源牌启动锅炉说明书ENVIRONMENT??Start-up boiler manual

ENVIRONMENT

杭州华电华源环境工程有限公司Hangzhou huadian huayuan environment engineering Co.,Ltd.

杭州华源前线能源设备有限公司Hangzhou huayuan qianxian energy equipment Co.,Ltd.

前言

Foreword

非常感谢您购买我司制造销售的SZS 型燃油(气)启动锅炉。本产品是杭州华电华源环境工程有限公司研制开发的新一代环保型、节能型产品。它具有热效率高、操作简便等优点。但如果安装、使用、维护不当,不但不能充分发挥该产品的优良性能,反而可能出现危险。

因此,在安装、使用该产品前请认真阅读本说明书、配套的燃烧器等辅机说明书!

Thank you very much for purchasing our oil/gas-fired steam boiler boiler,

,the new generation environment-friendly and energy efficient product we has developed,which is characterized by high thermal efficiency and easy operation.However,in the event that the boiler is not properly installed

and used,danger may even oc occur cur cur,

,not to mention the normal performance it is due to have.

Therefore,prior to installation and use of this product,this manual and the instructions of auxiliary units like the burner must be observed.

目录

Contents

Ⅰ、设计说明 (3)

I.Description of Design

一、锅炉规范 (5)

i.Specifications for Boiler

二、结构简介 (9)

ii.Brief Introduction to Structure

三、锅炉运行参数 (13)

iii.Boiler Operational Parameters

Ⅱ、安装说明 (15)

II.Instructions for Installation

一、安装前准备 (15)

i.Pre-installation Preparations

二、本体安装 (16)

ii.Boiler Body Installation

三、烘炉(暖炉) (18)

iii.Furnace Drying(Furnace Heating)

四、煮炉 (21)

iv.Boiling-out

五、总体验收 (25)

v.Overall Acceptance

Ⅲ、锅炉运行操作 (27)

III.Boiler Running&Operating

一、基本要求 (27)

i.Basic Requirements

二、停炉保养 (31)

ii.Furnace Blow-out&Maintenance

Ⅳ、电控操作说明 (33)

IV.Operating Instructions for Electric Controls

一、开机例行检查 (33)

i.Routine Inspections during Boiler Start-up

二、启停顺序及控制流程 (33)

ii.Start-stop Sequence&Control Procedure

三、联锁保护及故障处理 (40)

iii.Interlocking Protection&Troubleshooting

四、触摸屏(或上位机)操作 (42)

iv.Operation on Touch Screen(or Host Computer)

Ⅰ、设计说明

I.Description of Design

为了缩短电厂建设周期,确保安装进度,我司引进国外先进技术,开发了第二代快装式(整装式)启动锅炉。锅炉受热面全部在工厂内组装完成,现场只需安装相关的平台、扶梯、保温、外包装、管道、阀门、仪表等即可,大大减轻了现场的安装工作量,缩短了安装周期。锅炉可以采用雨棚式室外布置的形式不仅可以防止雨水的侵蚀,而且大大降低了建筑成本。当然也可以室内布置。

同时为了减轻运行人员的操作强度,锅炉运行也可以做到一键启停。

To shorten the power plant construction cycle and ensure the installation schedule,we have developed the second-generation package start-up boiler by introducing in the advanced technologies.Since the heating surface of boiler and its components are assembled in the factory,only the platform,ladder, insulation facilities,external packaging,pipelines and ducts,valves,and instruments have to be separately installed at the user’s site,which not only cuts done the workload for site installation but also shortens the installation cycle.The boiler can be provided with canopy for outdoor application to prevent rainwater corrosion and make the construction cost more efficient.Of course, indoor application is also permissible.

Meanwhile,to lessen the operator’s workload,the boiler can also be started or stopped by pressing only one key during operation.

一、锅炉规范

i.Specifications for Boiler

1、设计参数表

1.Table of Designed Parameters

序号No.名称

Name

单位

Unit

数据

Value

一、主要参数

1.Main Parameters

1锅炉型号SZS35-1.6/350-Y

2、安全门参数表

2.Table of Safety Valve Parameters

序号No.名称

Name

工作压力

Working

Pressure

MPa

整定压力

Set

Pressure

MPa

回座压力

Return

Pressure

MPa

备注

Remark

1上汽包安全门1

Steam-drum

Safety Valve1

1.8 1.908 1.774~1.832

2上汽包安全门2

Steam-drum

Safety Valve2

1.8 1.908 1.774~1.832

3过热器安全门

Super-heater

Safety Valve

1.6 1.664 1.548~1.597

3.运行整定参数表

3.Table of Operating and Setting Parameters

序号No.项目

Item

设定值

Set Value

备注

Remarks

1汽包压力保护值

Drum Pressure Protective

Value

1.80MPa

MFT并报警

MFT and

alarming

2紧急排空电动门动作压力

Operating Pressure of

Emergency Exhaust Electric

Valve

开启:1.6MPa

关闭: 1.55Mpa

On:1.6MPa

Off:1.55Mpa

3炉膛负压保护值

Furnace chamber negative

pressure protection

低值:-2500Pa

高值:+2500Pa

Low limit:-2500Pa

High limit:+2500Pa

MFT并报警

MFT and

alarming

4炉膛负压控制值

Furnace chamber negative

pressure control

0P a~+100Pa

5过热蒸汽温度调节值

Super-heated Steam

Temperature for Regulation

350(±20℃)

PID自动调节

PID Automatic

Regulation

6上锅筒

水位设定

Water

Level

Setting of

Steam

Drum

HH高高水位

HH-high high

water level

+100mm MFT并报警

MFT and

alarming

N正常水位

N-Normal water

level

0mm控制目标位

Target Level

Controlling

L低水位

L-Low water level

-50mm

LL低低水位

LL-Low low water

level

-100mm MFT并报警

MFT and

alarming

7给水箱水位

设定

Water

Level

Setting

Of

Feed-water

Tank

HH高高水位

HH-high high

water level

+800mm关进水阀

Shut down the

water intake

valve

N正常水位

N-Normal water

level

0mm调节进水阀

Regulate

water supply

valve

L低水位

L-Low water level

-30mm

LL低低水位

LL-Low low water

level

-600mm停给水泵

Stop feed

water pump

二、结构简介

ii.Brief Introduction to Structure

锅炉形式为双锅筒纵置式D型结构,并采用了密封性能可靠、炉膛承压能力高的全膜式水冷壁结构方式。炉膛前墙膜式水冷壁上布置了水平燃烧器,炉膛出口处布置了水平式过热器(采用与烟气逆流布置),而后是对流管束,烟气为“之字型”横向冲刷对流管束。最后经过省煤器由烟囱排出。本锅炉既可采用平衡通风方式,也可选用微正压方式。

The boiler is laid out in two-drum D-type lengthwise structure,and adopts the membrane water wall that had reliable airproof performance and whose furnace chamber is excelled at pressure-bearing capacity.The front wall of the furnace chamber is arranged with horizontal burner,and its exit is with the horizontal super-heater(arranged to have reverse flow relative to the fume). Following the super-heater is the convection bank.The flume flushes across the convection bank in zigzag type,and is discharged out of the stack through the coal economizer.This boiler can use either the balanced draft method or the micro-positive pressure way.

(1)锅筒及内部装置(具体尺寸与锅炉压力等参数有关)

(1)Boiler Drum&Internal Devices(Its specific dimension is concerned with parameters like boiler pressure)

锅炉上锅筒内径为Φ1000,壁厚为18mm,下锅筒内径为Φ800,壁厚为16mm,均采用SA-516Gr.70钢板卷制而成。上锅筒装有监控水位的平衡容器、电接点水位计、差压变送器,以及就地显示液位的水位计,并设置有连续排污、加药、气

体保护等管座。上锅筒上还装有两只弹簧式安全阀、压力表,以及锅炉超压保护用的压力控制器等。正常水位一般设置在上锅筒中心线处,最高及最低水位分别位于正常水位±50mm处。同时在上锅简内还设置有合理有效的汽水分离装置,在蒸发强度大的水冷壁上升管处装设了缝隙挡板、波纹板,对流管束区域设置了水下孔板,并在主蒸汽出口处设置了不锈钢丝网分离器。下锅筒设三个锅筒支座,两个滑动支座,一个固定支座。锅炉膨胀中心设置在下锅筒中间的固定支座处The internal diameter and wall thickness of the steam drum areΦ1000and 18mm,respectively,while these two values for the water drum areΦ800and 16mm,respectively.Both of them are rolled up by using SA-516Gr.70steel plate. The steam drum is provided with equilibrium container that monitors the water level,the electric-point hydrological gauge,differential pressure transmitter,and the hydrological gauge that indicates the local liquid level,as well as the tube holders for continuous blow-down,chemical dosing,gas protection,and so on. There are also two spring-loaded pressure relief valves,pressure gauge,and the pressure control used for boiler overpressure protection on the steam drum. Normal water level is usually set at the center line of the steam drum,and the HH and LL water levels are located at places respectively50mm over and below the normal level.Meanwhile,the steam drum has steam-water separator,baffle plate and corrugated plate on the riser tube of water wall where there is more evaporation,the water hole plate in the convection bank zone,and stainless steel mesh separator at the main steam outlet.The lower drum is provided with three boiler supports,i.e.two sliding supports,and one fixed supports.The boiler expansion center is just located on the fixed support in the middle of the water drum.

