塞拉利昂水泥厂项目桩基施工方案

Cement terminal project pile foundation construction program in Sierra Leone

一、旋挖成孔灌注桩施工 Rotary drilling hole pile construction

1.工程量1000M3砼 The project amount 1000M3 concrete

2.施工技术 Construction Technology

本工程项目桩基施工采用旋挖成孔工程钻机,在施工前须对场地进行清表、清障、平整、压实,使场地表面耐力不小于100Kpa 。施工时设置泥浆池、沉定池、泥浆循环系统和废浆池,沉淀池的容积两倍于一根桩的体积,储浆池容积大于16m3,以满足钻孔需要。

Pile Foundation Construction of the project use a rotary drilling rig,before construction,we need to cleared the table , wrecker , leveling , compaction venue to make sure the surface endurance is not less than 100Kpa.During construction, we need to set Mud pools , sedimentation tanks , mud circulation system and waste slurry pond.To meet drilling demand, Sedimentation tank volume is twice the volume of a pile , storage slurry pond volume should be greater than 16m3

3.工艺流程 Process 桩位定位埋设护筒钻机就位钻孔成孔质量检测

钢筋笼吊放泥浆制备,注浆跟进

砼浇筑养护成桩检测

钢筋笼制作、验收

4.操作工艺 Operation process

(1)测量定位 Measurement Positioning

(a )采用全站仪按照图纸测定位置并做好标色。

Use total station measurement position in accordance with the drawings

and make a standard color .

(b )利用水准仪测定护筒标高其误差不大于10MM 。

Level determination Casings for elevation of the error should not more than 10MM

(2)栓桩:桩位位置确定后,用两根相互垂直的十字线中心相交于桩点,

并定出他的控制点,做好标识妥善保护。

Bolt piles :once piles bit position is determined,we use two mutually perpendicular crosshairs center intersect at the pile point, set his control point and marked properly protected.

(3)钻机就位:履带坐落的位置应平整,坡度不大于3度,避免因场地不平整产生动力损失,倾斜、位移,重心高时还会引起安全事故。

Rig in place : Tracked located position should be flat , the slope is not greater than 3 degrees and avoid venue uneven loss of power , tilt , displacement , high center of gravity will also cause accidents

(4)对准桩位:首先调整旋挖机的桅杆,使之处于垂直状态,让钻头对准桩点。

Alignment Pile : First adjust the auger mast in a vertical state and the drill bucket should be align with the pile point .

(5)埋设护筒:定出十字控制点后,可采用钻机进行取土,钻至设计深度进行护筒埋设。

Bury casing:set cross control point the we use the rig dig the hole until the depth we can start to bury the casing.

护筒采用厚度6mm的钢板制作而成,长度在2m左右,护筒的直径为850mm,为防止钻进施工中护筒外圈返浆造成塌孔和护筒脱落,护筒底部应坐落在稳定的土层上,并且进入原土0.3-0.5m。护筒埋设位置应准确其中心点与桩定位点误差不大于50mm,并应保证护筒的垂度和水平度。

The casing was made by 6mm thick steel plate,the length should be around 2m and the casing diameter is 850mm. In order to prevent the outer tube Protection Drilling returned to the pulp caused the hole collapse and retaining barrel off the bottom of the pile casing should be located in the stable on the soil and into the original soil 0.3 -0.5m。Casing laying position should be accurate center point,pile anchor point error is not more than 50mm and also should ensure Casing for vertical and horizontal

(6)泥浆制作:采用现场所泥浆搅拌机或人工制作,宜先加水并计算体积,在搅拌下加入规定的膨润土,纯碱以溶液的方式在搅拌下缓缓加入,搅拌时间一般不少于3分钟,必要时还可加入其他外加剂,以增大泥浆比重。另拌制泥浆应根据工艺和穿越土层情况进行配合调整,膨润土泥浆性能指标制备可按下列参数(砂土层);粘度19-25%;比重1.18-1.30;含沙率小于6%,胶体率95%,PH值7.0-9.0。

Mud production:site slurry mixer or artificially produced advised adding water and calculating the volume,after that added with stirring a predetermined bentonite, soda ash solution with stirring was slowly added and the stirring time is generally less than 3 minutes , if necessary we can also add other admixtures to increase the mud weight. Besides, Mixing mud with the adjustment should be based on the process and through the soil , and the bentonite slurry performance indicators prepared according to the following parameters ( sand layer ) ; viscosity 19-25 % ; proportion 1.18 - 1.30 ; sandy rate less than 6% , colloidal rate 95%, PH value 7.0-9.0.

(7)旋挖钻钻进成孔Rotary Drill drilling hole

(a)以钻具钻头自重和液压缸加压作为钻进压力,每一回次的钻进量应以深度仪所示值为参考依据,以钻机说明书钻速,钻压扭矩为指导,进尺适当,不多钻也不少钻。钻多,辅助时间加长。钻少,回次进尺少,效率降低。

We take drill weight and hydraulic cylinder pressure as the drilling pressure , drilling depth meter should be shown the value reference for speed drilling rig manual the WOB torque for guidance , footage appropriate , not much drill is also a lot of drilling . Drill multi Auxiliary longer . Drilling less footage back to the times , reducing efficiency

(b)当钻头内装满土、砂后,将其提升上来,注意地下水位变化情况,并灌注泥浆。

When the drill is filled with soil and sand , we raise it up and pay attention to the groundwater level changes then perfuse mud

(c)旋转钻机将钻头内的土卸出,用铲车及时运走,运离不影响施工作业区。

Rotary rig to drill within the soil unloaded then transported with a forklift in a timely manner and transported from the impact of the construction work area (d)关闭钻头活门,将钻头转回孔口,降下钻头继续钻进。

Close the shutter then reversal of the drill orifice , lower the drill bit to continued drilling

(e)为保证孔壁稳定,应视表土松散层厚度,孔口下入长度适当的护筒,并保持泥浆面高度,随泥浆损耗及孔深增加,应及时向孔内补充泥浆,以维持孔内压力平衡。

Should be considered to ensure the stability of hole wall the topsoil loose layer thickness orifice into the appropriate length casing Protection , then keep the mud surface height with mud loss and deep hole should be timely supplement to the hole in

the mud , in order to maintain the hole pressure balance.

(f)提升钻头过快,易产生负压,造成塌孔.一般钻头提升速度控制在,装满渣土钻头提升0.937M/S,空钻头升降1.210M/S。

If we improve drill too fast , its easy to produce negative pressure, which will result in hole collapse .Usually when a drill filled with muck,the lifting speed should be controlled within 0.937M/S and for empty drill,the speed should be 1.210M/S (g)在桩端持力层钻进时右能会由于钻头的提升引起持力层的松驰,因此在接近孔底标高时应注意减小钻头的提升速度。

Due to the enhancement of the drill in the pile end bearing stratum drilling may cause relaxation of the bearing layer elevation thus when drilling near the bottom of the hole we should pay attention to reduce the lifting speed of the drill

(h)清孔:因旋挖钻用泥浆循环,在保障泥浆稳定的情况下,(清除孔底沉渣一般用双层底捞砂钻头,在不进尺的情况下,回转钻头使沉渣尽可能地进入斗内,反转,封闭斗门,即可达到目的。因本工程地质-24M以下为粘土层,视具体情况,确定清孔方法,确保沉渣厚度符合要求。

Clean-up holes :Because rotary drilling use mud circulation , so under the circumstance of stable mud protection ( when clear the hole bottom sediment generally we do with double bottom bailing bit , in the case of footage , rotary drill bit so that sediment went into the bucket , inverted closed shutter and this can achieve the purpose .Because of the engineering geology -24M below are the clay layer so we should depend on the specific situation then determine hole cleaning methods , to ensure the sediment thickness required

(i)钢筋笼制作:钢筋笼按设计图纸及相关规定要求制作。钢筋表面应洁净,使用前应将表面污垢、漆皮、鳞锈等清除干净;钢筋应平直,无局部弯曲、无裂纹、断伤。钢筋接头焊缝均匀、饱满、光滑;不得有裂纹、塌陷、咬边、夹渣,钢筋表面无明显烧伤等缺陷。每批焊条都应有出厂合格证。

The reinforcement cage production : steel cage was designed according to drawings and related regulations requirements. Reinforced surface should be clean before using.We should clean surface dirt , patent leather , scaly rust and the reinforcement should be straight with no local bending , no cracks , off injured. Reinforced joints should be uniform weld , full, smooth, without cracks , collapse , undercut , slag , steel surface burns and other defects . Each batch of electrodes should have factory certification

钢筋笼安装,视设计桩长的配筋长度及配备的工程吊车技术参数的实际情

况,进行分段制作,遂段吊放钢筋笼,各段之间根据主筋直径按设计要求采用单面电焊连接。双点起吊,确保钢筋笼不变形。当钢筋笼吊放至设计位置后,在孔口固定钢筋笼上端。

Reinforcement cage installation: According to the actual situation of the design length of pile reinforcement length and with engineering crane technical parameters , we should produce in segment , then the segment dipping steel cage main reinforcement diameter between paragraphs design requires single-sided welding . Using two-point lifting to ensure no deformation of the reinforcement cage . When the reinforcement cage was dipping to the design position,we fixed reinforcement cage in the upper of the orifice.

