系统稳定性和可靠性 1. 不同操作地条件下,系统工作的稳定性、可靠性和功能、指标的正确性; 2. 在各种工况条件下,特别是在局部故障或个别设备故障时,系统整体 3. 功能的正确性; 4. 各种环境、工况条件下,对设备的安全保护性能和系统的工作性能; 5. 各种环境、工况条件下,远程控制功能在实际操作中的安全性能。 (三)检验系统实际应用效果和应用功能的完善 1. 系统运行检测数据在管理中的应用; 2. 数据档案的应用; 3. 系统实时管理能力的应用; 4. 系统远程控制能力的应用; 5. 各类报表的应用;

机电设备安装及试运转管理办法

——方案计划参考范本——机电设备安装及试运转管理办法 ______年______月______日 ____________________部门

一、总则 1、为加强机电设备安装工程安全管理,依照国家及行业主管部门颁发的安全生产法律、法规,并结合机电设备安装工程施工特点,制定本规定。 2、机电科依据本规定及相关法律法规,根据现场实际情况,编写详细施工措施。 二、一般要求 1、从事机电设备安装工程,在编制施工组织设计前,机电矿长要组织施工技术、机电设备人员等共同对施工现场进行实地考察,针对工程特点和现场实际进行重大危险源辩识和安全评价,学习和掌握相关技术、安全方面的法规、规范、标准,编制相应的管理方案及应急救援预案,制定安全技术防护措施。对起重吊装、脚手架、管沟开挖等作业要制定专项施工方案,并经有关部门审核批准后方可实施。 2、对特殊工种上岗人员如:电工、电气焊、起重、机操和无损探伤检测等作业人员必须进行岗位适任证书核验,未经核验或核验不合格的,不得上岗作业。 3、施工机械、特种车辆等设备进场前,必须经过国家规定的安全技术状态检查,并经公司设备主管检查,合格后方可使用;机械设备操作人员必须依照有关规定持证上岗,严禁无证人员操作。 4、施工现场起重设备安装调试,必须符合国家质量技术监督局及其他行业主管部门的规范要求,经验收合格后方可使用。

5、施工现场临时用电线路、用电设施的安装和使用必须符合相关 电气安装规范,并按照临时用电施工组织设计进行架设,严禁随意拉 线接电。 6、施工现场必须设有保证施工正常进行并符合安全要求的夜间照明,危险潮湿场所的照明以及手持照明灯具,必须使用规定的安全电压。 7、施工时应采取专项防护措施,以保证施工现场及其相邻区域人 员和设施的安全。 8、施工时应严格按照经有关部门批准的施工总平面布置方案,搭 建和设置各项临时设施,堆放物料、停放机具设备,不得侵占场内道 路和安全防护设施。应严格分区隔离保管易燃易爆品,严格依照《中 华人民共和国消防法》的规定,建立和执行防火管理制度,设置符合 消防要求的消防设施,并保持完好的备用状态。保证消防疏散通道畅通,其设立应符合相关的规定和要求,在易于发生火灾的区域及储存、使用易燃易爆器材时,应采取特殊的消防措施,并加设警示标志。 9、施工时应遵守国家有关环保法律、法规,采取有效措施,控制 施工现场的各种粉尘、废气、废水、固体废弃物、噪声及震动对环境 的污染与危害。 10、施工现场要设立安全警示标识,严禁无关人员及车辆进入和 靠近。道路须保持平整、通畅,弯道处应设交通安全标志。 11、施工时应及时购置和发放符合国家标准的劳动防护用品,并 定期更新。严禁未按规定穿戴劳动防护用品的施工作业人员上岗作业。 三、作业现场

项目总承包工程调试及试运行管理方案

第十四节调试及试运行管理方案 工程的机电系统要求功能全面、运行良好,我单位为了确保机电各系统的正常运行,特编制了详细全面的调试方案,主要包括暖通、给排水、电气三部分,其中既包括各系统常规项目的调试,力图能够在总包、业主、监理等相关单位协助下顺利地完成调试工作,以确保工程的设计、施工成果能够得到完美体现。 1.机电系统调试的目的 机电系统调试的目的是为了确保建筑物各机电系统的工作处于最佳状态,满足业主方的使用要求。首先在系统调试过程中,检查施工缺陷,测定机电设备各项参数是否符合设计要求,并在测定设备的性能后对其进行调整,以便改善由于设备之间的相互不均衡导致的问题,确保为业主提供良好舒适的使用环境;其次在系统调试的过程中积累总结系统设备材料的相关数据,为今后的系统运行及保修提供可指导性的资料。 2.机电系统调试工作部署及工作流程 2.1调试部的设置 为保证机电系统调试工作顺利开展,最终达到满意的调试效果,工程开工时就组织经验丰富的专业工程师成立调试部。调试部负责施工过程中的各项检测与试验,以及整个系统性能的测定与调整。 2.2调试部人员配置及职能

3.机电系统调试准备 3.1机电系统调试计划 组织各家编排调试节点计划,主要依据机电总控进度计划编制,在工程中标后具体编排详细计划内容。3.2测试仪器准备 在调试前安排个专业提供检查合格的检测仪器仪表,如电缆绝缘测试、接地电阻测试、漏电开关测试仪、红外测温仪、钳形电流表、智能光电转速表、频闪仪、噪声分析仪、温湿度计、风速仪、超声波流量计、平衡阀测量仪等。 3.3测试仪器的数量 测试仪器数量主要依据调试计划内容进行准备。 3.4测试仪器的校验 测试仪器使用前应送到当地相关部门进行校验。 测试时所使用仪器必须经过相关部门校验合格。