(2)水冷系统

(2)Water Cooling System

水冷系统由上下锅筒间的对流管束、前膜式水冷壁、侧膜式水冷壁、后膜式水冷壁等组成。前、后膜式水冷壁由Φ60.3×3.91的管子组成,与上、下集箱焊接连接,集箱再与锅筒焊接。侧膜式水冷壁、中水冷壁(炉膛与对流管束的隔墙)也由Φ60.3×3.91的管子组成,直接与锅筒焊接连接。对流管束采用Φ48.3×3.68

管材,与锅筒直接焊接连接。管子材料为SA-210A-1。

The water cooling system is composed of the convection bank between the steam and water drums,and the front,side,and rear membrane walls.The front and rear membrane walls are made up ofΦ60.3X3.91tubes,and welded together with the upper and lower headers,the latter of which is then welded with the boiler drum.The side membrane wall and the middle water screen(the partition between furnace chamber and convection bank)are also made up of Φ60.3X3.91tubes and reaches to the boiler drum by welding.The convection bank usesΦ48.3X3.68tubing and is welded with the boiler drum directly.The code of the tube material is SA-210A-1.

(3)过热器

(3)Super-heater

过热器布置在炉膛出口、对流管束入口处,采用单级水平布置方式,由Φ42.2×3.56的SA-213T22管子组成,蒸汽由进口集箱进入过热器蛇形管,再到出口集箱。经喷水减温调节蒸汽温度后进入汇流集箱。

Super-heater is located at the connection of furnace chamber and convection bank and arranged in horizontal single-stage structure.It consists of Φ42.2X3.56SA-213T22tubes.The steam flows into the multiloop super-heater from the inlet header and then out into the outlet header.When the steam temperature is decreased by the water sprinkling,the condensate flows into the collector.

(4)省煤器

(4)Coal Economizer

省煤器(确切说应称为省油器)设计成可分式的单独结构,采用高效传热的螺旋鳍片管,管子采用φ33.4×3.38的无缝钢管。

Coal economizer(As more exactly,it should be called the oil economizer)is designed to be the sectional separate structure,and made up of highly efficient heat-transfer spiral finned tubes which are theφ33.4x3.38seamless steel tubes (5)燃烧系统

(5)Combustion System

燃烧器选用中间回油压力雾化轻油燃烧器,水平布置于前墙。燃烧器配备了高能点火装置、火焰检测装置,以及用于负荷调节的风门执行器、油量调节阀等。

为了确保点火的可靠性和安全性,专门设置了点火油枪(耗油量约在200kg/h),保证锅炉点火的成功率,以及避免点火时产生爆燃等突变现象。锅炉燃烧排放符合GB13271-2001《锅炉大气污染物排放标准》的要求。

Burner is selected among the light-fuel-fired burners that are characterized by middle oil return and pressure atomizing.It is located on the front wall.The burner is provided with high-energy ignition device,flame detector,and air damper actuator and oil control valve responsible for relevant load adjustment. To ensure the ignition reliability and safety,the burner is particularly provided with ignition oil gun(its oil consumption is about200kg/h)to guarantee the boiler ignition success and prevent unexpected phenomenon like explosion. Boiler’s emission resulting from the combustion conforms to provisions of GB 13271-2001Criteria for Air Pollutant Emission of Boiler.

燃烧负荷调节比不小于1:3,也即锅炉最小负荷可以在30%时仍能达到额定的参数要求。

Combustion load turndown ratio reaches1:3and over,which means that the boiler meets with the rated value even when the minimum load is at30%.(6)炉墙

(6)Chamber Wall

本锅炉采用安装简便的轻型炉墙,使用的绝热材料主要有:岩棉板、耐火混凝土、耐火砖等。

The boiler use light-weight chamber wall that is easy and convenient for installation and the thermal insulating materials it uses mainly include the refractory concrete,and fire bricks.

(7)平台扶梯

(7)Platform Ladder

本锅炉在需要频繁操作、监测、检修的部位均设置了操作平台和相关的连接扶梯。平台和连接扶梯符合GB4053.3《固定式工业防护栏杆安全技术条件》的要求。

The boiler is provided with operating platform and relevant connecting ladders at the place that may require frequent operations,monitoring,and inspection and repairs.The platform and connecting ladder conform to

GB4053.3Safety Requirements for Fixed Industrial Protective Railings.

(8)其它相关附件:

(8)Other Relevant Accessories:

锅炉炉膛上设置了检修人孔、观察孔、防爆门、炉膛风压测点及风压保护开关,炉膛出口及相关受热面的出口均设置了温度检测点。蒸汽/热水侧也设置了相关的压力、温度测点,便于运行控制和安全保护。

The furnace chamber is provided with access manhole,observation hole, explosion door,measuring point for chamber’s air pressure,and air pressure protection switch.The chamber’s exit and the exits of related heating surfaces are all provided with temperature monitoring points.Places for steam/hot water are also provided with related pressure and temperature measuring points,for the purpose of operating control and safety protection.

三、锅炉运行参数

iii.Boiler Operational Parameters

1、各部件热力计算总表:

1.Summary of Heat Calculations of All Parts

序号No.项目

Item

符号

Symbol

单位

Unit

炉膛

Furnace

Chamber

凝渣管

Slag

Coagulating

Pipe

过热器

Super

Heater

对流管束

Convection

Bank

省煤器

Coal

Economize r

1管径及壁厚

Tube Dia.&Wall

Thickness

d×δmm

Φ

60.3×3.91

Φ

48.3×3.68

Φ

42.2×3.56

Φ

48.3×3.68

Φ

33.4×3.38

2进口烟温

Inlet Fume

Temperature

θ'℃10681030763303

3出口烟温

Outlet Fume

Temperature

θ"℃10681030763303163

4进口工温

Inlet Working

Temperature

t'℃209.8209.8209.8209.880

5出口工温

Outlet Working

Temperature

t"℃209.8209.8350209.8131.5

6烟气流速

Fume Velocity

W y m/s13.719.817.914.9

2、锅炉烟风阻力参数:

2.Drag Parameters of Boiler’s Fume&Air

锅炉烟(空)气阻力(不包括燃烧器)

Pa2194 Resistance of Boiler’s Fume and Air

(excluding the burner)

烟气量(~163℃)

M3/h59817

Flue Gas Volume(about147℃)

空气量(20℃)

M3/h37205 Air Capacity(20℃)

3、过热器壁温:

3.Super-heater Wall Temperature

过热器管材质采用的SA-213T22,其最高使用温度范围为650℃,经过炉内

热负荷过热器区域的强度情况来看:进口处烟温最高处其壁温525℃,出口处

烟温最高处其壁温为460℃。壁温均小于650℃,合格。

The super-heater tubing uses SA-213T22,whose maximum permissible

temperature is650℃.In the view of thermal load intensity in super-heater zone,

the highest wall temperatures for inlet fume and outlet fume are525℃and460

℃,respectively,which are all below650℃.

Ⅱ、安装说明

II.Instructions for Installation

一、安装前准备

i.Pre-installation Preparations

锅炉安装前必须做好下列准备工作:

The following jobs should be achieved before boiler installation:

1、安装使用登记手续请参照当地技术监督部门的有关规定。

1.For boiler installation and operation registration procedures,please refer

to regulations set forth by local technical and supervision department

2、安装单位必须持有技术监督部门颁发的相应级别安装许可证且在有效期内方可担任施工任务。

2.The contractor responsible for installation should not undertake any boiler construction until it has obtained the installation license of the level corresponding to the boiler to be installed issued by the technical and supervision department concerned during the term of license validity.

3、安装前应认真查阅锅炉技术性文件,严格按照相关标准和产品图纸有关技术要求进行安装。

3.Technical documents of the specific boiler should be read through carefully before installation,and the boiler should be installed in strict line with technical requirements set forth in relevant standards and drawings.

4、安装地点的确定:

4.Determination of Installation Location:

(1)锅炉房的布置应符合GB50041-2008《锅炉房设计规范》中的规定,且布局要合理、美观。

(1)The boiler house should be laid out properly and pleasantly in conformity with provisions of GB50041-2008Code for Design of Boiler Houses.

(2)消防通道应畅通,给水和排污要合理。

(2)Fire passages should be kept free of any obstacles,and the water

supply and blow-down systems should be properly designed.

(3)燃料的存放要安全,取用要方便。

(3)Fuel should be stored safely and convenient for access.

(4)本体安装地点最好能接近蒸汽使用地点,以便缩短蒸汽输送管路,减少管路散热损失,降低基本建设费用。

(4)It is recommended that the boiler body be located in the vicinity of the site of steam use so as to shorten the steam pipeline,reduce pipeline thermal

loss,and cut down the infrastructure construction costs

5、检查安装所需的配件以及采购材料是否齐全,规格型号是否符合标准要求(特别要注意计量仪表的计量单位)。

5.The accessories and purchased materials necessary for installation should be checked for their completeness and conformity of models and specifications with the standards(particularly the measurement units of meters and gauges).