钢筋笼保护层垫块采用现场预制砂浆圆块。

The protective layer of the reinforcement cage pads use the site prefabricated mortar round block

(j)下钢筋笼,钢筋笼场内运输可采用人工抬运或加托架转运,不可使钢筋笼产生永久变形;钢筋笼采用双点起吊,对正后缓缓下入,不准强行压入。

Reinforcing Steel Cage: Reinforcement cage inside can be transported by artificial lift or bracket transport and the cage cannot be made permanent deformation; The reinforcement cage use dual point lifting , slowly down into the positive , not allowed to press into by forcement.

(k)下导管:导管连接要密封、顺直,导管下口离孔底约300mm就可,导管平台应平整,夹板牢固可靠。

Lower conduit : conduit connection must be sealed , straight, catheter down until the under mouth about 300mm from the bottom of the hole( the catheter platform should be smooth and plywood robust)

当钢筋笼吊放定位后,就可在孔口安放导管平台,吊放导管。导管采用直径250mm钢制标准导管,各节导管及其与承料斗间均以丝扣连接。导管在吊放前,在地面连接作水压试验,确保无渗漏方可使用。

When the reinforcement cage dipping positioned , the orifice can be placed with catheter platform then we start to dip catheter . The conduit was taken the 250mm diameter steel standards catheter, sections catheter and the Order of the hopper are threaded connection . Catheter before dipping in the ground connection for water pressure test to ensure no leakage before use

(l)浇筑砼:Pouring concrete

①钢筋笼,导管下放完毕,做隐蔽检查,必要时进行二次清孔,验收合格

后,浇筑砼。砼采用现场搅拌。

After decentralization of the reinforcement cage , catheters ,we need to do covert checks , and if necessary,we will do a second hole cleaning , after acceptance ,we can pour concrete( Concrete are mixing on site)

②预拌砼应具备设计的强度等级,有良好的和易性,塌落度宜180-220mm。

Ready-mixed concrete should have the strength grade design , good workability , and slump should be 180- 220mm

③初次灌注砼量应严格按照要求计算首灌砼立方量,以其数量必须满足充满孔底,并埋管深度不少于0.8m。

Initial perfusion concrete amount calculated in accordance with the requirements should be strictly cubic amount of initial concrete irrigation and the Quantity must fully filled the bottom of the hole meanwhile the buried depth should not less than 0.8m

④导管埋深,保证2-4m,随着砼面上升,随时提拨和拆除导管,以使导管在砼中始终保持2-4m。且在首批砼的初凝时间前完成砼浇灌,如无法保证,可经过试验给砼添加缓凝剂。为使砼密实,可利用吊机升降系统慢速振插导管。终灌时,按桩顶设计标高正确掌握最后灌注的砼量,使实灌砼面高出设计顶面1D 以上,以确保清除浮浆后桩顶砼的完整性。在水下砼灌注时,要勤测砼塌落度,按要求做好试块,作为质量控制及质量评定的依据。

Bury conduit in deep and make sure 2-4m,with the rising concrete surface,set aside at any time and removal of the catheter to make sure the catheter always keep in concrete 2- 4m .Besides,we need to finish perfusing the concrete Before the initial setting time of the first concrete and if this can not be guaranteed , we can add retarder to the concrete through test . Crane lifting system can be used to make concrete dense slow vibration catheterization .we can use Crane lifting system the slow vibration inserted catheter to make sure concrete compaction. Design elevation of the top of the pile when the final irrigation , proper understanding of the last perfusion concrete amount , the real irrigation concrete surface above the the design top surface 1D to ensure the integrity of the top of the pile of concrete to remove laitance . Perfusion of the underwater concrete to ground measured concrete slump , required to do the test block , as the basis for quality control and quality assessment.

⑤砼灌注过程中,为防止钢筋笼上浮,应采取如下措施,在孔口固定钢筋笼上端;灌注时间尽量缩短,防止砼进入钢筋笼时流动性变差,当孔内砼进入钢筋笼1-2小时,应适当提升导管,减少导管埋深,增大钢筋笼在下层砼中的埋置深

During Concrete casting process , in order to prevent steel cage floating we should take the following measures , fixing the upper end of the orifice reinforced cage ; making perfusion time as short as possible to prevent concrete to enter rebar cage which can cause flow variation , when the hole in the concrete into the rebar cage 1-2 hours , we should be appropriate to enhance the catheters to reduce catheter burial depth and increasing the embedment depth of the reinforcement cage in the lower concrete

⑥灌注结束时,控制桩顶标高,砼面应超过设计标高1D以上,保障桩头质量。

When perfusion was over , we must control the elevation of the top of the pile , the concrete surface should be more than the design elevation 1D to protect the pile head quality

⑦钻机移位:成孔施工完毕且验收合格后,移至下一桩位。另外当桩距(中心距)小于5m时,后一根桩钻孔必须在前一根桩砼灌注完成后24小时才能开钻。

The rig shift : move to the next one bit after the construction is completed into the hole and acceptance . In addition , when the pile spacing ( center distance ) is less than 5m , the next pile drilling must be the first 24 hours after a pile of concrete perfusion completed

(m)雨季施工Rainy season construction

①露天使用的电气设备,天关箱的防雨措施应可靠,放置较高位置,电焊机等导电设备应加保护罩。旋挖机雨期施工应有防雷接地并定期检查。

Open use of electrical equipment , switch boxes , water-resistant measures should be reliable , placed a higher position.Welding machines and other conductive equipment should be added to the protective cover . Rotary Drilling Rig working during rain period should be lightning protection,grounding and check regularly

②电气设备的接地保护就牢固可靠,漏电保护装置动作灵敏,操作人员应使用绝缘工具。检查有无地基塌陷情况,在旋挖钻机行走时,务必避开塌陷地段,桅杆还应适当向后倾斜一个安全角度。

Ground protection of electrical equipment on a solid , reliable , sensitive action leakage protection device , the operator should use insulated tools and check for foundation collapse during rotary drilling rig walking then be sure to avoid the collapse of the lot , the mast also should be appropriate backward tilt a safety point of

③钻机上下托板时,应有防滑措施,避免侧滑引起的安全事故。

Rig up and down the pallet should be non-slip measures to prevent security incidents caused by the sliding

④水管、导管、泥浆管不用时,应清理干净,整好平放。

When water pipes, ducts , mud tubes are not used, we should clean up the put them flat

⑤施工现场办公区、生活区所用电器装置应安全、可靠。在雷电频落区域,应加装防雷接地设施。

Construction site office area, living area with electrical installations should be safe and reliable . Installation of lightning protection and grounding facilities in the lightning frequency off the area are very important

二、砼配比设计要求Concrete mix design requirements

1.原材料及配合比Raw materials and mixture ratio

(1)水泥应符合相关要求,采用免检水泥并经过测试,严禁使用快硬型水泥,水泥必须有出厂合格证,如果水泥出场日期超过三个月对水泥质量有怀疑时应视不同情况进行复检,复检合格后方可使用。水泥在运输及堆放过程中应有防雨防潮措施,不同品种、标号、生产厂家的水泥严禁使用在同一根桩砼中并分别堆放。

Cement should comply with the relevant requirements , inspection-free cement and tested , prohibited the use of rapid hardening cement , the cement must have factory certification , cement exit date is more than three months then a suspect should be retested depending on the quality of the cement , complex inspection qualified before use . Cement transport and stacking process should be rain and moisture measures , different varieties , label , cement manufacturers cannot use with a pile of concrete and stacked separately

(2)石子的质量应符合相关要求,每批石料进场应有质保单。碎石的粒径采用5-40mm,5mm筛余量应为90%-100%,40mm筛余量大于5%。石料堆场应选干净处,严禁混入沙土杂质。

The quality of the stones should comply with the relevant requirements of each batch the stone approach should warranty single . Gravel particle size should be 5 -40mm the 5mm sieve margin should be 90 % -100 % and the 40mm sieve margin should be greater than 5 % . Clean stone yard to be elected at non- mixed sand impurities.