设备调试方案

设备调试方案 一,项目试运行程序与责任分工 (一)试运行的阶段 1,试运行目的。是检验单台机器和生产装置的制造、安装质量、机械性能或系统的综合性能,能否达到生产出合格产品的要求。 2,试运行阶段的划分。分为单机试运行、联动试运行、负荷试运行等阶段。前一阶段试运行是后一阶段的准备,后一阶段的试运行必须在前一阶段完成后进行。 1)单机试运行。指现场安装的驱动装置的空负荷运转或单台机器以空气、水等代设计的工作介质进行的模拟负荷试运行。单机试运行属于工程施工安装阶段的工作内容。但确因受介质限制或必须带负荷才能运转而不能进行单机试运行的单台设备,按规定办理批准手续后,可留待负荷试运行阶段一并进行。 2)联动试运行。指对试运行范围内的机器、设备、管道、电气、自动控制系统等,在各自达到试运行标准后,以水、空气作为介质进行的模拟运行。联动试运行适于成套设备系统的大型工程。 3)负荷试运行。是指对指定的整个装置按设计文件规定的介质打通生产流程,进行指定装置的首发衔接的试运行,以检验其除生产产量指标外的全部性能,并生产出合格产品。负荷试运行是试运行的最终阶段,自装置接受原料开始至生产出合格新产品、生产考核结束为止。(二)试运行责任分工及参加单位 1,单机试运行责任分工及参加单位 (1)单机试运行由施工单位负责。 (2)参加单位:施工单位、监理单位、设计单位、建设单位、重要机械设备的生产厂家。2,联运试运行责任分工及参加单位 (1)由建设单位(业主)组织、指挥。建设单位工作内容包括:负责及时提供各种资源,编制联动试运行方案,选用和组织试运行操作操作人员,实施试运行操作。 (2)联运试运行参加单位:建设单位、生产单位、施工单位以及总承包单位、设计单位、监理单位、重要机械设备的生产厂家。 (3)施工单位工作内容。包括:负责岗位操作的监护,处理试运行过程中机器、设备、管道、电气、自动控制等系统出现的问题并进行技术指导。 3,负荷试运行责任分工及参加单位 (1)由建设单位负责组织、协调和指挥。 (2)除合同另有规定外,负荷试运行方案由建设单位组织生产部门和设计单位、总承包,施工单位共同编制,由生产部门负责指挥和操作。 二、项目单机试运行前应具备的条件 1,机械设备及其附属装置、管线已按设计文件的内容和有关规范的质量标准全部安装完毕,包括: (1)安装水平已调整至允许范围。 (2)与安装有关的几何精度经检验合格。 2,提供了相关资料和文件: (1)各种产品的合格证书或复验报告。 (2)施工记录、隐蔽工程记录和各种检验、试验合格文件。 (3)与单机试运行相关的电气和仪表调校合格资料等。

项目组织设计及安装调试方案

项目组织设计及安装调 试方案 文档编制序号:[KKIDT-LLE0828-LLETD298-POI08]

项目组织设计及安装调试方案 根据《社会救助暂行办法》明确规定“县级以上人民政府民政部门应当建立申请和已获得社会救助家庭经济状况信息核对平台,为审核认定社会救助对象提供依据”。通过核对信息系统开展居民家庭经济状况信息核对,是全面建立居民家庭经济状况核对机制的重要内容,是落实《社会救助暂行办法》要求、提高对象认定准确性、促进公平公正的重要手段,是创新社会救助管理方式的重要举措。各地要把开展核对信息系统建设作为织密筑牢民生安全网的一项重要基础性工作来抓,增强责任感和使命感,认真履行职责,进一步加大工作力度,加快建设步伐。 构建统一的信息共享平台。信息共享平台能够实现数据共享和业务协同,是核对信息系统的重要组成部分。在服务内容方面,该平台能够实现各个节点的数据采集、汇总、整合、校核、查询、分发、交换等功能,满足信息查询、全文检索、比对分析、统计汇总等数据应用需求;在安全保障方面,各个节点均能提供访问控制、数据合法性检查、病毒查杀、加密传输、内容审计等信息安全保护机制;在运行管理方面,利用该平台可形成一个中心、多个节点的一对多集中管控模式,实现运行监控的统一管理。 通过信息共享平台,充分利用民政部提供的数据资源,推动本地民政系统内部和与其他部门之间的信息共享和业务协同。各地要根据民政部的总体设计,部署数据交换节点,或逐步更新已有信息共享系统。在核对信息系统项目立项过程中,各地应全面细致地分析本地区部门之间以及上下级之间的信息共享需求,建立完善信息共享目录和动态更新机制。 建设地方数据中心的过程中,一是要尽量使用国家电子政务外网和民政广域网,上述两网无法全覆盖的地方,在保证高效安全的前提下,可利用专线网络进行补充;二是要配备专用的网络设备、数据库服务器、应用服务器等必要设备;三是要安装经济适用的操作系统、数据库等基础软件。各地在充分论证的基础上,可采用物联网、云计算、大数据处理、移动互联网等新技术,进一步提高信息化资源的利用效率和管理水平。 项目总体方案 在项目中做好与建设方的配合措施,建设方在工程上起主导作用,为建设方服务是本我们永远追求的目标。本公司将在整个项目实施过程中,全面了解建设方的需求,掌握为建设方服务的内容,达到为建设方服务的效果和目的,最终实现工程项目的综合目标。为保证项目质量并在规定的工期内完成项目,我公司针对本项目的实施做如下保证措施:

设备调试、试运行方案

设备调试、试运行方案 设备调试、运行分别对仪表、电机、照明系统、接地进行测试调试,待各分项调试合格后,进行联合试运行。 1.调试方法 ①先检查各种照明配电柜是否已全部切断电源。 ②再检查各灯具是否测试合格及接线准确。 ③将本工程按系统、按照明配电箱控制的区域分成各自独立的调试区域,调试从上到下,逐层逐区域调试。 选择好A、B塔顶层最西端的照明配电箱,先引来临时电源,把该照明配电箱进线开关断开,且把正式进线先拆除,接着接上临时电源,送上电源,先打开箱内1路照明控制开关,再开启相关的照明灯具,正常,打开另一路照明控制开关。接着逐步打开照明配电箱内的全部开关。 然后采用相同的方法进行调试第二个照明配电箱,逐步调试完顶层的所有照明配电箱,再往下层调试,采用相同的方法直至所有的照明配电箱全部调试完。 ④照明系统每2小时用电压表和电流表测量电源电压、负荷电流,公建试运行24小时,住宅部分运行8小时。调试中逐个检查插座接线是否正确,开关控制灯具是否灵活、准确,控制顺序是否相对应,并随时观察灯具发光是否正常,导线发热是否有异常,发现问题及时查找原因进行整改,并作好记录。 2.电气动力系统调试 ⑴系统要求 ①各种用电设备安装完毕,且已经过绝缘测试合格。 ②相关管线敷设完,且已经过绝缘测试合格。 ③配电控制箱已经安装完,且已通过绝缘测试。 ④桥架、电缆敷设完毕,电缆绝缘测试合格。 ⑤母线敷设完毕,绝缘测试合格。 ⑥配电箱、柜安装完毕,绝缘测试合格。 ⑦各种高低压配电柜安装完毕,测试合格。 ⑵调试方法 ①先检查各种动力配电柜是否已全部切断电源。

②再检查各动力配件组成部分如:母线、电缆、电动机等,是否测试合格及接线准确。 ③将本工程按系统、按配电箱控制的区域分成各自独立的调试区域。 3.电机系统调试 ⑴电机调试运行步骤: 单机检查校验→线路绝缘摇测→控制回路接线→电机性能检查、接线→设备调整→供电回路电源电压测量、电机接线情况检查→单机无荷载启动→单机带荷载启动→数据记录 ⑵电机空载运行2小时,每隔1小时测量一次电源电压、空载电源直至2小时。 ⑶电机试运行接通电源后,如发现电机不能启动和启动时转速很低或声音不正常等现象,应立即切断电源检查原因。 ⑷电机试运行中需检查:电机的旋转方向、声音、气味是否正常;换向器、滑环及电刷的工作情况是否正常;电机的温度是否过热;轴承的温升是否正常;电机的振动是否符合要求。 ⑸交流电机带负荷启动次数应尽量减少,如产品无规定时按在冷态时可连续起动2次,在热态时,可连续起动1次。

最新项目供货安装和调试方案(整理到技术方案中即可)

项目供货安装和调试方案(整理到技 术方案中即可) 项目供货、安装和调试方案质量管理的方针、目标和承诺质量方针我们的质量方针是:优秀的产品,一流的服务。质量目标我们的质量目标是:确保各阶段工作的有效性,把符合用户实际需求的产品适时地交付用户。有效性:阶段成果经过严格的确认,确实成为下一步工作的依据。适时:指按规定的进度或按与用户共同协商的时间。质量承诺我们的质量承诺是:我们在工作中严格执行ISO9000质量标准。质量管理的目的和内容目的:满足用户要求,规范自身行为,达到供需双方共同获益的效果;内容:质量

策划——目的、范围、做什么、何时做、谁来做、如何做;质量控制——监视过程,发现、排除不合格;质量保证——满足质量要求,取得需方信任;质量改进——完善、改进质量体系;本项目供货、实施的组织结构保障针对本次项目,神州数码认为必须有良好的组织结构保障才能确保本项目的顺利实施。神州数码公司提出和项目单位一起组建适于本项工程系统平台实施和管理的组织和领导机构。本项目组织机构如下图:项目领导小组项目实施组供应链商务小组安装实施小组技术支持小组验收小组质量监售后支控小组持小组具体供货、安装、调试实施步骤为了使项目能够按照计划、有条不紊地进行,神州数码将整个实施过程分为实施前期、实施中期、实施后期三个阶段,每个阶段根据具体任务分为多个环节。项目实施环节统计如下:项目环节实施前期设备供货进行商务洽谈,确保项目中所有设备

如期、安全地到达用户现场。根据设计方案,协助项目单位制订设备安装实施的技术标准;制定详细实施方案根据项目单位网络现状提供详细的网络、机房环境等分配方案;制定详细的进度计划;编制实施方案、技术参数手册和设备安装手册。相关技术人员进行内部培训。检查、核实实施现场的环境。商务组技术支持小组任务内容简述任务执行组技术支持小组质量监控组内部技术培训实施环境调查技术支持小组安装实施小组技术支持小组安装实施小组实施中期设备到货设备到货,并在指定的地点交货、到货验收及验收现场安装调试设备初验实施小组进行现场设备安装调试工作、现场培训工作实施小组完成安装调试工作后,进行网络联调,并依据测试计划对设备进行自测。项目领导组商务小组安装实施小组技术支持小组安装实施小组技术支持小组安装实施小组安装实施小组质量监控组技术支持小组安装