二、本体安装

ii.Boiler Body Installation

锅炉安装中对各部件的要求,应按GB50273《锅炉安装工程施工及验收技术规范》要求执行。若因锅炉超宽超高无法整体运输的,须进行现场组装。

The requirements for each part during boiler installation should be carried out in accordance with GB50273Technical Codes for Construction and Acceptance of Boiler Installation Engineering.Where the boiler is unable to be transported as a whole due to extra width or height,it should be assembled at the construction site.

现将一些要注意的事项申述如下:

Aspects that should be noted are stated as follows:

1、根据锅炉、锅炉房设计图纸、技术文件并对照锅炉图纸的要求,校验锅炉土建基础的正确性。

1.Correctness of the boiler’s foundation should be reviewed and verified in accordance with the design drawings(for boiler and boiler house)and technical documents,and by referring to the boiler’s drawings.

2、根据炉体重量,准备好吊装工具,吊装就位后炉体应符合图纸要求。

2.The hoisting tool should be provided in accordance with the boiler body weight.When the hoisting tool is put in place,the boiler body should be placed as required by the drawing

3、检查锅炉底脚与基础面接触是否良好,如有空隙加垫铁片使锅炉保持受力均匀。

3.Check if the boiler footings are well contacted with the ground surface. Where there is any gap,iron plate can be used under the footing to give the boiler uniform stress.

4、烟道法兰连接处均应采用硅酸铝绳等,使各接头密封严密,以防泄露。烟囱吊装应保持铅垂度、直线度和图纸要求。

4.Flue flange should be wound with alumina-silicate rope at the connection to seal all the joints and prevent leakage.The stack that is to be hoisted should be kept vertical and linear,and as required by drawings.

5、安装燃烧器应严格按照燃烧器制造单位提供的技术资料和说明进行;燃料管路及电气线路的安装应符合锅炉房设计规定及有关规范如《蒸汽锅炉安全监察规程》和消防安全方面等规定进行。

5.The burner should be installed strictly in compliance with the technical information and instructions provided by the burner manufacturer;the combustion ducts and electric wiring should conform to boiler house design and relevant specifications such as the Specifications for Safety Supervision of Steam Boiler and fire protection requirements.

6、热工仪表、阀门和管道的组装。

6.Assembly of thermodynamic instruments,valves and pipelines and ducts.

7、安全阀应在水压试验后安装,安装必须垂直,并应连接排放管引至安全处。

7.The relief valve should be installed vertically after the hydraulic test,and led to safe place after connecting with the discharge pipe.

8、安装压力表时,应使刻度盘垂直,压力表刻度盘上应画出红线,以示锅炉最高许可工作压力,压力表旋塞旋转要灵活,不得漏水,存水管应通畅。

8.When the pressure gauge is to be mounted on,its dial should be held vertical and drawn with a red line to indicate the boiler’s highest permissible working pressure.The gauge faucet should be agile and with no leakage,and the disconnection trap should be maintained free of obstacles.

9、由合格操作人员连接总电源进线(此线为三相四线,AC400/230V±10%),为确保安全,锅炉本体应接地线连接,对地电阻应小于10Ω。

9.The main power lead-in line(three-phase four-wire line, AC400/230V±10%)should be connected by the qualified electrician.To ensure the safety,the resistance to ground should be less than10Ωwhen the boiler body is grounded.

10、燃料贮存罐应设置在便于观察又符合消防要求的地方。

10.The fuel storage tank should be installed at the place that is accessible for observation and conforms to fire protection requirements

11、根据有关标准和要求,将燃料供应管路、水路、电路等全部接通后,准备水压试验。

11.When the fuel supply pipe,water pipeline and circuits are all connected up in accordance with relevant standards and requirements,the hydraulic test then can be started

12、在总体验收前应对供汽、进油、回油及给水管路进行安装后吹扫,以避免管路氧化皮等杂质进入过滤器。

12.Pipelines for gas supply,oil supply,oil return,and feed water should be purged after installation before the overall acceptance so as to prevent contaminants like pipeline oxide skin getting into the filter.

三、烘炉(暖炉)

iii.Furnace Drying(Furnace Heating)

新安装锅炉和连续停用3个月以上都应进行烘炉(暖炉);

The new boiler and the boiler that has not been used for the past three months or above should be dried in the furnace;

1、烘炉前的准备工作

1.Preparations before Furnace Drying

编制烘炉方案及烘炉曲线,对参加人员进行技术交底,并准备好有关烘炉记录。炉墙上布置好测温点或取样点,并准备好温度计或取样工具。

Furnace drying plan and curve should be prepared;and all participants involved should be trained and take a good note of all records about the drying. The chamber wall should be furnished with points for temperature measurement or sampling,and provided with thermometer or sampling appliances.

2、烘炉

2.Furnace Drying

本锅炉采用火焰烘炉法进行烘炉,其中前期为开火种阀小火烘炉,后期~15%燃烧器负荷烘炉。

This boiler adopts flame drying method,in which the furnace is dried at mild fire during earlier and transitional stages,and at about15%of the burner’s load at the final stage.

前期烘炉阶段(小火):首先开启引风机前调节门1/5到1/6左右,点燃燃烧器小火,根据升温的情况调整火焰的大小,使炉膛保持微负压,烟气缓慢流动,

根据各测点显示数据,然后逐渐加大火焰,以过热器后部的烟气温度为监控调节值。

fire):):Turn on the front regulating Furnace Drying at Earlier Stage(mild fire

valve of the induced fan to1/5–1/6and ignite the burner’s mild fire.Regulate the flame shape relative to temperature rise and make sure that the furnace chamber is maintained at micro-negative pressure and the fume flows slowly. Then increase the blaze and take the fume temperature at the tail of the super-heater as the value for regulation.

后期烘炉阶段(~12.5%燃烧器负荷):当用小火已不能使过热器后温度再提高的时候(一般为2-3天)应加大燃料投入量烘炉,并启动引风机、逐步增大送风量,加强燃烧,使烟气温度不断提高。

load):): Furnace Drying at Final Stage(about12.5%of the burner’s load When the super-heater is unable to reach higher temperature by mild fire(this usually takes2-3days),more fuel should be fed into the furnace,and the induced fan should be turned on to deliver the input air gradually,intensifying the combustion and increasing the fume temperature.

3、烘炉时间的温度控制

3.Time and Temperature Control of Furnace Drying

烘炉期间,控制温度很重要,升温的速度对烘炉的效果有着直接影响,因此,采用测量过热器后部的烟气温度的办法来控制燃料供给量及送、引风量。

During furnace drying,temperature control is very critical,and the heating-up rate plays a direct role on drying effects.Therefore,by measuring the fume temperature at the tail of the super-heater,the fuel feeding and air input rate can then be controlled.

第一天温升不得超过50℃,以后每天升温不得超过30℃,每小时不得超过10℃,烘炉后期,烟温不得超过220℃。在最高温度范围内,烘炉持续时间不得少于24小时。如果炉墙特别潮湿应适当减慢温升速度。

Temperature rise on the first day should not exceed50℃,and the temperature rise per day and per hour for subsequent days should not exceed 30℃and10℃respectively.At the final drying stage,the fume temperature should not exceed220℃.Within the highest temperature vicinity,the drying duration should not be less than24hours.Where the chamber wall is especially damp,heating-up rate should be appropriately slowed down.

4、控制燃烧火焰

https://www.360docs.net/doc/a016376414.html,bustion Flame Control

烘炉时燃烧要均匀,按时记录温度读数,并且要注意观察炉体膨胀情况和炉墙情况,以便出现异常时及时处理。

During furnace drying,the combustion should be maintained uniform.The temperature readings should be recorded on schedule,and the furnace body expansion and the chamber wall should not be watched carefully for their changes and be properly handled in case of atypical conditions.

5、及时排出水蒸汽

5.Timely Discharge of Water Vapor

为了及时排出烘炉期间产生的水蒸汽,在烘炉时,应打开上部检查门,当发现炉墙的温度比较大时,还应减缓升温速度并加强通风,以便使炉墙中的水分及时蒸发并顺利排出。

To discharge the water vapor generated during furnace drying betimes,the upper access door should be opened during drying.Where chamber wall has a higher temperature,the heating-up rate should be slowed down and the ventilation should be enhanced so that the moisture inside the chamber wall can be evaporated and discharged as soon as possible.

6、烘炉时间

6.Furnace Drying Time

烘炉时间一般为5-7天,究竟多少天数适宜,要根据炉墙的具体情况,当时当地的气候条件等因素具体确定。

The time for furnace drying is usually5-7days,depending on specific chamber wall and local weather.

7、烘炉的合格标准

7.Standards for Acceptable Furnace Drying

7.1炉墙经烘烤后不应有变形和裂纹,混凝土不得有塌落等缺陷。

7.1There should not be distortion and cracks on the furnace wall nor concrete slump after the firing.

7.2凡达到下列规定中任一种标准时,即认为达到合格。

7.2It is considered as acceptable when one of the following standards is met.