(3)沙的质量应符合相关要求,选用级配合理、质地坚硬、颗粒干净的中粗砂,砂进场每批要有合格证,砂的模数控制在2.3-3.0之间,在储运堆放过程中防止混入杂物。

Sand quality should comply with the relevant requirements , selection of gradation, hard texture and clean particles of grit. sand approach each batch should have a certificate , the modulus of the sand control in is between 2.3-3.0 , stacked in the storage and transportation process to prevent mixed with debris

2.混凝土搅拌Concrete mixing

施工现场设砼搅拌站,由JS750型搅拌机、沙石堆场和水泥库组成。砼搅拌时应严格按配合比称重砂、石、外加剂。砼原材料投量允许偏差:水泥为±2%;砂石土为±3%;水、外加剂为±2%。原材料投料时应依次加入石、砂、水泥和外加剂,砼的搅拌时间不少于90S。砼搅拌过程中及时测试坍落度和制作试块,拌好的砼应及时浇筑,若出现离析现象应重新搅拌,砼坍落度控制在18-22CM。

Construction site set concrete mixing station , by the JS750 -type mixer, sand yard and cement silo . Concrete mixing should be strict with the ratio of the weighing sand , stone , admixtures . Allowable deviation of concrete and amount of raw materials : cement ± 2 % ; the gravel soil ± 3% ; water , admixtures of ± 2 % . Raw material feeding should then added to the stone , sand , cement and admixtures , concrete mixing time should not less than 90S . Test the Slump and production test block during concrete mixing process in a timely manner , the concrete should be marinated pouring segregation phenomenon should be re-mixed concrete slump control 18- 22CM

3.砼浇筑Concrete pouring

按相关要求制作试块,试块为150×150×150MM,每根工程桩做一组试块,清水养护28D后,送交测试,试块脱模后及时放进现场砌置的水池内养护。

Test block, according to the relevant requirements of the production test block should be 150 × 150 × 150MM, each pile do a group of test block and clean water after 28 days of curing , sent to test into the scene in a timely manner after ejection of the test block puzzle set within the conservation pool

三、工程质量标准及质量保证措施

Engineering quality standards and quality assurance measures

本工程施工及验收要求遵循相关的标准规定。

The construction and acceptance requirements follow standard regulations . (一).工程质量标准Engineering quality standards

1.原材料和砼强度保证符合设计要求和相关的规定。

Raw materials and concrete strength to ensure compliance with design requirements and other relevant provisions .

2.成孔深度符合设计要求,孔底沉渣厚度小于10CM。

Drilling depth can meet the design requirements ., sediment thickness of the bottom of the hole is less than 10CM

3.实际浇注量不小于计算体积。

The actual pouring amount is not less than the calculated volume .

4.浇筑后的桩顶标高及浮浆的处理符合设计要求和施工相关规定。

The elevation of the top of the pile after pouring and floating pulp processing to meet the design requirements and construction of the relevant provisions

(二)允许偏差项目Tolerance variation project

1.成桩后的桩孔中心位置偏差,中间桩小于1/4D;边桩不小于1/6D。

Deviation into a pile after pile hole center position , the middle of the pile is less than 1/4D; side pile is not less than 1/6D

2.钢筋笼的制作:Reinforcement cage production :

(钢筋保护层:50mm);Reinforced protective layer : 50mm

主筋间距偏差:±10mm;Main reinforcement spacing deviation : ± 10mm;

箍筋间距偏差:±20mm;Stirrup spacing deviation : ± 20mm;

钢筋笼直径偏差:±10mm;Reinforcement cage diameter deviation : ± 10mm;

钢筋笼总长度偏差:±100mm;The total length of the reinforcement cage deviation : ± 100mm;

钢筋搭接长度:≥10d;Reinforced Lap length : ≥ 10d;

焊缝宽度:≥0.7d;Weld width : ≥ 0.7d;

焊接厚度:≥0.3d。Welding thickness : ≥ 0.3d.

3..桩垂直度小于1%。Pile vertical degree is less than 1%.

4..砼施工Concrete Construction

砼强度等级大于设计砼强度等级;Concrete strength rating is higher than the design concrete strength rating ;

砼坍落度18-22cm 18-22cm concrete slump

主筋保护层厚度≥75mm;main reinforcement protection layer thickness ≥ 75mm;

所使用的材料必须具有质量保证书和检测试验合格报告;

The material used must have a quality assurance books and testing compliance

report ;

成桩砼质量连续完整,无断桩、缩径、夹泥现象,浇筑砼密实度要好,桩头砼无疏松现象。

The quality of the concrete piling is continuous complete , no broken pile necking silted phenomenon , pouring concrete density is better , trailer coupling concrete without loose

(三)质量保证措施Quality assurance measures

1..管理措施Management measures

(1)公司的工程技术部直接对该项目的工程质量进行监督和控制,直接掌握质量动态,指导全面质量管理工作,展开严格岗位责任制,对各工序、工种实行检查监督管理,行使质量否决权。

Company's engineering department directly supervise and control the quality of the project and to gain direct control over the quality of dynamic guidance of total quality management , expand the strict system of personal responsibility to implement the inspection and supervision of the management of various processes , type of work , the exercise of the quality of the veto

(2)对主要工序设置管理点,严格按工序质量控制体系和工序控制点要求进行运转。

Setting management points to major process and we should be in strict accordance with the requirements of the process quality control system and process control point operation

(3)实行三级质量验收制度;每道工序组100%自检;质量100%检验;工地技术负责30%抽查。

The implementation of the three - tier system of quality inspection ; each process group 100% self-test ; quality 100% inspection ; site technology is responsible for 30% of spot checks

(4)认真填写施工日记。Fill in construction Diary .

2.技术措施Technical measures

(1)桩轴线及桩位放样,定位后要进行复测,定位精度误差不超过5mm。埋设护筒时由测量人员到场,用仪器校正中心后方能固定护筒,保证护筒的垂直度。

Loft pile axis and piles bit , to retest after positioning , the positioning accuracy error of should not more than 5 mm . when bury the casings,the surveyor should at the scene, we should fix the casings with the center of instrument calibration, to ensure

the verticality of the casings

(2)钻机定位,旋挖钻机桅杆必须垂直,不合要求随时纠正。

Rig positioning , rotary drilling rig mast must be vertical,if not,we should correct at any time.

(3)孔底沉渣检测小于30cm

The hole bottom sediment detect is less than 30cm

(4)确保钢筋笼的垂直度

Ensure the verticality of the reinforcement cage

(5)砼搅拌时砂石料经过磅称称重,误差不超过3%,严格控制水灰比。根据现场砂石料的含水率情况调整加水量。每根桩做1-2次坍落度试验。

Aggregate concrete mixing after weighing scales, weighing error should less than 3% , and we should be strict control of the water-cement ratio . Adjust the amount of water according to the site aggregate moisture content and each pile we should have 1-2 slump test

(6)根据地层特点及时调整泥浆性能,防止钻孔扩径、缩径和坍塌,控制好砂层土的泥浆相对密度,确保孔壁稳定。

Timely adjustment mud performance according to the formation characteristics in order to prevent drilling flaring , necking and collapse , and good control of the sand layer soil slurry relative density to ensure the stability of the hole wall

四、施工总体计划Construction master plan

(一)施工总体计划Construction master plan

本工程施工合同约定:180 天。根据工期要求。桩基设计及场地等条件,计划进旋挖钻机一台及其配套设备。

The construction contract : 180 days. According to the schedule requirements . Pile foundation design and site conditions , we plan to purchase a rotary drilling rig and its ancillary equipment

