TEST REPORT

Test Phase: pilot test

Test Duration:2003-04-21 ~ 2003-05-14

Test Project Manager:chenliang Signature:陈亮Prepared by:chenliang Signature:陈亮Date:2003-06-10 Reviewed by:taomaoqi Signature:陶茂旗Date:2003-06-10 Approved by:hualin Signature:华麟Date:2003-06-11

T&R Dept. of Emerson Network Power Co., Ltd.

Test Report

Principal: 陈亮Reviewed by: 陶茂旗Approved by: 华麟

Contents

1. INTRODUCTION (3)

2. TEST STANDARD (3)

3. TEST ENGINEER AND TEST DURATION (3)

4. TEST ITEMS AND RESULTS (3)

4.1F UNCTION &P ERFORMANCE TEST (3)

4.2E NVIRONMENTAL T EST /T YPE TEST (7)

4.3EMC TEST (7)

4.4W HITE-BOX TEST (8)

4.5D IMENSIONS M EASUREMENT (8)

4.6M ARGIN TEST (8)

4.7R ELIABILITY TEST (8)

4.8S AFETY TEST (9)

5. TEST INSTRUMENTATION (9)

6. APPENDIX (10)

6.1T EMPERATURE-RISE R ESULTS (10)

6.2T YPE T EST R EPORT (10)

6.3 CHECKSUM (10)

Key Words: PS481000-5/100 (W54AAZ)

Abstract:This test is a pilot test. The test objects are PS481000-5/100 power system.

This report describes the details, the results and the problems during this test.

1. Introduction

The pilot test includes electric performance test and type test. The report describes the details, the results and the problems during the test. The new part of PS481000-5/100 is only rectifier and rectifier shelf. The AC/DC Distribution are same as old power system. The change of supervision unit is software. So main test are supervision program and rectifier shelf: RACK1000-5 (10 rectifiers) & RACK1500 (15 rectifiers). If no indication, the test result is RACK1500’s.

2. Test Standard

Q/DMBM1179-2003《Industry Standard for PS481000-5/100》

《Test specification of Power system》V3.1

3. Test Engineer and Test Duration

Test Engineer: ChenLiang

Test Duration: Apr.21, 2003 ~May.14, 2003

4. Test Items and Results

4.1 Function & Performance test

4.2 Environmental Test / Type test

Pass

refer to type test report: W54AAZ-TTT-3V1 4.3 EMC test

4.4 White-box test

The white-box test is not involved in power system test.

4.5 Dimensions Measurement

4.6 Margin test

The margin test is not involved in pilot test.

4.7 Reliability test

4.8 Safety test

5. Test Instrumentation

6. Appendix

6.1 Temperature-rise Results

Lab Ambient Temperature:22.0℃test system:RACK1500 Output: 56.4V/1518A

6.2 Type Test Report

Pass

Report Serial Number: W54AAZ-TTT-3V1

6.3 checksum

V1.52

M14C3U151: B60A

M14C3U152: 8FD9

M14C3U153: 70C6

M14C3U154: A9E8

7. 评审参考资料及测试过程资料

附件第 1 页共 21 页

附件第 2 页共 21 页

附件第 3 页共 21 页

附件第 4 页共 21 页

附件第 5 页共 21 页

附件第 6 页共 21 页

测试手段齐套率=100 %

说明:

未测试项目是指:

1、规格书中明确规定的性能、指标而没有测试的项目;

2、电性能测试规范、白盒测试规范、极限测试规范、异常测试规范、安规测试规范、EMC测试规范、环境测试规范等规范规定要测试的

项目而没有测试的项目。

统计:测试手段齐套率=(应测试的项目数-因为测试手段不齐全而未测试项目数)/ 应测试的项目数×100%

附件第 7 页共 21 页