7.2.1炉墙灰浆试样法

7.2.1Chamber Wall Mortar Sampling

在过热器位置的炉墙中部、下部位置分别取耐火砖的丁字交叉缝处的灰浆50g,若其含水率小于2.5%,则为合格。

汽轮机使用说明书

N30-3.43/435型汽轮机使用说明书 1、用途及应用范围 N30-3.43/435型汽轮机系单缸、中温中压、冲动、凝汽式汽轮机。额定功率30MW,与汽轮发电机配套,装于热电站中,可作为电网频率为50HZ地区城市照明和工业动力用电。 其特点是结构简单紧凑、操作方便、安全可靠。汽轮机不能用以拖动变速旋转机械。 2、主要技术数据 2.1 额定功率:30MW 2.1 最大功率:33MW 2.3 转速:3000r/min 2.4 转向:从机头看为顺时针方向 2.5 转子临界转速:1622.97r/min 2.6 蒸汽参数: 压力: 3.43MPa 温度:435℃ 冷却水温:27℃(最高33℃) 排汽压力(额定工况):0.0086MPa 2.7 回热抽汽:4级(分别在3、6、8、11级后) 2.8给水加热:2GJ+1CY+1DJ 2.9 工况: 工 况 项 目进汽量抽汽量排汽量冷却水温电功率汽耗Go Gc Ge Ne t/h t/h t/h ℃kW Kg/kw·h 额定工况131.0 0.0 102.77 27 30007.1 4.366 夏季凝汽工况135.5 0.0 107.98 33 30029.4 4.512 最大凝汽工况145.0 0.0 114.14 27 33055.7 4.387 最大供热工况143.5 20.0 93.51 27 30049.2 4.776 70%额定负荷工况93.0 0.0 73.93 27 21013.9 4.426 50%额定负荷工况69.5 0.0 56.47 27 15009.0 4.631 高加切除工况122.0 0.0 107.8 27 30032.7 4.062 2.10 各段汽封漏汽流量 前汽封后汽封

生物质锅炉使用说明书文档

YG-48/9.2-T型锅炉 使用说明书 图号:38300-0-0 编号:383800 SSM 编制: 校对: 审核: 标审: 审定: 济南锅炉集团有限公司 2007年4月

目录 一、概述 二、锅炉机组启动应具备的条件 三、锅炉机组启动前的检查与准备 四、锅炉机组启动 1、锅炉通风 2、锅炉冷启动 3、锅炉热启动 4、锅炉的升压操作 五、启动要求及注意事项 六、锅炉运行 1、锅炉正常运行 2、生物质点火的调节 七、停炉 1、正常停炉 2、紧急停炉 3、临时停炉 4、锅炉保温 5、锅炉疏水 八、停炉保护 九、故障处理 1、锅炉系统的停炉瓮中保护 2、低压循环系统的停炉保护 3、烟气系统的停炉保护 4、各部件的停炉保护 十、启动中的组织与分工 十一、检验及维护保养

一、前言 本锅炉是采用国外先进的生物燃料燃烧技术的48T/H振动炉排高温高汽锅炉。锅炉为高温、高压参数自然循环炉,单锅筒、单炉膛、平衡通风、室内布置、固态排渣、全钢构架、底部支撑结构型锅炉。 锅炉安装完毕后的首次启动,是对锅炉整套系统设计、安装的一次全面检查,通过试运,暴露和消除设备的缺陷和问题,为机组投产做好准备,通过启动如烘炉、煮炉、吹管等,使运行人员通过操作设备,熟悉系统,积累经验,检验各种连锁保护、自动系统投入率,同时也是结燃烧系统、给料、除尘、除渣、辅机等的一次运行考核。在整定安全阀等工作结束后,转入七十二小时试运。 本说明书主要是根据生物质燃料锅炉燃烧特点提出的特殊要求。锅炉的水、汽、电气等控制,按有关规定执行。 二、锅炉机组启动应具备的条件 1、试运的现场条件 (1)场地基本平整,消防、交通及人行道路畅通。厂房各层场面起码应做好粗地面,最好使用正式地面,试运现场应有明显标志和分界,危险区应有围栏和警告标 志。 (2)试运区施工脚手架全部拆除,现场清扫干净,保证运行安全操作。 (3)试运区的梯子、步道、栏杆、护板应按安装完毕,正式投入使用。 (4)排水沟道畅通、沟道及孔洞盖板齐全。 (5)试运范围的工业、消防及生活用水系统应能够投入正常使用,并备有足够的消防器材。 (6)试运现场具有充足的正式照明。事故照明应能在故障时及时自动投入。 (7)各运行岗位都应有正式的通讯装置。根据试运要求增设临时岗位,并应有可靠的通讯连络设施。 (8)要加强锅炉房内的防冻措施。 (9)要保证料仓及其他建筑物的通风。 2、下列系统中的设备、管道、阀门等安装完毕,保温完成。 锅炉范围内管道、汽水系统、疏放水、放汽系统、加药系统、辅用蒸汽系统、排污系统。 3、下列设备经调试合格 (1)送风机、引风机经调试结束并符合要求。 (2)热工测量、控制和保护系统的调试已符合点火要求。 (3)锅炉安全系统必须满足安全点火、运行的条件,所有旁路上的安全系统必须注明。如果安全系统不满足运行,DCS系统能够自动停止锅炉运行。 4、组织机构、人员配备和技术文件准备 (1)电厂应按试运方案措施,配备各岗位的运行人员及试验人员。并有明确的岗位责任制,运行操作人员应培训合格,并能胜任本岗位的运行操作和故障处理。 (2)施工单位应根据试运方案措施要求,配备足够的维修人员,并有明确的岗位责任制。维护检修人员应了解所在岗位的设备(系统)性能,并能在统一指挥下 胜任检修工作,不发生设备、人身事故和中断试运工作。 (3)施工单位应备齐参加试运设备(系统)的安装验收签证和分部试运记录。 (4)施工单位编制的调整试运方案措施,经试运指挥部审定后,应打印完毕,并分

电厂锅炉炉膛防爆控制系统实用版

YF-ED-J1707 可按资料类型定义编号 电厂锅炉炉膛防爆控制系 统实用版 Management Of Personal, Equipment And Product Safety In Daily Work, So The Labor Process Can Be Carried Out Under Material Conditions And Work Order That Meet Safety Requirements. (示范文稿) 二零XX年XX月XX日

电厂锅炉炉膛防爆控制系统实用 版 提示:该安全管理文档适合使用于日常工作中人身安全、设备和产品安全,以及交通运输安全等方面的管理,使劳动过程在符合安全要求的物质条件和工作秩序下进行,防止伤亡事故、设备事故及各种灾害的发生。下载后可以对文件进行定制修改,请根据实际需要调整使用。 传统的热工控制装置采用分立元件的组装 式仪表,硬件数量大,系统设计功能不十分完 善。随着大型火电机组的热工控制装置的发 展,控制系统则具有硬件可靠、内存容量大、 软件功能强等特点,使机组的自动控制功能大 大改善,炉膛防爆控制系统也随之日趋完善。 传统的炉膛压力控制系统是一个简单的单 回路控制系统,采用炉膛压力信号直接控制引 风机入口动叶或导叶开度来维持炉膛压力。近 代控制系统则采用送风机动叶开度代表总风量

作为前馈信号,炉膛压力作为主调信号,控制引风机入口动叶或导叶开度来维持炉膛压力在期望的设定值。传统的自动调节系统对炉膛压力只起调节作用,而没有保护功能,当炉膛压力测量值与设定值偏差较大时,自动调节系统会切至手动并发出报警信号,交运行人员手动处理。而以计算机为基础的现代炉膛压力控制系统则将运行程序、压力调节、联锁、保护统一协调,为设备提供了可靠的安全保证系统。当炉膛压力出现事故征兆时,控制系统能自动采取适当措施控制炉膛压力,防止或减少事故,避免由于运行人员操作不及时而扩大事故。 1炉膛爆炸分类及原因分析 炉膛爆炸可分为炉膛外爆及炉膛内爆两

亚临界300MW汽轮机运行说明书

东汽D300N启动运行说明书 2009-03-24 16:03:40 作者:yangfei来源:浏览次数:0 网友评论0 条版本号:A 东方汽轮机厂 N300-16.7/537/537-8型 汽轮机启动、运行说明书 D300N-000106ASM 编号 第全册 2001年7月10日 编号 D300N-000106ASM 编制 校对 审核 会签 审定 批准

目录 序号章-节名称页数备注 1前言2 21机组启动所必备的条件1 31-1机组启动前的检查2 42中压缸启动(IP)1 52-1冷态启动(IP)7 62-2温态启动(IP)5 72-3热态、极热态启动(IP)6 83高中压缸联合启动(HIP)1 93-1冷态启动(HIP)14 103-2温态启动(HIP)5 113-3热态、极热态启动(HIP)6 124运行1 134-1正常运行2 144-2变负荷运行2 154-3异常运行2 165停机1 175-1滑参数停机2 185-2额定参数停机1 195-3紧急停机2 206启动、运行限制要求1 216-1机组禁止启动运行限制要求1 226-2机组启动、运行的限制值5