工程项目调试及试运行管理制度

1 目的 为了规范调试管理工作、规定调试各阶段的工作程序、保证调试质量,特依据公司有关规定特制定本制度。 2 范围 本规定适用于娄底市裕德科技有限公司娄底污泥无害化处理与综合利用项目。 3 定义 调试的组织机构:调试的领导机构为调试指挥组,由项目经理出任组长。调试指挥组由项目部各成员、总承包单位、施工单位、监理单位等有关单位的代表组成,同时应邀请主要设备厂商派员参加。 4 职责 4.1 总经办 负责对公司所属项目调试的监管。 4.2调试指挥组的职责 1、负责调试运行阶段的组织协调、统筹安排和指挥工作。 2、负责组织实施调试方案和措施。 3、组织和办理调试运行后的验收签证及资料交接。 4、负责核查试运应具备的条件。 5、提出试运行计划。 6、组织实施试运行方案和措施。 7、负责试运行现场指挥和具体协调工作。 4.3施工单位的职责 1、负责处理工程缺陷,并根据整改通知单进行相关部分的整改。 2、负责设备单机调试。 4.4设备供货商的职责 负责主要大型关键设备的单机调试。 4.5生产单位的职责

1、参加调试运行后的接收工作。 2、负责调试期间设备的启停操作。 3、负责调试期间运行参数的记录工作。 4.6设计单位的职责 负责必要的设计修改,提交完整的竣工图。 4.7监理单位的职责 按合同负责调试阶段的监理工作。 5 程序 5.1调试工作指导思想 1、严格执行项目相关质量控制标准,以调试创新为手段,高标准、高质量的完成各项调试项目,达到或超过国内先进技术指标。 2、项目施工进度应同调试进度有机结合起来,达到紧张有序、优质高效、缩短工期的目的。 3、充分发挥人才、技术优势,做好公司的技术参谋,对调试中发现的技术难题,本着严谨科学、实事求是、积极稳妥的态度,提出解决对策。 4、依据调试是项目工程质量动态检验的特殊地位,为公司把好项目建设的最后一关,提高项目整体质量。 5、把事前策划放在突出的地位,做到调试进度、质量随时处于受控状态。 5.2调试及试运行的工作程序 5.2.1调试运行应具备的条件 1、项目施工工作已经结束,记录完整,验收合格,调试运行必须的临时设施完备。分系统调试应按系统对设备、电气、仪控等全部项目进行检查验收合格。 2、调试方案、措施、专用记录表格准备齐全。 3、现场环境满足安全工作需要。 4、组织落实、人员到位、职责分明。 5、调试仪器、设备准备完毕,能满足调试要求。 5.2.2调试运行工作程序

安装调试方案

安装调试方案 1)、如果此项目中标,公司将成立专门项目组负责该项目的具体实施 具体分工如下: 合同签定以后,项目小组和实施小组将共同对设备方案的技术细

节进行分析、探讨,制定详细安装调试计划,包括: 1、安装调试手册; 2 、安装调试进度安排; 3 、安装方式; 4、调试方法; 5、调试工具的准备; 6 、安装调试环境的准备; 7、对影响项目实施的关键工序、关键设备进行分析,提出相应的解决措施; 8、技术参数手册、培训手册和安装手册; 9、制定项目建设质量管理方案和措施; 2)、安装现场环境调查及现场勘察 为确保各工程实施小组到达现场后能够尽快展开工作,保证项目顺利进行,我公司将在实施前 10 天内对用户单位设备安装环境进行调查,填写安装环境调查表。同时,我们还将提前向用户单位提交各种主要设备的具体环境要求,在用户单位的积极配合下,确保在现场实施工作开始前完成场地环境准备工作。 3)、现场安装调试 设备到达安装现场后,由我公司技术人员和用户共同清点完毕后,工程实施小组的工程师将开始设备安装调试工作 项目组将有包括项目经理在内的多名工程师参加项目实施,他们负责现场设备、辅助设备的安装和调试,完成后同时填写项目安装调试报告。 我们在设备安装和调试的同时,将对使用单位的设备操作和维护人员进行现场培训,同时为每个设备及系统提供一套完整的技术资料。

4)、到货验收 在合同设备到达用户指定的地点后,用户与我公司代表将共同开箱验货,依标书要求对全部设备的型号、规格、数量、外型、包装及资料、文件(如装箱单、保修单、随箱介质等)的验收,当出现损坏、数量不全或产品不对等问题时,我公司将负责解决;同时按标书技术部分要求对其产品的性能和配置进行测试检查,并做出测试方案和测试报告,保证所有硬件设备在标书中所规定的地点和环境下 , 实现正常运行 , 并达到标书要求的性能和产品技术规格中的性能。 5)、安装调试承诺: 1、我公司承诺:交货期为签订合同起 29 日历天,保证严格按照采购方的交货时间和产品质量要求,及时送达客户指定地点,运输过程中所有费用由我公司承担。 2、我公司中标后,将派出有经验的工程技术人员到用户现场进行调研,根据用户要求和实训室实际情况制定安装方案,设备送达学校后按用户确定的方案进行安装调试,直到设备正常使用运行、验收。 3、保证我公司的工程质量符合国家标准、行业标准和用户要求。 4、保证我公司提供产品均为行业正品,质量优良,无假冒伪劣,不以次充好。 5、我公司负责所有设备安装、调试(包括与计算机连接调试),以及所有所需配套设施(如全部设备安全控电箱与保护开关等)的供应、安装、调试(包括所有费用)。 6、在完成安装、调试、检测后,可向用户提供检测报告、技术手册,提供中文版