施工中采用隔桩跳打(保证相邻桩距大于4倍桩径),钻孔、砼浇筑分开作业的方式进行施工。同时根据生产进程及时优化,提高施工效率。

We take the skip drilling during construction ( to ensure adjacent pile spacing is greater than four times the pile diameter ) , drilling,concrete pouring operations separately for construction . Simultaneously we optimized according to the production process in a timely manner to improve the efficiency of construction

(二)施工进度计划Construction schedule

根据以往施工经验及网络优化成果,施工φ750工程桩用时情况分析如下:

According to the construction experience and network optimization based on past achievement ,Constructiing the φ750 project pile time use,refer to the following analysis:

钻机移位、就位及开钻准备;The rig shift , in place and prepare drilling

钻进成孔;Drilling into a hole

吊放钢筋笼、导管;Dipping reinforcement cage and catheter ;

水下砼浇筑;Underwater concrete pouring

根据以上分析,一台旋挖转机每天(8h)可成孔 2 个,砼浇筑成桩 2 个。

Based on the above analysis , a rotary rig work every day (8h) can dig 2 holes and two concrete pouring into piles

八主要设备,工具配置Major equipment , configuration tools

根据土层特点,桩径以及桩长情况,选用8R-30旋挖转机,制浆设备,泥浆泵。

Based on soil characteristics , pile diameter and pile length ,we choose 8R-30 rotary drilling rig , pulping equipment , mud pump

主要设备工具表如下Main equipment tools table as following

序号serial number 名称

Name

型号

Model

数量

Quantity

价值(万元)

Value

备注

Note

1 旋挖钻机Rotary drilling rig 1

2 泥浆泵Mud pump 2

3 制浆机Pulper 1

4 砼搅拌机Concrete mixer 1

5 液压汽车吊Hydraulic truck crane 2

6 翻斗车Dumpers 5

7 电焊机Welding machine 3

8 挖掘机Excavator 1

9 装载机Loaders 1

10 排污泵Sewage pump 2

11 泥浆比重计Mud hydrometer 2

12 水准仪Level 1

13 全站仪Total station 1

14 钻斗Drilling bucket 1

15 导管Catheter/ conduit 1

16 导管操作平台 1

17 上料斗Hopper 1

18 发电机组Generator sets 2

19 清水泵Clean Water Pump 2

20 砼试模等Concrete tryout 12

日常常见中文英文对照表

handbag手提包 hatbox帽盒 cosmetics case 化妆箱 gloves手套 wrist watch手表 belt腰带 pendant项饰 necklace项链 neck scarf围巾 earrings耳环 sun glasses太阳镜 ring戒指 bracelet手链, 手镯 tie领带 cuff links袖扣 ascot宽领带 hair net发网 brush毛刷 nail polish指甲油 cream rinse营养发水 hair spray发胶 powder puff粉扑

face powder粉 compact带镜粉盒 astringent化妆水 perfume香水 skin milk乳液 cold cream油底霜 atomizer喷雾式香水 hand mirror手镜 bobby pin发夹 false eyelashes 假睫毛 lipstick口红 wig假发 tissue面纸 purse手包 brooch胸针 shawl披肩 neckerchief领巾 台湾是中国神圣领土不可分割的一部分Taiwan is an inalienable part of the inviolable territory of China. 〃台湾同胞Taiwan compatriots 〃台湾、香港、澳门保持原有的资本主义制度和生活方式长期

不变Taiwan, Hong Kong and Macao will retain the current capitalist system and way of life for a long time to come. 〃炭疽anthrax 〃踢皮球pass the buck 〃逃废银行债务evasion of repayment of bank loans 〃韬光养晦hide one’s capacities and bide one’s time 〃讨价还价wheel and deal 〃统筹兼顾make overall plans adn take all factors into consideration; overall planning and all-round consideration 〃同乡会an association of fellow provincials or townsmen 〃筒子楼tube-shaped apartment 〃团队精神team spirit; esprit de corps 〃团结就是力量Unity is strength. 〃退耕还林还草grain for green 〃退耕还林还牧convert the land for forestry and pasture 〃鸵鸟政策ostrich policy; ostrichism 〃脱贫致富?cast (shake, throw) off poverty and set out on a road to prosperity? 〃拖欠工资arrears of wage W 〃挖墙脚undermine the foundation of sth.; cut the ground

韩-中-英姓氏对照表

韩国姓氏-中英韩对照表 姓氏中文英文其他可以使用的表示方法(越左边的越常用) ?贾Ga Ka,Kah,Gah ?简Gan Kan,Khan ?葛Gal Kal,Garl,Gahl,Karl ?甘Gam Kam,Kahm,Karm ?康姜Gang Kang,Kahng,Kwang,Khang 强刚疆 ?介Gae ?甄坚Gyeon Kyun,Kyeon,Kyen,Kyoun,Kyon,Kwion ?景庆Gyeong Kyung,Kyoung,Kyeong,Kyong,Kung ?桂Gye Kye,Kay,Kae,Gae,Keh ?高Go Ko,Koh,Goh,Kho,Gho,Kor ?桥Gyo Kyo ?曲Gok Kok ?公孔Gong Kong,Kohng,Koung,Goung,Khong ?郭Gwak Kwak,Kwag,Kwack,Gwag,Koak ?丘具邱Gu Koo,Ku,Goo,Kou,Kuh ?国菊鞠Guk Kook,Kuk,Gook,Kug,Gug,Cook ?君Gun ?弓Gung Koong,Kung,Kwoong ?Gwok Kweag ?权Gwon Kwon,Kweon,Kwun,Gwon,Kwan

?斤Geun Geun,Keun ?琴Geum Keum,Kum,Gum,Guem,Kuem ?奇箕Gi Ki,Kee,Key,Gee,Ky,Khee,Kie ?吉Gil Kil,Gill,Khil,Kill,Keel ?金Gim Kim,Kym ?罗Na Ra,Nah,La,Rha,Rah ?栾Nan ?南Nam Nahm,Nham,Narm ??南宮Namgung Namkung,Namkoong,Namgoong,Namkoung, Namgoog,Namgooing ?浪Nang Nahng,Lang ?乃奈Nae Na ?路卢鲁No Noh,Roh,Ro,Rho,Nho ?雷赖Noe ?楼Nu ?段单端Dan Dahn ?谭Dam ?唐Dang Tang ?大Dae Dai,Dea ?道都陶Do Doh,Dho,To,Doe ?Dokgo Dokko,Toko,Tokko,Dockko ?敦顿Don

中英文无线电陆空通话范例教程

FSAAC中英文无线电陆空通话范例教程(空管飞行必读) 范例航线:上海浦东国际机场(ZSPD)-北京首都国际机场(ZBAA) 航向介绍:该航线经上海情报区、北京情报区。在上海情报区的空域范围内,经过上海管制区、济南管制区;在北京情报区的空域范围内容,经过北京管制区。航路里程是643海里,选用浦东机场起飞跑道为17L,选用首都机场落地跑道36R。 C:Controller(管制员)P:Pilot(飞行员) 1、申请停机位 P:浦东地面,晚上好,东方123,机型波音767,申请停机位。 Pudong GND, Good evening,CES123,Boeing767,request stand. C:东方123,浦东地面,停机位廊桥205号。 CES123,GND,Stand/spot/bay/gate/parking bay 205. 站调席位发放停机位时,须使用中文,严禁使用“GATE xxxx”、"PAR KINGxxxx"等英文。机组收到机位、航线后,直接联系放行。 P:停机位廊桥205号,东方123。

Bay 205,CES123.————————————————————————— 2、申请放行 P:浦东放行,晚上好,东方123,停机位廊桥205号,机型波音767,通波ALFA已抄收,申请放行至北京。 Pudong DEL,Good evening,CES123, stand 205,boeing767,I have information A,reque st IFR clearance to Beijing. 联系放行时,首先你需要告诉管制你在哪儿(机位),你的机型,你是否抄收机场情报通波(包含起飞使用跑道,起始上升高度,标准离场程序,离场频率及气象信息;怎样抄收机场ATIS情报通波如何抄收请见:&highlight=ATIS)以及你要到哪儿去(目的地)。 C:东方123,浦东放行,许可放行至北京,按计划航路飞行,预计使用跑道17L,起始高度900米,修正海压1012,PIKAS11号离场,离场频率,应答机5001。 CES123,DEL,cleared to Beijing via flight planned route,expect runway 17L,initial cli mb 900m on QNH1012,PIKAS11 departure,departure frequency ,squawk 5001. 放行许可里必须包含许可放行至某个目的地和使用计划航路,使用跑道,起始高度,离场程序,离场频率以及应答机编码。