236-3一般注意事项2 246-4定期检查试验2 257机组启停辅助操作1 267-1高压缸预暖2 277-2高压缸夹层加热系统2 287-3汽轮机低压缸喷水1 297-4事故排放系统1 前言 本说明书的启动模式,是根据我厂300MW汽轮机本体结构特点,并参照引进高压抗燃油数字电液控制系统(DEH)的技术特点提出来的,适用于我厂新一代全电调型300MW汽轮机。汽轮机启动操作方式有三种,即“自启动方式”、“操作员自动方式”和“手动方式”。运行人员可根据现场实际情况选择使用。 在“自启动方式”,DEH控制系统的ATS处于“控制状态”。ATS根据机组的状态,控制汽轮机自动完成冲转、升速、同期并网、带初负荷等启动过程。有关“自启动方式”详细操作和监视要求见《高压抗燃油数字电液控制系统(DEH)使用说明书》(由DEH供货商提供)。 在“操作员自动方式”,DEH控制系统的ATS不参与控制而处于“监视状态”,由运行人员根据汽轮机本体状态和本说明书提供的启动操作程序,在操作盘上手动给定转速或负荷的目标值和变化率,由DEH的基本控制系统按照运行人员给出的目标值和变化率自动完成冲转、升速、同步和带负荷操作。DEH系统通过CRT显示自动监视启动参数,越限时发出“报警”或“遮断”信号,指导运行人员进行操作,并可通过打印机打印出当时的和历史的数据,供运行人员研究分析。

汽轮机自密封汽封系统说明书

汽轮机自密封汽封系统说明书 1概述 汽轮机汽封系统的主要作用是为了防止蒸汽沿高压缸轴端向外泄漏,甚至窜入轴承箱致使润滑油中进水:同时防止空气通过低压轴端漏入低压缸而破坏机组的真空。 本机组汽封系统采用自密封汽封系统,即在机组正常运行时,由高压缸轴端汽封的漏汽经喷水减温后作为低压轴端汽封供汽的汽轮机汽封系统。多余漏汽经溢流站溢流至排汽装置。在机组启动,停机或低负荷运行阶段,汽封供汽由外来蒸汽提供。该汽封系统从机组启动到满负荷运行,全过程均能按机组汽封供汽要求自动进行切换。 自密封汽封系统具有简单、安全、可靠、工况适应性好等特点。 2系统组成及主要设备 该系统由轴端汽封的供汽、漏汽管路,高压主汽阀和主汽调节阀的阀杆漏汽管路,中压联合汽阀的阀杆漏汽管路以及相关设备组成。 本轴封供汽采用二阀系统,即在汽轮机所有运行工况下,供汽压力通过二个调节阀即高压供汽调节阀和溢流调节阀来控制,使汽轮机在任何运行工况下均自动保持供汽母管中设定的蒸汽压力。机组启动或低负荷运行时由高压蒸汽经高压气源供汽站调节阀,进入自密封系统。上述二个调节阀及其前后截止阀(或闸阀)和必需的旁路阀组成二个压力控制站。此外,为满足低压缸轴封供汽温度要求,在低压轴封供汽母管上设置了一台喷水减温器,通过温度控制站控制其喷水量,从而实现减温后的蒸汽满

足低压轴封供汽要求。 该系统所有调节阀执行机构均为气动型式,由DCS控制。调节阀及执行机构均采用进口件,性能稳定,运行可靠。 为保证高压气源供汽站在机组正常运行中始终处于热备用状态,特在调节阀前设有带节流孔板的旁路。机组正常运行时,汽封供汽母管中蒸汽经带节流孔板的旁路进入压力控制站,使之保持热备用状态。本系统还设置一台JQ-80-3型汽封加热器及两台轴封风机(其中一台备用),用于抽出最后一段轴封腔室漏汽(或气),并维持该腔室微负压运行。 为了防止杂质进入轴封,各供汽支管上设有Y型蒸汽过滤器。系统供汽母管还设有一只安全阀,安全阀整定压力为0.3MPa(a),可防止供汽压力过高而危及机组安全。 3系统运行 3.1启动准备 3.1.1 关闭各压力调节站,接通供汽汽源,调节站前供汽管道暖至过热器温度。确认系统仪器仪表正常。3.1.2 确认汽轮机盘车已投入。 3.1.3 凝结水再循环已建立。 3.1.4打开各压力调节阀及温度调节阀前后的手动截止阀,闸阀。 3.1.5接通气动调节阀供气气源(气源为0.4~0.7MPa (g)的仪表用压缩空气),以及相应的供电电源。 3.1.6 开启汽封加热器冷却水(凝结水)管路手动闸阀,汽封加热器投入运行。 3.1.7 开启轴封风机,开启风机进气管路电动蝶阀,风机正常投入运行(一台运行,另一台备用),通过

锅炉使用说明书.

江联重工股份有限公司JG-136/9.8-Q型锅炉 使用说明书 Q13601-SM4 2013年3月

前言 欢迎使用本公司燃气锅炉系列产品。 本使用说明书,仅针对本锅炉的主要特点,作一些使用说明,供贵公司编写运行规程参考。贵单位的运行管理应根据劳动部《蒸汽锅炉安全技术监察规程》(电站锅炉同型时还应遵照电力部《电力工业锅炉压力容器监察规程》)要求,参照有关部颁规程和典型锅炉运行规程,结合设备系统、运行经验和制造厂的技术文件,编制现场锅炉运行规程、事故处理规程以及各种系统图和有关管理制度。 贵单位的锅炉启动、调试,应根据有关规程要求、设计资料和设备技术文件编制下列试验计划(或技术组织措施):超压水压试验、烘炉、煮炉(当锅炉额定蒸汽压力为9.8MPa及其以上时的化学清洗)、冲管、吹管、严密性试验、安全阀调整和校验、水位标定试验和热工控制设备、测量仪表、自动保护装置的调试以及机组整套启动的技术组织措施(包括反事故措施)。上述计划或措施需经验收委员会试运行指挥组批准。 为确保贵单位锅炉的安全稳定运行,锅炉运行操作人员不但需要经司炉培训取得合格证,了解锅炉运行规程,还应掌握所有控制装置的机理和作用,了解锅炉原理,熟悉锅炉结构和系统,能以正确的方法进行锅炉点火、启动以及熄火、停炉操作,能以正确的方法熟练地进行调整、运行和事故处理,掌握锅炉的给水方法,清楚的知道但锅筒水位过高或过低时应采用的措施等。 为确保贵单位锅炉的安全稳定运行,锅炉应具备下述自动调节和联锁保护装置: 1.锅炉应有给水自动调节装置,应有可区分报警信号的高水位、低水位的自动报警装置,并应装设备用给水泵。 2、锅炉应有下列功能的联锁保护装置: (1)引风机断电时,自动切断送风机电源盒燃气供应; (2)送风机断电时,自动切断燃气供应; (3)锅炉燃气压力低于2000Pa时,自动切断燃气供应; (4)可靠地点火程序控制和熄火保护装置; 在点火程序控制中,点火前的吹扫风量应不小于四倍的从炉膛到烟囱入口烟道总容积,且通风时间应持续不少于10分钟,通风时引、鼓风机风门及全部

国电泰州电厂2x1000MW锅炉简介

国电泰州电厂一期工程2×1000MW超超临界燃煤机组锅炉是由哈尔滨锅炉厂有限责任公司在日本三菱重工业株式会社(Mitsuibishi Heavy Industries Co. Ltd)的技术支持下,设计的超超临界变压运行直流锅炉,采用П型布置、单炉膛、改进型低NOX PM (Pollution Minimum)主燃烧器和MACT(Mitsuibishi Advanced Combustion Technology)型低NOx 分级送风燃烧系统、反向双切圆燃烧方式,炉膛采用内螺纹管垂直上升膜式水冷壁、循环泵启动系统、一次中间再热、调温方式除煤/水比外,还采用烟气分配挡板、燃烧器摆动、喷水等方式。锅炉采用平衡通风、露天布置、固态排渣、全钢构架、全悬吊结构,燃用神府东胜、兖州、同忻煤。 锅炉型号:HG-2980/26.15-YM2型。其中HG表示哈尔滨锅炉厂,2980表示该锅炉BMCR 工况蒸汽流量,单位是t/h。26.15表示该锅炉额定工况蒸汽压力,单位是MPa,YM2表示该锅炉设计煤种为烟煤,设计序列号为2。

2.1锅炉技术规范 2.2.1锅炉主要设计参数 锅炉的最大连续蒸发量(B-MCR)为2980t/h。在B-MCR工况下,锅炉出口主蒸汽参数 26.25MPa(a)/605,再热蒸汽参数为 4.85MPa/603℃,对应汽机的入口参数为 25.0MPa(a)/600/600℃ 锅炉型号:HG-2980/26.15-YM2,锅炉的主要设计参数见表2-1。 表2-1 锅炉的主要设计参数 2.2.2锅炉设计条件 锅炉的设计条件主要包括锅炉运行后主要燃用的煤种、点火及助燃用油,对锅炉给水及蒸汽品质要求,电厂的厂用电系统电压配置及配电原则,锅炉运行条件,年利用小时数和年可用小时数,机组运行模式等。 1.煤种 泰州电厂的锅炉以神华煤为设计煤种、以同忻煤和兖州煤为校核煤种进行设计和校核,各煤种的有关参数如表2-2所示: 表2-2 煤种参数