制浆区辅助设备安装及试运行方案

一、编制依据 1、设备厂家提供的相关图纸以及其它技术资料; 2、本项目施工图CHEC-204-1S-J0302等; 3、《机械设备安装工程施工及验收规范》GB50231-2009; 4、《电力建设工质量验收及评价规程》(锅炉机组篇)DL/T5210.2-2009; 5、《压缩机、风机、泵安装工程施工及验收规范》GB50275-2010; 6、《电力建设安全工作规程》(火力发电厂部分)DL/5009.2002; 7、《电力建设安全健康与环境管理工作规定》2003版; 8、《工程建设标准强制性条文》电力工程部分2015版; 9、北京电力建设公司计量体系文件; 10、北京电力建设公司企业标注化体系文件; 11、北京电力建设公司职业安全卫生与环境管理体系。 二、工程概况 本工程为陕西华电榆横煤电有限责任公司榆横发电厂1、2号机组超低排放改造工程,其中制浆区域安装及试运设备主要包括除雾器冲洗水泵1台、磨机浆液循环泵2台、硫化风机2台、硫化风电加热1台、石灰石浆液泵2台、制浆泵房地坑泵2台、制浆泵房地坑搅拌器1台、石灰石粉仓仓顶除尘器1台、除尘风机1台。为满足安全施工需要,合理安排工程进度,确保工程施工质量,特编制本施工方案。 三、作业前的条件和准备 3.1设备验收 3.1.1设备开箱,应在建设单位、监理单位、分包单位有关人员参加下检查,并应作出记录; 3.1.2按设备装箱清单核对泵的规格、型号、数量是否符合设计要求; 3.1.3检查随机资料,设备的出厂合格证书或质量证明书是否齐全; 3.1.4设备交接验收应在业主及有关单位参与下共同进行,并做好记录;

3.1.5开箱应使用合适的工具,不得猛烈敲击,以防损坏设备; 3.1.6设备开箱后,发现有损坏或质量缺陷应及时上报,并做好记录; 3.1.7设备验收完毕后,应填写设备验收清点记录。 3.2施工前应具备的条件 3.2.1施工人员及工机具到达施工现场。(施工人员齐整,所有施工人员已完成入场教育,施工用工器具、起吊机具、焊接机具等性能良好,安全设施齐备,能够满足施工需求。) 3.2.2施工材料准备齐全并检验合格,满足施工需要。 3.2.3专项施工方案审批完毕,技术交底签字完毕; 3.2.4施工图纸及相关的技术资料齐全,并经过会审,满足现场施工需求。 3.2.5具备施工条件,夜间施工区域有充足的照明。 3.2.6电源设施齐全,道路畅通,作业时要有安全防护措施。 3.2.7尽量避免交叉作业,施工区不应有易燃、易爆等危险品。 3.2.8本项目作业前上一道工序施工及验收完毕,具备下道工序施工条件。 3.3主要施工机具配置及人员安排 3.3.1施工设备及工器具

项目安装调试方案、计划进度和人员安排

项目安装调试方案、计划进度和人员安排 1.概述 闭路监控系统能在人们无法直接观察的场合,却能实时、形象、真实地反映被监视控制对象的状况,且能做到全天候24小时不间断进行,现已成为人们在现代化管理中一种极为有效的观察管理工具。由于它具有只需一人在控制中心操作就可观察许多区域,甚至远距离区域的独特功能,被认为是保安工作之必须手段,因此闭路电视监控系统在现代化教学管理和护卫中起独特作用。 本系统采用统一的技术规范、兼容明晰的信息格式,将高性能的系统设备有机地集成在一起,构成一个高度自动化的闭路电视监控管理系统。保证图像清晰、色彩真实、防闪稳定和操作容易,并可在所处环境下长期可靠地运行。 2.系统设计目标 1架构合理 2稳定性和安全性 3低成本低维护量 4先进性,可靠性,可扩充性

总体设计 代表性建筑,是休闲娱乐场所。人员流动较大。初步设计为三个区域(东北边治安岗亭为第一个区域,中间办公楼为第二区域,西南边治安岗亭为第三区域)。每个区域有一套硬盘录像系统,值班人员可监视本区域人员及公园设施的监控实时画面和录像,能对本区域所发生的情况作出响应。实现分片监控。办公区监控机房与分控点之间用目前最先进的光纤进行连接,与分控点紧密连接。主监控机房通过三台电视分别显示三个分控点的即时画面并能实现控制功能。从而实现对整个沭河公园的全局监视。以下详细介绍分控点和主监控机房的规划。 1.分控点 1.1录像系统组成 1.硬盘录像系统 2.前端定点摄像机 3.高速云台摄像机 4.线材及辅助设施 1.2线路传输部分 1 监控线路入地以整洁,安全,规范的原则进行处理 根据摄像机安装位置建议选择采用同轴电缆和超五类双绞线,以保证监控信息的准确传输。控制线设计采用RVVP2*1.0圆形双绞屏蔽电缆。 2 监控系统和中心控制室采用单独电源主干采用AC220V供电,在摄像机前端采用变压器 3 防雷(电源防雷视频信号防雷) 系统设计在摄像机前端安装视频防雷器。当视频信号有过电压现象发生,避雷器瞬间导通,以保证前端摄像机和末端矩阵主机的安全 1.3 录像部分 1.设计整个录像系统可以连续保存录像资料十天(录像时间由甲方自定)2.系统支持监视录像与回放 1.4 显示和控制部分 监控系统的显示部分主要由硬盘录像机的显示器完成