无线传感器网络论文中英文资料对照外文翻译

中英文资料对照外文翻译 基于网络共享的无线传感网络设计 摘要:无线传感器网络是近年来的一种新兴发展技术,它在环境监测、农业和公众健康等方面有着广泛的应用。在发展中国家,无线传感器网络技术是一种常用的技术模型。由于无线传感网络的在线监测和高效率的网络传送,使其具有很大的发展前景,然而无线传感网络的发展仍然面临着很大的挑战。其主要挑战包括传感器的可携性、快速性。我们首先讨论了传感器网络的可行性然后描述在解决各种技术性挑战时传感器应产生的便携性。我们还讨论了关于孟加拉国和加利 尼亚州基于无线传感网络的水质的开发和监测。 关键词:无线传感网络、在线监测 1.简介 无线传感器网络,是计算机设备和传感器之间的桥梁,在公共卫生、环境和农业等领域发挥着巨大的作用。一个单一的设备应该有一个处理器,一个无线电和多个传感器。当这些设备在一个领域部署时,传感装置测量这一领域的特殊环境。然后将监测到的数据通过无线电进行传输,再由计算机进行数据分析。这样,无线传感器网络可以对环境中各种变化进行详细的观察。无线传感器网络是能够测量各种现象如在水中的污染物含量,水灌溉流量。比如,最近发生的污染涌流进中国松花江,而松花江又是饮用水的主要来源。通过测定水流量和速度,通过传感器对江水进行实时监测,就能够确定污染桶的数量和流动方向。 不幸的是,人们只是在资源相对丰富这个条件下做文章,无线传感器网络的潜力在很大程度上仍未开发,费用对无线传感器网络是几个主要障碍之一,阻止了其更广阔的发展前景。许多无线传感器网络组件正在趋于便宜化(例如有关计算能力的组件),而传感器本身仍是最昂贵的。正如在在文献[5]中所指出的,成功的技术依赖于

网页设计中最常见的30款英文字体

网页设计中最常见的30款英文字体 关于英文字体,对我们网页设计师朋友们来说一定并不陌生,即使我们很少做英文语系的网站,但在浏览国外网站的时候,大家一定都会有或多或少的认识。其实不单单是在网页中,很多移动操作系统和浏览器中都广泛使用了今天我们即将介绍的这些字体。 想必大家也都能猜出来像Arial、Helvetica 这种大名鼎鼎的字体肯定在里面了,那么还有什么呢?一起来详细了解一下吧! 首先,补充个小知识: 网页设计中的英文字体,一般有以下五类: serif(衬线) sans-serif(无衬线) monospace(等宽) fantasy(梦幻) cuisive(花体) 一、网页设计中最常见的无衬线字体 在常见的两种字体风格中,衬线体的笔划感太”过”,不是特别的商业。随着瑞士设计风格的大力推广,无衬线字体变得愈发流行起来。 建议: 个人认为Tahoma 以及Verdana 字符编码效果最好,适用于多种环境 Arial 字体族科:Arial, “Helvetica Neue”, Helvetica 变体: Arial:有时称为Arial Regular以便与Arial Narrow区别,其包括Arial、Arial Italic(斜体)、Arial Bold (粗体)、Arial Bold Italic(粗斜体)和Arial Unicode MS Arial Black:此字体的特色在于其笔画相当的粗,包含Arial Black、Arial Black Italic(斜体) Arial Narrow:为Arial的细瘦版本,包含Arial Narrow Regular、Arial Narrow Bold(粗体)、Arial Narrow Italic(斜体)和Arial Narrow Bold Italic(粗斜体) Arial Rounded:包含Arial Rounded Bold(粗体),此字体可在微软韩文字体Gulim找到 ——以上来自百度百科

无线电通信用英语

第1篇:有关问候的用语 (1)Good morning 、Good afternoon、 Good evening! 早上(下午、晚上)好! 比如我们这里的下午欧洲是上午、我们的中午十一点多日本已过了十二点 (2) Very good morning to you,my friend!你好,早安,我的朋友!(3) Hello,my friend!你好,我的朋友 (4)I’m very glad to meet you.非常高兴遇见你。 第2篇:有关感谢联络的用语 (1) Thank you for coming back to my call. 谢谢你回答我的呼叫。(2) Thanks for your call. 非常感谢你的呼叫。 (3) Thanks for the nice QSO.(Short QSO,nice contact) 非常感谢这次好的直接联络(短促的联络、好的联络)。 (4) Thanks for the nice report. 非常感谢你的报告。 (5) thank you so much for the best enjoyable contact. 非常感谢这次愉快的联络。 (6) Thank you very much for the information. 谢谢你告诉我这些消息。 (7)I’m very glad to meet you.遇到你非常高兴。 (8)I’m very glad to contact with you.我非常高兴和你联络。(9)I’m so pleasure to see you for the first time. 初次见面非常高兴。 (10)It’s a great happiness to contact with you again. 和你再次联络是极大的愉快。

设计方案常用字体库中英文对照表

设计常用字体库中英文对照表 当确实字体时,Photoshop会提示丢失字体,但是提示的字体名称是 一串英文字符,即使字体的名称是中文的也是一样。这给我们的带来 了困难,很难找到对应的字体来安装。今天要用字体了,所以就收集 了下供大家参考希望对大家有帮助! (简体部分) 中文字体名英文字体名文件名 PS name 汉字数 方正报宋简体 FZBaoSong-Z04S FZBSJW FZBSJW—GB1-0 7156 方正粗圆简体 FZCuYuan-M03S FZY4JW FZY4JW—GB1-0 7156 方正大标宋简体 FZDaBiaoSong-B06S FZDBSJW FZDBSJW—GB1-0 7156 方正大黑简体 FZDaHei-B02S FZDHTJW FZDHTJW—GB1-0 7156 方正仿宋简体 FZFangSong-Z02S FZFSJW FZFSJW—GB1-0 7156 方正黑体简体 FZHei-B01S FZHTJW FZHTJW—GB1-0 7156 方正琥珀简体 FZHuPo-M04S FZHPJW FZHPJW—GB1-0 7156 方正楷体简体 FZKai-Z03S FZKTJW FZKTJW—GB1-0 7156 方正隶变简体 FZLiBian-S02S FZLBJW FZLBJW—GB1-0 7156 方正隶书简体 FZLiShu-S01S FZLSJW FZLSJW—GB1-0 7156 方正美黑简体 FZMeiHei-M07S FZMHJW FZMHJW—GB1-0 7156 方正书宋简体 FZShuSong-Z01S FZSSJW FZSSJW—GB1-0 7156 方正舒体简体 FZShuTi-S05S FZSTJW FZSTJW—GB1-0 7152 方正水柱简体 FZShuiZhu-M08S FZSZJW FZSZJW—GB1-0 7156 方正宋黑简体 FZSongHei-B07S FZSHJW FZSHJW—GB1-0 7156 方正宋三简体 FZSong III-Z05S FZS3JW FZS3JW—GB1-0 7156 方正魏碑简体 FZWeiBei-S03S FZWBJW FZWBJW—GB1-0 7156 方正细等线简体 FZXiDengXian-Z06S FZXDXJW FZXDXJW—GB1-0 7156 方正细黑一简体 FZXiHei I-Z08S FZXH1JW FZXH1JW—GB1-0 7156 方正细圆简体 FZXiYuan-M01S FZY1JW FZY1JW—GB1-0 7156 方正小标宋简体 FZXiaoBiaoSong-B05S FZXBSJW FZXBSJW—GB1-0 7156 方正行楷简体 FZXingKai-S04S FZXKJW FZXKJW—GB1-0 7156