锅炉电脑控制器使用说明书1

新一代燃气锅炉电脑控制器 使用说明书

北京亿明电气设备有限公司 目录及注意事项 一、概述 二、安装接线 三、显示

四、基本操作 五、参数设定 六、运行与控制 七、报警和连锁保护 八、异常处理及故障排除 附表、附图 感谢您使用本公司产品,为了正确使用本机并充分发挥效用,请您在使用之前务必仔细阅读说明书! 开箱检查: ◇观察产品包装箱上标示的规格、型号,确认和您定购的相符 ◇按装箱单核对产品、附件的规格、数量 ◇确认本机在运输过程中没有损坏 ◇有任何问题请在3日内与本公司联络。如在收到货物7日内未与本公司书面联络,则视同您已认可。超过此限,恕不受理。 安全注意 ◇本机必须由具有相应资格的专业技术人员按说明书安装 ◇安装使用的配件必须符合国家电气标准 ◇确认电源电压在规定的范围之内。保证良好的接地 ◇不能将强电接入弱电信号输入端 售后服务 ◇在您遇到问题或设备故障时,请及时与我公司用户服务部门联系。请您在反映问题时尽量说明:产品的型号、编号、配件、锅炉生产厂、购买日期、使用情况、具体故障现象 ◇在正常安装、使用的情况下,本机自出厂之日起12个月内发生质量问题实行在厂免费保修。超过保修期后视情况需收取相应费用 ◇如出现以下问题,应由用户承担相关费用:①使用不当造成的人为损坏②自然灾害及污染等造成 的损坏③电源电压异常、电路连接不当等造成的损坏 使用条件 ◇环境温度:0 ~45 ℃ ◇大气压力:86 ~106 Kpa ◇相对湿度:< 90 %(无结露) ◇额定电源电压:220V AC,频率:50Hz ◇电源电压范围:额定值的90% ~110% ◇强电线路和连接传感器等的弱电线路必须分别穿管走线,否则控制器可能无法正常工作

汽轮机运行说明书

Z784.05/01 N110-8.83/535 110MW双缸双排汽凝汽式汽轮机 运行说明书 南京汽轮电机(集团)有限责任公司 北京全四维动力科技有限公司

编制刘博 2008.11 校对徐其福 2008.11 审核王蕴善 2008.11 会签 标准审查郝思军 2008.12 审定 批准

目次 编制说明 (1) 1机组启动前的准备工作 (2) 1.1机组启动必备条件 (2) 1.2机组启动前的检查和准备 (2) 1.3机组禁止启动范围 (4) 2机组启动 (5) 2.1冷态滑参数启动(纯凝工况) (5) 2.2温态滑参数启动(纯凝工况) (7) 2.3 热态、极热态滑参数启动 (8) 2.4 轴系临界转速(计算值,弹性支承) (10) 3运行和维护 (13) 3.1运行和维护的基本要求 (13) 3.2机组启动、运行的限制值 (14) 3.3蒸汽参数的允许变化范围 (17) 3.4定期检查试验 (18) 4 停机 (19) 4.1滑参数停机 (19) 4.2额定参数停机 (21) 4.3紧急停机 (22)

编制说明 1、本说明书规定了保证汽轮机安全启动、带负荷运行和停机时的基本要求。对 汽封系统、调速系统、顶轴系统等的操作应按相应的技术文件执行。 2、本说明书供电厂编制启动运行规程时参考。机组启动详细操作规程及启、停、 运行中的一般注意事项,电厂可根据本说明书及有关技术文件,结合电厂实际,另行制定。但启动运行中的各项控制指标以本说明书的要求为准。 3、本说明书提供的汽轮机冷、温、热态、极热态启动曲线仅供汽轮机首次启动 时参考,以后可根据多次启动经验对该曲线进行修正。启动应以规定的各项控制指标为依据。 4、有关汽轮机的技术特性,结构特点等可参阅随机供给电厂的有关技术文件、 图纸资料及说明书。 5、对于新安装机组的首次启动运行及停机,应参阅本说明书并根据具体情况另 行编制运行规程。 6、本说明书中的蒸汽压力为绝对压力,油压为表压。 7、本说明书中的真空值按标准大气压换算得出: 真空水银柱(mmHg)=760(mmHg)-排汽压力(MPa)×7500(mmHg/MPa) 用户应参照当地大气压进行修正。

瑰都啦咪锅炉使用说明书

安装锅炉时注意事项 ·安装锅炉,需选择受厂家委托或所购代理店或有资格的专业部门。 ·常压锅炉不得将阀门安装在压力释放管上,安装阀门易引发锅炉爆炸。·常压锅炉必须装有补充水箱,不能直接与自来水管连接。蒸汽锅炉的补水箱应与锅炉容水量对等。供热水管,应与屋顶水箱连接,不要直接接自来水。锅炉不要安装在潮湿的地方。潮湿将腐蚀炉体,加速线路损坏漏电。油箱与锅炉要保持一定的距离,设立防火墙,保证锅炉运作的安全性 根据当地水质情况,锅炉应增加排污次数,次数由操作人员自行设定。蒸汽锅炉必须使用软化水设备。热水锅炉推荐使用(硅磷晶)水处理。不安装水处理时基本是一年好,二年赖,三年就烧坏。因为水垢也将付出更多的使用成本(燃料)水垢原因还可能引起锅炉爆炸。 开机工作程序 1 将手动键切换成自动位置;按下点火键, 燃烧器开始工作,锅炉投入全自动工作程序:燃烧器工作8--10分钟后,观察烟囱冒烟情况,若没有黑烟,说明各系统比例合理,燃烧器运转正常,若有黑烟,则应调整燃烧器的风门,直至不冒黑烟时为止; 2 锅炉在运行中,当水位降到最低安全水位线时,电控箱能自动亮起危险 水位灯,并报警蜂鸣响,同时,启动水泵工作,这时应及时查看水泵是否按指令工作,止由于控制系统或水泵失误,影响正常运行; 3 锅炉在运行中,若观察不到水位计的水位线位置时,必须立即在水位计

处放水,如果出水流畅,则说明供水过满,这时需手动停止水泵工作,继续放水,直正水位位线时,再换成自动运行。若水位计放不出水,说明水位己经低于水位计的最低可见边缘,此时,必须立即停止锅炉运行,关停燃烧器和水泵,开启排污阀,如果排水过急,则应立即关闭排污阀,检查水泵和电控箱的线路是否失控,修复后,锅炉才能继续投入运行。如果排污阀排水缓慢,甚至没有水排出来,仅冒少量蒸汽,此时说明锅炉已严重缺水,已处于“烧干锅”的状态。此时,千万不能进水,以免发生破坏性的严重后果。这时,锅炉必须停止运行1小时以上,并打开手孔,卸下燃烧器和炉顶板,仔细检查锅护的损坏情况,并上报上级主管部门和当地锅炉监督部门,作进一步检查。若情况正常,才能投入运行。若情况严重,则由当地锅炉监督部门作出检查结论,按结论

燃气锅炉使用说明书

安装锅炉时注意事项 ·安装锅炉,受委托所购代理店或有资格的专业部门。 ·不得将阀门安装在压力释放管上。 ·必须装有补充水箱,不能直接与自来水管连接。 ·供热水管,应与屋顶水箱连接,不要直接接自来水。 ·锅炉不要安装在潮湿的地方。 ·气表与锅炉要保持一定的距离,设立防火墙,保证锅炉运作的安全性。 根据当地水质情况,锅炉应增加排污次数,次数由操作人员自行设定。蒸汽锅炉必须使用软水设备,热水锅炉推荐选用(硅磷晶)水处理。不安装水处理时基本是一年好,二年赖,三年就烧坏。因为水垢也将付出更多的使用成本(燃料)水垢原因还可能引起锅炉爆炸 开机工作程序 1 将手动键切换成自动位置;按下点火键, 燃烧器开始工作,锅炉投入全自动工作程序:燃烧器工作8--10分钟后,观察烟囱冒烟情况,若没有黑烟,说明各系统比例合理,燃烧器运转正常,若有黑烟,则应调整燃烧器的风门,直至不冒黑烟时为止; 2 锅炉在运行中,当水位降到最低安全水位线时,电控箱能自动亮起危险水位灯,并报警蜂鸣响,同时,启动水泵工作,这时应及时查看水泵是否按指令工作,止由于控制系统或水泵失误,影响正常运行; 3 锅炉在运行中,若观察不到水位计的水位线位置时,必须立即在