MBR调试方案,管理手册

本部分包括:调试条件、调试准备、试水方式、单机调试、单元调试、分段调试、接种菌种、驯化培养、全线连调、检测分析、改进缺陷、补充完善、正式试运行、自行检验、正式提交检验、竣工验收。 1、调试部分 1.1 调试条件 (1)土建构筑物全部施工完成; (2)设备安装完成; (3)电气安装完成; (4)管道安装完成; (5)相关配套项目,含人员、仪器,污水及进排管线,安全措施均已完善。1.2 调试准备 组成调试运行专门小组,含土建、设备、电气、管线、施工人员以及设计与建设方代表共同参与; (1)拟定调试及试运行计划安排; (2)进行相应的物质准备,如水(含污水、自来水),电,药剂的购置、准备; (3)准备必要的排水及抽水设备,堵塞管道的沙袋等; (4)必须的检测设备、装置(PH计、试纸、COD检测仪、SS); (5)建立调试记录、检测档案。 1.3 试水(充水)方式 (1)按设计工艺顺序向各单元进行充水试验。 (2)构筑物未进行充水试验的,充水按照设计要求一般分三次完成,即1/3、1/3、1/3充水,每充水1/3后,暂停3-8h,检查液面变动及建构筑物池体的渗漏和耐压情况。特别注意:设计不受力的双侧均水位隔墙,充水应在二侧同时冲水。已进行充水试验的建构筑物可一次充水至满负荷。 (3)充水试验的另一个作用是按设计水位高程要求,检查水路是否畅通,保证正常运行后满水量自流和安全超越功能,防止出现冒水和跑水现象。 1.4 单机调试 (1)工艺设计中单独工作运行的设备、装置或非标均称为单机。应在充水后,进行单机调试。 (2)单机调试应按照下列程序进行: 1)按工艺资料要求,了解单机在工艺过程中作用和管线连接。

设备单机试运行方案

设备单机试运行方案 永城20万吨/年乙二醇装置 乙二醇设备单机试运行方案一、编制说明及依据: 1、编制说明: 单机试运转是综合反映机械设备的设计、制造、安装和操作技术的性能和质量好坏的重要检验手段。为了早日正式、顺利、安全发电,应当及时完成试运转工作,根据本试运方案工程特点,参照各类机械设备的试运条件和有关规范的编制本试运方案,目的是防止在试运转中发生人身伤亡和设备损坏事故。适用于我单位施工的乙二醇分馏区、气体净化区、中间原料罐区、成品罐区、冷冻热力站等设备试运行。 2、编制依据: 1)设备安装图纸及产品说明书; 2)《现场设备、工业管道焊接工程施工及验收规范》GB50236-98 3)《工业设备及管道绝热工程施工规范》GB50126-2008 4)《机械设备安装工程施工及验收通用规范》GB50231-2009 5)《石油化工施工安全技术规程》SH3505-1999 6)《化工机器安装工程施工及验收通用规定》HG20203-2000 7)《压缩机风机泵安装工程施工及验收规范》GB50275-2010 1 二、工程概况 永城永金化工有限公司乙二醇安装工程位于河南省永城市沱南工业园区,工程监理单位为南京华源工程管理有限公司,设计单位:中国石油集团工程设计有限责任公司辽阳分公司。

本工程中泵类设备有119台。主要输送介质有甲醇、乙二醇等。单机最大功率为75KW,单机最小功率为3KW,用电压为380V,本试车由施工单位、监理单位、建 设单位及设备供应商一起参与。 三、试运程序及试运设备清单 1、试运程序 设备试运前检查?系统检查?设备加注油、脂?脱开联轴器?电机检查及旋转方向?电机2-4小时单试?联轴器装配?手动盘车?带负荷4-8小时试运?办理验收交接手续。 备注: 1)厂家说明书明确要求不需脱开联轴器的设备可整体试运; 2)设备脱开联轴器,电动机试运合格后,联轴器进行装配,并复查联轴器中心,并盘运转子,转子应灵活,无摩擦。 2、试车单机设备性能一览表,见附页。 2 四、试运转 (一)单机试运转的条件 1、试运设备及附属装置均已全部安装完毕,且各类记录资料齐全,并经有关 各方验收合格。 2、机械设备的安装水平度已调整至允许的范围。 3、基础混凝土及二次灌浆层达到设计强度。 4、各水位计和油位计标高最高,最低和正常工作位置的标志。 5、转动机械 加好符合要求的润滑油、脂、油位正常。 6、工业水系统已装好并具有可靠的水源且经反复冲洗干净达到试运条件。 7、各有关的手动、电动、气动、液动阀件,经检查调试试验,动作灵活,可靠,