常用英文对照表

服装尺寸表英语词汇 Tops 上衣 bust,bust width (女)胸围,[粤]胸阔 chest,chest width (男)胸围,[粤]胸阔 waist 腰围 bottom,hem,hem opening 下摆,[粤]脚围 waistband width (夹克等上衣)脚围 waistband height (夹克等上衣)脚高 front cross 前胸宽,[粤]前胸阔 across measure 横量,[粤]横度 neck width,neck across 领宽,[粤]领横 neck drop (center back to center front) 领深(后中到前中)front neck drop 前领深 back neck drop 后领深 placket width 门襟宽,[粤]门筒阔 pocket welt width 袋口高 pocket high point 袋尖高(口袋最长的高度) shoulder across 总肩宽,[粤]肩阔 shoulder length,small shoulder 肩长,[粤]小肩长(单边肩长)armhole(curve)袖窿,[粤]夹圈(弯量,[粤]弯度)armhole(straight)袖窿,[粤]夹圈(直量,[粤]直度)armpit 腋窝,[粤]夹底 sleeve length 袖长 overarm 上袖长 underarm 下袖长 sleeve crown height 袖山高 biceps 袖肥,[粤]袖髀围 upper arm width,sleeve width 袖肥,[粤]袖髀阔 sleeve opening 袖口 cuff width 袖头宽,[粤]鸡英宽 cuff height 袖头高,[粤]鸡英高 elbow width,forearm width 肘宽 center back length 后中长 back cross 后背宽,[粤]后背阔 collar length 领长 collar point spread 领尖距 collar point 领尖长 upper collar height 上级领高 collar band height 领座高,[粤]下级领高 logo meas: edge to side fold 标识位置:边到折边 Bottoms 下装 waist(relax)腰围(松量,[粤]松度) waist(stretched)腰围(拉量,[粤]拉度) waistband width (裤、裙等下装)腰围 waistband height (裤、裙等下装)腰头高 hip,hip width 臀围,坐围 high hip 上臀围,上坐围 thigh(under crotch),thigh width 髀围,大腿围(裤浪底量)leg opening 裤脚围 knee 膝围

中文名字韩语对照表(姓名韩文翻译)

下载后,按Ctrl+F就可以搜索了! ?仮伽佳假家价加可呵咖哥哿嘉坷嫁宊家苛茄葭斝暇架枷柯榎槚歌珂珈迦痂稼笳耞舸街袈诃謌贾跏轲驾 ?刻却却各咯埆恪搉搁悫桷壳珏脚觉角阁 ?侃偘刊垦奸奸干干悭拣涧茛恳暕杆柬栞杆干玕迀癎看磵秆秆竿简肝艮艰衎谏赶间龈 ?乫喝噶渴葛曷楬碣秸竭褐羯蝎蝎鞨鹖 ?勘坎坩埳堪嵌嵁弇憾撼泔淦减澉邯感憨戡敢柑橄欿敛甘疳监瞰矙绀轗酣鉴鉴鹻碱龛 ?匣岬甲胛钾闸韐 ?傋僵刚堈壃姜冈岗康强强强忼慷扛江茳姜降杠橿殭畺疆矼穅罡襁糠绛纲襁羌羗羫腔舡讲豇钢缰鱇 ?介价个凯剀匃垲恺忾慨揩漑芥盖改槪槩玠疥皆盖磕个豈铠开闿 ?喀客 ?坑更硁粳羹赓铿 ?醵 ?倨去呿居巨拒据据渠苣莒蕖蘧举昛炬遽祛秬袪裾筥籧胠腒距踞車巨锯駏 ?干件健巾建揵愆楗犍睷腱虔褰謇蹇键鞬骞 ?乞乬杰朅杰桀榤

?俭剑剑捡芡检睑钤黔 ?刧刦劫怯迲 ?偈揭憩 ?挌激隔击格檄毄膈觋阒骼鬲鴃 ?坚狷樫牵犬遣甄畎羂笕绢縳缱肩蠲茧见谴鲣鹃 ?抉决洁玦结缺觖诀阕 ?傔兼嗛岒慊拑蒹歉箝缣谦钳鎌黚鼸 ?京俓倞倾儆冏刭劲勍卿哽垧境庚径惸憬泾茎庆憼扃擎敬景暻更梗檠炅烱焭茕颎璟璥琼径畊痉硬磬竟竞竸絅经绠罄耕耿胫褧謦警轻镜顷颈顈頚駉惊鲠鲸黥 ?系启堺阶契季届悸溪葪蓟阶戒桂械棨烓禊界瘈癸磎稽罽筓系綮縘系继计诫溪鸡髻鸡 ?估凅刳古叩告呱固塙姑孤尻库拷沽苦苽菰藁郜考故敲暠杲枯栲槁槀槹櫜牯痼皋皐盬睾瞽稁稿罟袴箍篙糕羔羖翱考股胯膏蛊觚诂诰賈辜酤钴锢雇靠顾高鸪鷱鼓 ?哭喾斛曲梏槲谷縠觳谷毂鹄 ?困坤堃昆昆悃捆滚昆捆棍琨裍裈绲衮衮锟阃髡鲲鹍鹍齫

?搰汨滑榾矻骨鹘 ?供倥公共功孔崆工悾拱控恐恭攻栱杠珙空箜蚣蛩蛬贡赣跫釭巩龚 ?串 ?侉埚伙夸寡挝猓菓戈果过瓜科稞窠蝌裹夸课跨踝銙锅颗骒 ?廓藿郭椁椁癨躩霍鞹 ?丱串冠官宽惯涫灌菅棺款爟管瓘祼盥窾筦管绾罐观贯輨錧鑵关雚颧馆髋鹳 ?佸刮括恝栝适筈聒髺鸹 ?侊光匡圹广恇洸狂犷茪旷桄框炚爌珖磺筐絖纩胱诓诳矿 ?卦呙挂挂罣罫诖

中英文无线电陆空通话范例教程

精心整理 FSAAC 中英文无线电陆空通话范例教程(空管飞行必读) 范例航线:上海浦东国际机场(ZSPD )-北京首都国际机场(ZBAA )? 643 C : 1P ????PudongGND,Goodevening,CES123,Boeing767,requeststand.? C :东方123,浦东地面,停机位廊桥205号。?

??????CES123,GND,Stand/spot/bay/gate/parkingbay205.? 站调席位发放停机位时,须使用中文,严禁使用“GATExxxx”、"PARKINGxxxx"等英文。机组收到机位、航线后,直接联系放行。 P 2 P ALFA 联系放行时,首先你需要告诉管制你在哪儿(机位),你的机型,你是否抄收机场情报通波(包含起飞使用跑道,起始上升高度,标准离场程序,离场频率及气象信息;怎样抄收机场ATIS情报通波如何抄收?请见:)以及你要到哪儿去(目的地)。?

C:东方123,浦东放行,许可放行至北京,按计划航路飞行,预计使用跑道17L,起始高度900米,修正海压1012,PIKAS11号离场,离场频率126.65,应答机5001。? ????CES123,DEL,clearedtoBeijingviaflightplannedroute,expectrunway17L,initialclimb 900monQNH1012,PIKAS11departure,departurefrequency126.65,squawk5001.? 离 P 压1012 ????? ? C ????CES123,readbackiscorrect,callwhenready(forGND).? ??????? P:东方123,地面准备好了。? ????CES123,readyforGND.?