水位计处放水,如果出水流畅,则说明供水过满,这时需手动停止水泵工作,继续放水,直正水位位线时,再换成自动运行。若水位计放不出水,说明水位己经低于水位计的最低可见边缘,此时,必须立即停止锅炉运行,关停燃烧器和水泵,开启排污阀,如果排水过急,则应立即关闭排污阀,检查水泵和电控箱的线路是否失控,修复后,锅炉才能继续投入运行。如果排污阀排水缓慢,甚至没有水排出来,仅冒少量蒸汽,此时说明 锅炉已严重缺水,已处于“烧干锅”的状态。此时,千万不能进水,以免发生破坏性的严重后果。这时,锅炉必须停止运行1小时以上,并打开手孔,卸下燃烧器和炉顶板,仔细检查锅护的损坏情况,并上报上级主管部门和当地锅炉监督部门,作进一步检查。若情况正常,才能投入运行。若情况严重,则由当地锅炉监督部门作出检查结论,按结论处理。 燃气锅炉在使用中因为气压,环境,水垢,电压等问题会出现故障运行注意事项: 主控器及电器类配件禁止自行拆卸,防止触电及其它事故发生。燃气燃烧器及阀门组严禁自行拆卸及调整,在必须调整或清扫的情况下,需有资质的人员进行操作。 。故障现象及排除方法(燃气锅炉) 使用中发生故障,请按下面的内容找出故障原因,并进行调节,若找不出原因或排除不了故障。请及时与您购买的销售店或代理店取得联系,切勿乱拆。

600MW超临界汽轮机DEH说明书

600MW超临界机组DEH系统说明书 1汽轮机概述 超临界600/660MW中间再热凝汽式汽轮机主要技术规范 注意: 上表中的数据为一般数据,仅供参考,具体以项目的热平衡图为准。 由于锅炉采用直流炉,再热器布置在炉膛较高温区,不允许干烧,必须保证最低冷却流量。这就要求在锅炉启动时,必须打开高低压旁路,蒸汽通过高旁进入再热器,再经过低旁进入凝汽器。而引进型汽轮机中压缸在冷态启动时不参与控制,仅全开全关,所以在汽轮机冷态启动时,要求高低旁路关闭,再热调节阀全开,主蒸汽进入汽轮机高压缸做功,经高排逆止门进入再热器,经再热后送入中低压缸,再进入凝汽器。由于汽轮机在启动阶段流量较小,在3000 r/min 时只有3-5%的流量,远远不能满足锅炉再热器最低的冷却流量。因此,在汽轮机启动时,再热调节阀必须参加控制,以便开启高低压旁路,以满足锅炉的要求。所以600MW 超临界汽轮机一般要求采用高中压联合启动(即bypass on)的启动方式。 2高中压联合启动 高中压缸联合启动,即由高压调节汽阀及再热调节阀分别控制高压缸及中压缸的蒸汽流量,从而控制机组的转速。高中压联合启动的要点在于高压缸及中低压缸的流量分配。启动过程如下:

2.1 盘车(启动前的要求) 2.1.1主蒸汽和再热蒸汽要有56℃以上的过热度。 2.1.2 高压内缸下半第一级金属温度和中压缸第一级持环下半金属温度,大于204 ℃时,汽轮机采用热态启动模式,小于204℃时,汽轮机采用冷态启动模式,启动参数见图“主汽门前启动蒸汽参数”,及“热态起启动的建议”中规定。 冷再热蒸汽压力最高不得超过0.828MPa(a)。 高中压转子金属温度大于204℃,则汽机的启动采用热态启动方式,主蒸汽汽温和热再热汽温至少有56℃的过热度,并且分别比高压缸蒸汽室金属温度、中压缸进口持环金属温度高56℃以上,主蒸汽压力为对应主蒸汽进口温度下的压力。第一级蒸汽温度与高压转子金属温度之差应控制在 56℃之内,热再热汽温与中压缸第一级持环金属温差也应控制在这同样的水平范围。在从主汽阀控制切换到调节阀控制之前,主汽阀进汽温度应大于“TV/GV切换前最小主汽温”曲线的限值(参见“主汽门前启动蒸汽参数”曲线)。 2.1.3 汽轮机的凝汽器压力,应低于汽机制造厂推荐的与再热汽温有关的低压排汽压力限制值,在线运行的允许背压不高于0.0247MPa(a)。 2.1.4 DEH在自动方式。 2.2 启动冲转前(汽机已挂闸) 各汽阀状态: 主汽阀TV 关 高调阀GV 开 再热主汽阀RSV 开 再热调阀IV 关 进汽回路通风阀VVV开(600r/min至3050r/min关) 高排通风阀HEV 开(发电机并网,延迟一分钟关) 高排逆止阀NRV 关(OPC油压建立,靠高排汽流顶开) 高中压疏水阀开(分别在负荷大于10%、20%关高、中压疏水阀) 低排喷水阀关(2600r/min至15%负荷之间,开) 高旁HBP 控制主汽压力在设定值,并控制热再热温度在设定值 低旁LBP 控制热再热压力在设定值

某电厂启动锅炉技术规范书

. .. . 招标编号: 某电厂2×350MW低热值煤发电工程 建设总承包(EPC) 设备招标文件 启动锅炉设备 第三卷技术规书 2016年5月

目录 附件1 技术规 (1) 附件2 供货围 (42) 附件3 技术资料和交付进度 (49) 附件4 设备监造(检验)和性能验收试验 (54) 附件5 技术服务和设计联络 (59) 附件6 分包商/外购部件情况 (62) 附件7 大部件情况 (63) 附件12 技术规偏差表 (64) 附件13 投标方需要说明的其它容 (65) 附件14 招标文件附图 (66)

附件1 技术规 1 总则 1.1本技术规书编制原则和适用围 1.1.1本技术规书适用于某电厂2×350MW低热值煤发电工程超临界湿冷机组的启动锅炉设备。提出了该设备的功能设计、结构、性能、安装和试验等方面的技术要求。 1.1.2本技术规书只规定了主要原则和适用围,提出的是最低限度的要求,并未对一切细节作出具体规定,也未充分引述有关标准和规的条文。投标方应保证提供符合本技术规和工业标准的功能齐全的全新的优质产品及其相应服务。对有关安全、环保等强制性标准,满足其要求。 1.1.3投标方提供的产品应满足招标方的要求。 1.1.4在签订合同之后,招标方保留对本技术规提出补充要求和修改的权力,投标方承诺予以配合。如提出修改,具体项目和条件由投标方、招标方双方商定。 1.1.5 本技术规书所使用的标准如与投标方所执行的标准水平不一致时,按较高标准执行。 1.1.6本技术规书经双方签字认可后作为订货合同的附件,与合同正文具有同等效力。 1.1.7本工程采用KKS标识系统。投标方在中标后提供的技术文件(包括相关设备资料、图纸)须有KKS编写,KKS编码采用GB/T50549-2010《电厂标识系统编码标准》。具体标识要求由提出,在设计联络会上确定。 1.1.8在投标方所确定设备装置的选型围,招标方选择其中任何一种品牌都不会出现商务问题;为满足电厂对同类型设备的选型尽量统一的技术原则要求,投标方不可以任何理由拒绝招标方对热控设备选型的统一协调。外购设备的采购需接到招标方的书面确认通知后方可进行,同时重要设备或批量设备的技术协议签署时需邀请招标方有关人员参加并签字后方可有效,以便提高设备的安全和技术性能,确保控制接口完善。 1.1.9若本技术规各附件前后有不一致的地方,应以有利于设备安全运行、工程质量为原则,由招标方确认。 1.1.10按招标文件要求,投标方签定合同1个月提出合同设备的设计、制造、检验/试验、装配、安装、调试、试运、验收、试验、运行和维护等标准清单给招标方,供招标方确认。 1.1.11投标方对供货围的启动锅炉设备(含辅助系统及设备、附件等)负有全责,包括分包(或对外采购)的产品。分包(或对外采购)的主要产品制造商须事先征得招标方的认可。

生物质锅炉使用说明书模板

生物质锅炉使用说 明书

YG-48/9.2-T型锅炉 使用说明书 图号: 38300-0-0 编号: 383800 SSM 编制: 校对: 审核: 标审: 审定: 济南锅炉集团有限公司 4月 目录

一、概述 二、锅炉机组启动应具备的条件 三、锅炉机组启动前的检查与准备 四、锅炉机组启动 1、锅炉通风 2、锅炉冷启动 3、锅炉热启动 4、锅炉的升压操作 五、启动要求及注意事项 六、锅炉运行 1、锅炉正常运行 2、生物质点火的调节 七、停炉 1、正常停炉 2、紧急停炉 3、临时停炉 4、锅炉保温 5、锅炉疏水 八、停炉保护 九、故障处理 1、锅炉系统的停炉瓮中保护 2、低压循环系统的停炉保护

3、烟气系统的停炉保护 4、各部件的停炉保护 十、启动中的组织与分工 十一、检验及维护保养 一、前言 本锅炉是采用国外先进的生物燃料燃烧技术的48T/H振动炉排高温高汽锅炉。锅炉为高温、高压参数自然循环炉, 单锅筒、单炉膛、平衡通风、室内布置、固态排渣、全钢构架、底部支撑结构型锅炉。 锅炉安装完毕后的首次启动, 是对锅炉整套系统设计、安装的一次全面检查, 经过试运, 暴露和消除设备的缺陷和问题, 为机组投产做好准备, 经过启动如烘炉、煮炉、吹管等, 使运行人员经过操作设备, 熟悉系统, 积累经验, 检验各种连锁保护、自动系统投入率, 同时也是结燃烧系统、给料、除尘、除渣、辅机等的一次运行考核。在整定安全阀等工作结束后, 转入七十二小时试运。 本说明书主要是根据生物质燃料锅炉燃烧特点提出的特殊要求。锅炉的水、汽、电气等控制, 按有关规定执行。 二、锅炉机组启动应具备的条件 1、试运的现场条件