安装调试方案

供货安装调试方案 1)、如果此项目中标,公司将成立专门项目组负责该项目的具体实施。具体分工如下: 合同签定以后,我公司将对设备方案的技术细节进行分析、探讨,制定详细安装调试计划,包括: 1、安装调试手册; 2、安装调试进度安排; 3、安装方式; 4、调试方法; 5、调试工具的准备; 6、安装调试环境的准备; 7、对影响项目实施的关键工序、关键设备进行分析,提出相应的解决措施; 8、技术参数手册、培训手册和安装手册; 9、制定项目建设质量管理方案和措施; 2)、安装现场环境调查及现场勘察 为确保到达现场后能够尽快展开工作,保证项目顺利进行,我公司将在中标后对用户单位设备安装环境进行调查。同时,我们还将提前向用户单位提交各种主

要设备的具体环境要求,在用户单位的积极配合下,确保在现场实施工作开始前完成场地环境准备工作。 3)、现场安装调试 设备到达安装现场后,由我公司技术人员和用户共同清点完毕后,工程实施小组的工程师将开始设备安装调试工作。 项目组将有包括项目经理在内的多名工程师参加项目实施,他们负责现场设备、辅助设备的安装和调试,完成后同时填写项目安装调试报告。 我们在设备安装和调试的同时,将对使用单位的设备操作和维护人员进行现场培训,同时为每个设备及系统提供一套完整的技术资料。 4)、到货验收 在合同设备到达用户指定的地点后,用户与我公司代表将共同开箱验货,依标书要求对全部设备的型号、规格、数量、外型、包装及资料、文件(如装箱单、保修单、随箱介质等)的验收,当出现损坏、数量不全或产品不对等问题时,我公司将负责解决;同时按标书技术部分要求对其产品的性能和配置进行测试检查,并做出测试方案和测试报告,保证所有硬件设备在标书中所规定的地点和环境下, 实现正常运行, 并达到标书要求的性能和产品技术规格中的性能。 5)、安装调试承诺: 1、我公司承诺:供货安装期为签订合同起30日历天,保证严格按照采购方的交货时间和产品质量要求,及时送达客户指定地点,运输及安装过程中所有费用由我公司承担。

工程调试和试运行方案

目录 1.调试步骤注意事项 (75) 1.1调试程序 (75) 1.2 主体设备及构筑物调试 (77) 2.使用操作与运行管理 (79) 3.故障分析与排除 (80)

本工程方案设计采用“调节池+接触氧化池+斜管沉淀池+消毒池”处理工艺。具体调试方案如下: 1.调试步骤注意事项 污水处理站调试和试运行是污水处理工程建设的重要阶段,是检验污水处理站前期设计、施工、安装等工程质量的重要环节,也是使污水经处理后达标排放的技术保证,工程施工验收合格后,即进入调试阶段,调试分为调试前的准备、清水试车和污水调试。 1.1调试程序 1.1.1调试前的准备 1.1.1.1设备安装完工后,按单体调试、局部调试和系统联合试运转三个步骤进行。清水和污水联调的主要工作是按图纸检查各构筑物的施工质量;各机械设备、仪表、阀件是否满足设计或污水处理站生产工艺要求;各处理单元及连接管段流量的匹配情况;自动控制系统是否灵敏可靠;检查设备有无异常震动和噪音; 1.1.1.2电气系统:检查控制柜配电是否正确,接线是否牢固;供电电源是否符合安装条件要求;检查地线是否接妥; 1.1.1.3设备部分:检查各设备管路是否连接好,检查上各个设备和所有连接紧固螺钉是否松动,各元气件连接是否良好; 1.1.1.4通电前,检查面板上所有的按钮都处于关闭〔OFF〕状态; 1.1.1.5开机前,检查各手动阀在正确状态,才能开机; 1.1.1.6检查各设备的构筑物及设备的放空阀门,使之全部关闭,各构筑物及设备的主管线的进水阀门、出水阀门全部打开,所有机泵的进、出水管的阀门全部打开;7.用清水将设备及管道的油污、泥土、焊渣等污物清洗干净。 1.1.1.7操作工认真阅读工艺原理图、主要设备的使用说明书,牢记设备操作程序,

设备单机试运行方案

永城20万吨/年乙二醇装置 乙二醇设备单机试运行方案 一、编制说明及依据: 1、编制说明: 单机试运转是综合反映机械设备的设计、制造、安装和操作技术的性能和质量好坏的重要检验手段。为了早日正式、顺利、安全发电,应当及时完成试运转工作,根据本试运方案工程特点,参照各类机械设备的试运条件和有关规范的编制本试运方案,目的是防止在试运转中发生人身伤亡和设备损坏事故。适用于我单位施工的乙二醇分馏区、气体净化区、中间原料罐区、成品罐区、冷冻热力站等设备试运行。 2、编制依据: 1)设备安装图纸及产品说明书; 2)《现场设备、工业管道焊接工程施工及验收规范》GB50236-98 3)《工业设备及管道绝热工程施工规范》GB50126-2008 4)《机械设备安装工程施工及验收通用规范》GB50231-2009 5)《石油化工施工安全技术规程》SH3505-1999 6)《化工机器安装工程施工及验收通用规定》HG20203-2000 7)《压缩机风机泵安装工程施工及验收规范》GB50275-2010

二、工程概况 永城永金化工有限公司乙二醇安装工程位于河南省永城市沱南工业园区,工程监理单位为南京华源工程管理有限公司,设计单位:中国石油集团工程设计有限责任公司辽阳分公司。 本工程中泵类设备有119台。主要输送介质有甲醇、乙二醇等。单机最大功率为75KW,单机最小功率为3KW,用电压为380V,本试车由施工单位、监理单位、建设单位及设备供应商一起参与。 三、试运程序及试运设备清单 1、试运程序 设备试运前检查→系统检查→设备加注油、脂→脱开联轴器→电机检查及旋转方向→电机2-4小时单试→联轴器装配→手动盘车→带负荷4-8小时试运→办理验收交接手续。 备注: 1)厂家说明书明确要求不需脱开联轴器的设备可整体试运; 2)设备脱开联轴器,电动机试运合格后,联轴器进行装配,并复查联轴器中心,并盘运转子,转子应灵活,无摩擦。 2、试车单机设备性能一览表,见附页。