平面设计最常用的6种英文字体

字体设计一直是设计师最头疼的事,选择好是字体往往会事半功倍,然而中国设计师由于设计教育的问题和文化差异,往往对英文字体忽视,随便选一个往往就使用在了我们的作品中,设计师好坏的差别很大程度上是字体选择的差别,大马设计精选出出这6种最常的英文字体,他们都是久经考验的经典字体,有些经过了数百年的洗礼,有些像空气一起存在于我们周围,相信看过这个帖子会对你的设计会有很大帮助,并且每一个介绍后都有下载链接,可以下载安装使用。 1. 无处不在的:Helvetica Helvetica是世界上最著名和流行字样之一。它干净、清晰的字形领导了一股清楚、易懂而快速的阅读潮流。Helvetica是由米耶丁格和爱德华德·霍夫曼(Eduard Hoffmann)在瑞士哈斯铸造所(Haas’sche Schriftgießerei)所制做。最初的名称是“Neue Haas Grotesk”,意为“哈斯的新无衬线铅字”,后来被哈斯的德国母公司斯滕佩尔(Stempel)在1960改为 Helvetica,源自瑞士的拉丁文,使其更具有国际市场竞争力。 1983年,D. Stempel AG和Linotype 公司一起重新设计并数字化了Helvetica,取名Neue Helvetica,建立了一个新的统一的字体家族。直到今天,原有的Helvetica家族包含了34种不同的字体磅值,而Neue Helvetica家族却有51种字体磅值。 Helvetica字体家族已经成为很多数字印刷机和操作系统中不可缺少的一部分,同时也成为了当代视觉文化中一个无法替代的指南针。,世界无数的Logo在使用Helvetica,比如:如3M ,BASF 美国航空,BWM,英特尔,汉沙航空,Knoll,松下,无印量品,三星,德国铁路。 更多关于这个字体信息请点击下载: 世界著名字体系列——Helvetica

小学生常用英语单词对照表

小学生常用英语单词对照表 一、学习用品(school things)pen /pen/ 钢笔 pencil /'pensl/ 铅笔 pencil-case /'penslkeis /铅笔盒ruler /'ru:l?/ 尺子 book /buk/ 书 bag /b?g/ 包 post card /p?ust kɑ:d/ 明信片newspaper /'nju:z,peip?/ 报纸schoolbag /sku:lb?g/ 书包eraser / i'reis? / 橡皮 crayon / 'krei?n / 蜡笔sharpener / '?ɑ:p?n? / 卷笔刀story-book/'st?:ri] buk /故事书notebook / 'n?utbuk / 笔记本Chinese book/'t?ai'ni:z/语文书English book / 'i?gli? / 英语书maths book/ m?θs / 数学书magazine / ,m?g?'zi:n / 杂志dictionary / 'dik??neri / 词典 二、身体部位(body) foot / fut / 脚 head / hed / 头 face / feis / 脸 hair / h?? / 头发 nose / n?uz / 鼻子 mouth / mauθ / 嘴 eye / ai / 眼睛 ear / i? / 耳朵 arm / ɑ:m / 手臂 hand / h?nd / 手 finger / 'fi?g? / 手指 leg / leg / 腿 tail / teil / 尾巴tooth /tu: θ/ 牙齿eyebrow/?aibrau/ 眉毛 三、颜色(colours) red /red/ 红 blue /blu:/ 蓝 yellow /'jel?u/ 黄 green /gri:n/ 绿 white /wait/ 白 black /bl?k/ 黑 pink /pi?k/ 粉红 purple /'p?:pl/ 紫 orange /'?:rind?/ 橙brown /braun/ 棕 四、动物(animals) cat /k?t/ 猫 dog /d?g/ 狗 pig /pig/ 猪 duck /d?k/ 鸭 rabbit /'r?bit/ 兔子 horse /h?:s/ 马 elephant /'elif?nt/ 大象ant /?nt/ 蚂蚁 fish /fi?/ 鱼 bird /b?:d/ 鸟 snake /sneik/ 蛇 mouse /maus/ 鼠 kangaroo /,k??g?'ru:/ 袋鼠monkey /'m??ki/ 猴子panda /'p?nd?/ 熊猫 bear /b??/ 熊 lion /'lai?n/ 狮 tiger /'taig?/ 老虎 fox/f?ks/ 狐狸

英语无线电陆空对话用语手册6

英语无线电陆空对话用语手册 (第六辑) 声明: 以ICAO附属书第十(航空通信)第二卷(包含航行业务程序的通 信程序)以及ICAO Doc.4444(航行业务程序-航空及航空交通业务)为准-标准总结。 编写、翻译、校准: 中华飞行联盟CCA-6060, 中国民用航空飞行学院飞行学员及中国民航大学空管学员。 警告: 本手册内容完全来源于国外标准无线电陆空对话教程。禁止任 何人以谋取商业利益为由,进行非法盗用及盗版;禁止任何人对本教程做出侮辱性评价;本手册为总结版本,仅供模拟航空交通管制员参考学习,禁止用于真实管制中。 感谢: 韩国航空大学航空交通学部教材提供。 感谢中国民用航空飞行学院飞行学员及中国民航大学空管学员校正。

(七)进入跑道及起飞。 第五辑中,第六节内容为申请滑行,第七节紧接第六节中联系塔台,进入跑道及起飞内容。 说明:在真实地面管制中,地面管制员会向航空器通报地面风的情况,内容应为,平均风向,风速及风向,风速的重大变化。但在模拟飞行管制中,并未有这项内容,故在塔台管制时,航空器起飞许可中,常常包括地面风风向风速及修正海压值。 下面为地面风风向,风速的英文表达方式。 1.Wind100at4meters/4knots. 地面风100,4米每秒/4节。 2.Wind variable at4meters/4knots. 地面风向不定,风速4米每秒/4节。 3.Wind100at4meters,gust[gɑst](ɑ为短音节)to13. 地面风100,4米每秒,最大阵风13米每秒。

例: 第一种情况: PILOT:PUDONG Tower,China eastern123,Holding point runway17R, Ready for departure. 飞行员:浦东塔台,东方123,跑道(17R)外等待,已准备好离场。 TOWER:China eastern123,Line up(runway17R)。 塔台:东方123,进跑道(17R)等待。 PILOT:Line up,China eastern123. 飞行员:进跑道等待,东方123。 TOWER:China eastern123,Wind100at4meters,QNH1003,Cleared for take-off(runway17R),Report airborne. 塔台:东方123,地面风100,4米每秒,修正海压1003,可以起飞,(跑道17R),离地报。 PILOT:Cleared to take off,(wilco),China eastern123. 飞行员:可以起飞,(照办),东方123。 *1.当机场内有多条跑道同时使用时,为了避免航空器驾驶员混淆,

FSAAC中英文无线电陆空通话范例教程

FSAAC中英文无线电陆空通话例教程(空管飞行必读) 例航线:浦东国际机场(ZSPD)-首都国际机场(ZBAA) 航向介绍:该航线经情报区、情报区。在情报区的空域围,经过管制区、管制区;在情报区的空域围容,经过管制区。航路里程是643海里,选用浦东机场起飞跑道为17L,选用首都机场落地跑道36R。 C:Controller(管制员) P:Pilot(飞行员) P:浦东地面,晚上好,123,机型波音767,申请停机位。 Pudong GND, Good evening,CES123,Boeing767,request stand. C:123,浦东地面,停机位廊桥205号。 CES123,GND,Stand/spot/bay/gate/parking bay 205. P:停机位廊桥205号,123。 Bay 205,CES123. P:浦东放行,晚上好,123,停机位廊桥205号,机型波音767,通波ALFA已抄收,申请放行至。 Pudong DEL,Good evening,CES123, stand 205,boeing767,I have information A,request IFR clearance to Beijing. C:123,浦东放行,许可放行至,按计划航路飞行,预计使用跑道17L,起始高度900米,修正海压1012,PIKAS11号离场,离场频率126.65,应答机5001。 CES123,DEL,cleared to Beijing via flight planned route,expect runway 17L,initial climb 900m on QNH1012,PIKAS11 departure,departure frequency 126.65,squawk 5001. P:许可放行至,按计划航路飞行,预计使用跑道17L,起始高度900米,修正海压1012,PIKAS11号离场,离场频率126.65,应答机5001,123。 cleared to Beijing via flight planned route,expect runway 17L,initial climb 900m on QNH1012,PIKAS11 departure,departure frequency 126.65,squawk 5001,CES123. C:123,复诵正确,地面准备好叫。 CES123,readback is correct,call when ready (for GND). P:123,地面准备好了。 CES123,ready for GND. C:123,联系地面121.8,再见。 CES123,contact GND on 121.8,goodday. P:联系地面121.8,再见,123。 Contact GND on 121.8,goodday,CES123. P:浦东地面,晚上好,123,停机位廊桥205,地面已准备好,请求推出开车。 Pudong GND, good evening,CES123,parking Bay 205,ready for GND,request pushback and startup. C:123,浦东地面,可以推出开车,机头朝北。 CES123,GND,pushback and startup approved,face to north. P:可以推开,机头朝北,123。 pushback and startup approved, face to north,CES123. P:123,推出开车完毕,请求滑出。 CES123,pushback and startup completed,request taxi (out). C:123,延滑行道BRA VO3、ALFA、ALFA12,跑道17L。 CES123,Taxi via B3,A,A12 to runway 17L.

中韩姓氏对照表

[资料] 中韩姓氏对照表 2007-04-06 11:36 P.M. ? ?(贾) ?(简) ?(葛) ?(甘) ?(康) ?(姜) ?(强) ?(刚) ?(疆) ?(介) ?(甄) ?(坚) ?(景) ?(庆) ?(桂) ?(高) ?(曲) ?(公) ?(孔) ?(郭) ?(桥) ?(丘) ?(具) ?(邱) ?(国) ?(菊) ?(鞠) ?(君) ?(弓) ?(*) ?(权) ?(斤) ?(琴) ?(奇) ?(箕) ?(吉) ?(金) ? ?(羅] ?(欒] ?(南] ?(浪] ?(乃] ?(奈] ?(路] ?(盧] ?(魯] ?(雷] ?(赖] ?(楼] ? ?(段) ?(单) ?(端) ?(谭) ?(唐) ?(大) ?(道) ?(都) ?(陶) ?(敦) ?(顿) ?(董) ?(杜) ?(头) ? ?(马) ?(麻) ?(万) ?(梅) ?(孟) ?(明) ?(牟) ?(毛) ?(睦) ?(苗) ?(墨) ?(文) ?(米) ?(闵) ? ?(朴) ?(潘) ?(班) ?(房) ?(方) ?(庞) ?(邦) ?(裵) ?(白) ?(范) ?(凡) ?(卞) ?(边) ?(卜) ?(奉) ?(凤) ?(夫) ?(丕) ?(彬) ?(宾) ?(氷) ? ?(史) ?(谢) ?(舍) ?(森) ?(尙) ?(西) ?(徐) ?(石) ?(昔) ?(宣) ?(卨) ?() ?(薛) ?(雪) ?(葉] ?(成) ?(星) ?(苏) ?(邵) ?(孙) ?(宋) ?(松) ?(水) ?(洙) ?(淳) ?(荀) ?(舜) ?(顺) ?(升) ?(施) ?(柴) ?(愼) ?(申) ?(沈] ?(辛) ? ?(阿) ?(安) ?(夜) ?(艾) ?(襄) ?(梁] ?(杨) ?(梁) ?(鱼) ?(严) ?(呂] ?(余) ?(汝) ?(連] ?(燕) ?(延) ?(廉] ?(影) ?(永) ?(荣) ?(芮) ?(吴) ?(玉) ?(温) ?(邕) ?(雍) ?(王) ?(姚) ?(龍] ?(禹) ?(于) ?(云) ?(芸) ?(元) ?(袁) ?(韦) ?(魏) ?(劉] ?(柳] ?(兪) ?(庾) ?(陸] ?(尹) ?(殷) ?(阴) ?(伊) ?(异) ?(李] ?(印) ?(任) ?(林] ? ?(慈) ?(章) ?(庄) ?(张) ?(蒋) ?(邸) ?(传) ?(全) ?(田) ?(钱) ?(占) ?(程) ?(丁) ?(郑) ?(诸) ?(齐) ?(赵) ?(曺) ?(宗) ?(钟) ?(左) ?(朱) ?(周) ?(俊) ?(池) ?(智) ?(晋) ?(秦) ?(眞) ?(陈) ? ?(车) ?(仓) ?(蔡) ?(昌) ?(菜) ?(采) ?(天) ?(千) ?(楚) ?(肖) ?(初) ?(崔) ?(秋) ?(邹) ?(椿)

Word中地各种英文字体及数字字体对照表A-Z

AcadEref : 1 2 3 4 5 6 7 8 9 0 a b c d e f g h i j k l m n o p q r s t u v w x y z A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AIGDT: AmdtSymbols: 1 2 3 4 5 6 7 8 9 0 a b c d e f g h i j k l m n o p q r s t u v w x y z A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AMGDT: 1 2 3 4 5 6 7 8 9 0 a b c d e f g h i j k l m n o p q r s t u v w x y z A B C D E F G H I J K L M N O P Q R S T U V W X Y Z Arial: 1 2 3 4 5 6 7 8 9 0 a b c d e f g h i j k l m n o p q r s t u v w x y z A B C D E F G H I J K L M N O P Q R S T U V W X Y Z Arial Black: 1 2 3 4 5 6 7 8 9 0 a b c d e f g h i j k l m n o p q r s t u v w x y z

Arial Narrow: 1 2 3 4 5 6 7 8 9 0 a b c d e f g h i j k l m n o p q r s t u v w x y z A B C D E F G H I J K L M N O P Q R S T U V W X Y Z BankGothic Lt BT: 1 2 3 4 5 6 7 8 9 0 a b c d e f g h i j k l m n o p q r s t u v w x y z A B C D E F G H I J K L M N O P Q R S T U V W X Y Z BankGothic Md BT: 1 2 3 4 5 6 7 8 9 0 a b c d e f g h i j k l m n o p q r s t u v w x y z A B C D E F G H I J K L M N O P Q R S T U V W X Y Z Batang: 1 2 3 4 5 6 7 8 9 0 a b c d e f g h i j k l m n o p q r s t u v w x y z A B C D E F G H I J K L M N O P Q R S T U V W X Y Z BatangChe: 1 2 3 4 5 6 7 8 9 0 a b c d e f g h i j k l m n o p q r s t u v w x y z A B C D E F G H I J K L M N O P Q R S T U V W X Y Z Book Antiqua: 1 2 3 4 5 6 7 8 9 0 a b c d e f g h i j k l m n o p q r s t u v w x y z

常用原材料中英文对照

常用原材料英文缩写与中文名称对照表A 英文缩写全称 A/MMA 丙烯腈/甲基丙烯酸甲酯共聚物 AA 丙烯酸 AAS 丙烯酸酯-丙烯酸酯-苯乙烯共聚物 ABFN 偶氮(二)甲酰胺 ABN 偶氮(二)异丁腈 ABPS 壬基苯氧基丙烷磺酸钠 B 英文缩写全称 BAA 正丁醛苯胺缩合物 BAC 碱式氯化铝 BACN 新型阻燃剂 BAD 双水杨酸双酚A酯 BAL 2,3-巯(基)丙醇 BBP 邻苯二甲酸丁苄酯 BBS N-叔丁基-乙-苯并噻唑次磺酰胺 BC 叶酸 BCD β-环糊精 BCG 苯顺二醇 BCNU 氯化亚硝脲 BD 丁二烯 BE 丙烯酸乳胶外墙涂料 BEE 苯偶姻乙醚 BFRM 硼纤维增强塑料 BG 丁二醇 BGE 反应性稀释剂 BHA 特丁基-4羟基茴香醚 BHT 二丁基羟基甲苯 BL 丁内酯 BLE 丙酮-二苯胺高温缩合物 BLP 粉末涂料流平剂 BMA 甲基丙烯酸丁酯 BMC 团状模塑料 BMU 氨基树脂皮革鞣剂

BN 氮化硼 BNE 新型环氧树脂 BNS β-萘磺酸甲醛低缩合物 BOA 己二酸辛苄酯 BOP 邻苯二甲酰丁辛酯 BOPP 双轴向聚丙烯 BP 苯甲醇 BPA 双酚A BPBG 邻苯二甲酸丁(乙醇酸乙酯)酯 BPF 双酚F BPMC 2-仲丁基苯基-N-甲基氨基酸酯 BPO 过氧化苯甲酰 BPP 过氧化特戊酸特丁酯 BPPD 过氧化二碳酸二苯氧化酯 BPS 4,4’-硫代双(6-特丁基-3-甲基苯酚) BPTP 聚对苯二甲酸丁二醇酯 BR 丁二烯橡胶 BRN 青红光硫化黑 BROC 二溴(代)甲酚环氧丙基醚 BS 丁二烯-苯乙烯共聚物 BS-1S 新型密封胶 BSH 苯磺酰肼 BSU N,N’-双(三甲基硅烷)脲 BT 聚丁烯-1热塑性塑料 BTA 苯并三唑 BTX 苯-甲苯-二甲苯混合物 BX 渗透剂 BXA 己二酸二丁基二甘酯 BZ 二正丁基二硫代氨基甲酸锌 C 英文缩写全称 CA 醋酸纤维素 CAB 醋酸-丁酸纤维素 CAN 醋酸-硝酸纤维素 CAP 醋酸-丙酸纤维素 CBA 化学发泡剂

相关文档
最新文档