项目组织设计及安装调试方案

项目组织设计及安装调试方案

项目组织设计及安装调试方案 3.3.1项目概况 根据《社会救助暂行办法》明确规定“县级以上人民政府民政部门应当建立申请和已获得社会救助家庭经济状况信息核对平台,为审核认定社会救助对象提供依据”。经过核对信息系统开展居民家庭经济状况信息核对,是全面建立居民家庭经济状况核对机制的重要内容,是落实《社会救助暂行办法》要求、提高对象认定准确性、促进公平公正的重要手段,是创新社会救助管理方式的重要举措。各地要把开展核对信息系统建设作为织密筑牢民生安全网的一项重要基础性工作来抓,增强责任感和使命感,认真履行职责,进一步加大工作力度,加快建设步伐。 构建统一的信息共享平台。信息共享平台能够实现数据共享和业务协同,是核对信息系统的重要组成部分。在服务内容方面,该平台能够实现各个节点的数据采集、汇总、整合、校核、查询、分发、交换等功能,满足信息查询、全文检索、比对分析、统计汇总等数据应用需求;在安全保障方面,各个节点均能提供访问控制、数据合法性检查、病毒查杀、加密传输、内容审计等信息安全保护机制;在运行管理方面,利用该平台可形成一个中心、多个节点的一对多集中管控模式,实现

运行监控的统一管理。 经过信息共享平台,充分利用民政部提供的数据资源,推动本地民政系统内部和与其它部门之间的信息共享和业务协同。各地要根据民政部的总体设计,部署数据交换节点,或逐步更新已有信息共享系统。在核对信息系统项目立项过程中,各地应全面细致地分析本地区部门之间以及上下级之间的信息共享需求,建立完善信息共享目录和动态更新机制。 建设地方数据中心的过程中,一是要尽量使用国家电子政务外网和民政广域网,上述两网无法全覆盖的地方,在保证高效安全的前提下,可利用专线网络进行补充;二是要配备专用的网络设备、数据库服务器、应用服务器等必要设备;三是要安装经济适用的操作系统、数据库等基础软件。各地在充分论证的基础上,可采用物联网、云计算、大数据处理、移动互联网等新技术,进一步提高信息化资源的利用效率和管理水平。 3.3.2项目总体方案 在项目中做好与建设方的配合措施,建设方在工程上起主导作用,为建设方服务是本我们永远追求的目标。本公司将在整个项目实施过程中,全面了解建设方的需求,掌握为建设方服务的内容,达到为建设方服务的效果和目的,最终实现工程项

投标人建议的安装、调试、验收方法或方案

1.1投标人建议的安装、调试、验收方法或方案 1.1.1系统整体调试 我方工程执行小组根据系统设计方案、应用平台设计方案和实施方案对集成项目中的网络、系统设备、应用平台进行调试。安装后的软硬件调试,其中包括电脑,中控,投影,幕布等是否能正常工作。工程完毕后,由双方共同测试验收。 1.1.2用户现场培训 我方工程实施小组在项目安装调试过程中,对用户方配合人员进行工程安装设臵及注意事项的现场讲解和培训,提高用户方人员对设备的使用维护,软件维护、网管、安全维护和管理能力。 1.1.3工程初验/终验 在“系统试运行”结束后,双方共同检验本项目的实际运行情况,并决定是否可以投入使用。 1.1.4具体的验收方案 1.1.4.1基本信息 甲方:建设单位/项目发包方 乙方: 乙方按照合同要求实行施工,从年月日至年月日乙方认为已经完工,要求甲方进行验收。 1.1.4.2验收项目 1.1.4. 2.1.产品设备验收 所有设备及功能符合合同要求(使用了合同规定的设备、数量符合、售后服务手续齐全) 阶段验收项目验收内容验收方式结果 验收前检设备到货 (见合同 1)外观到货验收□合格□不合格 2)型号、规格、数量到货验收□合格□不合格

查清单)3)设备相关说明书到货验收□合格□不合格 系统安装设 备 安 装 1)外观随工现场□合格□不合格 2)安装紧固性随工现场□合格□不合格 3)安装位臵随工现场□合格□不合格 4)安装工艺随工现场□合格□不合格 1.1.4. 2.2.兼容性验收 验收内容验收结果 端口规格验收是否支持VGA接口□是□否是否支持网络接口□是□否是否支持Console接口□是□否 多平台验收 是否支持Windows平台□是□否 是否支持其他平台□是□否串口设备支持 是否支持网络设备等□是□否 是否支持其他设备等串口设别□是□否电源控制设备是否能实现远程开关机□是□否是否不需在被控服务器中安装额外软件□是□否1.1.4.2.3.操作功能性验收 验收内容验收结果 操作界面是否为全中文界面□是□否远程访问鼠标控制方便,无明显延迟□是□否远程访问显示效果能至16Bit真彩,画面流畅□是□否远程访问能支持1280 X1024@75Hz分辨率□是□否在机房本地端操控时,支持鼠标操作□是□否