D600B启动运行说明书(DOC)

版本号:A 东方汽轮机厂 N600-16.7/538/538-1型汽轮机 运行说明书 编号D600B-000106ASM 第全册 2003年8月

编号D600B-000106ASM 编制 校对 审核 会签 审定 批准

关于本手册内容和使用上的重要通告 仔细阅读本手册,学习如何正确安装设备,否则可造成人员伤亡或设备损坏事故。 仔细保存并反复学习本手册,以保证长期连续安全运行。 本手册不是初级读物,只有经适当培训和取得资格证的人员才能使用本手册。本手册是根据用户方人员(他们已接受过本设备运行和维护方面的系统培训,以及经过技术指导)阅读和使用这一要求来编写的。 本手册不是一本完整的教科书,这类手册不可能涵盖设备方面的以及使用方面的所有信息资料。本手册没有提供安装时可能发生的每一偶然事件的解决方针及其信息资料,如发生本手册没有明确涵盖的任意情况均可向东方汽轮机厂提出咨询。 本手册的一个明确目的。本手册所包含的信息只能被用户所使用而且只包括了那些信息,即已购买了本设备的用户而且他们已向东方汽轮机厂提出了所要求的信息,其它人员和为其它目的而使用本手册均不能认可,对于那些非经认可的使用,东方汽轮机厂不承担任何责任而且不作陈述。 本手册不是担保书或合同文件,东方汽轮机厂关于本手册中的设备和包含的信息资料的保证只包括在东方汽轮机厂和用户之间所签订的合同之中。 本手册中包含了东方汽轮机厂的专利资料,东方汽轮机厂保留它们的所有权。为了我们之间的友好关系以及为了一个明确目的,我们提供了这些资料,接受者收到资料后应妥为保管,控制使用,并同意:(a)本手册不能全部或部分给予使用,复印或晒制,也不能泄露给除我们已发放者之外的任何其它第三方。 (b)本手册中包含的任何信息资料均不得编入其它文件中。 本手册文件内容允许修改而不事先通知。 版权所有,违者必究。东方汽轮机厂2003年。 1

东汽50MW汽机(启动运行说明书)

密级:公司秘密 东方汽轮机有限公司DONGFANG TURBINE Co., Ltd. N50-8.83-6型汽轮机 启动运行说明书 编号D50U-000106ASM 版本号 A 2013年4月

编号D50U-000106ASM 编制<**设计签字**> <**设计签字日期**> 校对<**校对签字**> <**校对签字日期**> 审核<**审核签字**> <**审核签字日期**> 会签<**标准化签字**> <**标准化签字日期**> <**会二签字**> <**会二签字日期**> <**会三签字**> <**会三签字日期**> <**会四签字**> <**会四签字日期**> <**会五签字**> <**会五签字日期**> <**会六签字**> <**会六签字日期**> <**会七签字**> <**会七签字日期**> <**会八签字**> <**会八签字日期**> <**会九签字**> <**会九签字日期**> 审定<**审批签字**> <**审批签字日期**> 批准<**批准签字**> <**批准签字日期**>

目录 序号章—节名称页数备注 1 编制说明 1 2 1 机组启动前的准备工作 1 3 1-1 机组启动必备条件 1 4 1-2 机组启动前的检查和准备 2 5 1-3 机组禁止启动范围 1 6 2 机组启动 1 7 2-1 原则性启动参数及定义 1 8 2-2 冷态滑参数启动 3 9 2-3 温态滑参数启动 3 10 2-4 热态、极热态滑参数启动 4 11 2-5 轴系临界转速数据 1 12 3 运行和维护 1 13 3-1 运行和维护的基本要求 3 14 3-2 机组启动运行的限制值 2 15 3-3 蒸汽参数的允许变化范围 1 16 3-4 偏周波运行限制值 1 17 3-5 定期检查试验 1 18 4 停机 1 19 4-1 正常停机前的准备工作 1 20 4-2 滑参数正常停机 3 21 4-3 额定参数正常停机 1 22 4-4 紧急停机 2

电厂煤粉锅炉点火启动

电厂煤粉锅炉点火启动 电厂煤粉锅炉点火启动、停运和低负荷助燃均需耗用大量的燃油。近年来,随着油价涨幅已近50 %连续上扬,使得电厂煤粉锅炉点火助燃成本大幅增加,如何降低电厂煤粉锅炉用油已迫在眉睫。这里主要从锅炉启停和正常维护着手谈谈。 1 锅炉启动时的节油 1、1 锅炉启动前及时投入炉底加热 在锅炉冷炉启动时,首先利用高辅联箱用汽投入炉底加热,初期控制加热用汽量,严格按规定的升温升压条件加热,以便使汽包和炉管金属膨胀良好。等达到一定温度(60℃)后可加大进气量或投入邻炉炉底高温高压(从邻炉汽包直接引出的蒸汽)的蒸汽,加快升温速度,等汽包壁温达100℃以上时再投油加热到冲转条件就比较容易了,大大缩短了投油时间。若300MW机组从冷态开始投油(安平均3支油,一只小油枪出力0、8T/H计算)升温至120℃左右,至少在5-7小时,最少也要耗油10吨以上,一年按照2次/台炉启动计算,节约费用在20万元人民币以上。及时地投入炉底加热不但节油还有以下好处:提高炉膛温度;缩短启动时间;消除冷热不均产生的热应力,避免热应力拉伤拉裂焊口;稳定燃烧`。 1、2 锅炉启动时的油风配比

锅炉厂一般按锅炉满负荷的30 %设计点火油枪出力,就单个点火燃烧器而言,油枪实际喷油量与点火时燃烧器供风量相对应的理论喷油量的差值往往达实际喷油量的50%左右。其差值部分的大多数形成了不完全燃烧损失,其中机械未完全燃烧损失占极大部分。主要原因有: 1、2、1 油雾结构同气流结构不匹配,油雾穿透风层。 1、2、2 风量与油量不匹配,油量远高于风量。 我们可以看看浙江大学点火燃烧器风油匹配问题实验室模拟研究的数据来说明,下面是在这两种情况下的模拟试验。 1234油量/ kg?h19 76、56 24、35 10、44 50、2α1、1 10、7 10、5 80、51收集油量/ kg?h200型工业性等离子发生器,可直接点燃煤粉,用于电厂锅炉的点火启动和稳燃

汽轮机安装使用说明书

型 9MW补汽凝汽式汽轮机安装使用说明书 汽轮机集团股份有限公司 2007年12月

汽轮机股份有限公司安装使用说明书 型 9MW补汽凝汽式汽轮机共页第 1 页目录 一、用途 (2) 二、技术规范…………………………………3~5 三、主要辅助设备……………………………6~8 四、主要安装数据……………………………9~17 五、汽水电消耗表 (18) 六、汽轮机TSI监测装置 (19) 七、测点参数…………………………………20~22 八、工况图、修正曲线及热平衡图…………23~27 资料来源编制 校对 审核 提出部门标准审查

标记处数更改文件号签字日期批准文件审定 前言 本说明书仅介绍了汽轮机的主要技术规范、辅助设备、安装数据等内容,有关安装、运行、维护等内容见《安装使用说明书》(第二分册)。 一、用途 本汽轮机适用企业自备电站及公用电站,不适于拖动变速旋转机械。

二、技术规范 产品代号KD9663 产品型号型 额定功率MW 9 经济功率MW 9 额定转速r/min 3000 旋转方向顺汽流方向看为顺时针 额定进汽压力及变化范围MPa + –(绝对) 额定进汽温度及变化范围℃ 370+15–15 额定工况进汽量t/h ~37 Ⅰ额定补汽压力及调整范围MPa + –(绝对) 额定工况补汽温度℃150 额定补汽量/最大补汽量t/h 14/16 Ⅱ额定抽汽压力及调整范围MPa 额定工况抽汽温度℃额定抽汽量/最大抽汽量t/h 冷却水温 正常℃25 最高℃33 额定排汽压力MPa (绝对) 临界转速r/min ~1983 额定转速时振动值mm ≤ (全振幅) 临界转速时振动值mm ≤ (全振幅) 汽轮机安装时最大件重量t ~26 汽轮机检修时最大件重量t ~20 转子重量t 运行层标高m 8

某电厂启动锅炉技术规范书

招标编号: 某电厂2×350MW低热值煤发电工程 建设总承包(EPC) 设备招标文件 启动锅炉设备 第三卷技术规范书

2016年5月

目录 附件1 技术规范 (1) 附件2 供货范围 (55) 附件3 技术资料和交付进度 (63) 附件4 设备监造(检验)和性能验收试验 (69) 附件5 技术服务和设计联络 (75) 附件6 分包商/外购部件情况 (79) 附件7 大部件情况 (80) 附件12 技术规范偏差表 (81) 附件13 投标方需要说明的其它内容 (82) 附件14 招标文件附图 (83)

附件1 技术规范 1 总则 1.1本技术规范书编制原则和适用范围 1.1.1本技术规范书适用于某电厂2×350MW低热值煤发电工程超临界湿冷机组的启动锅炉设备。提出了该设备的功能设计、结构、性能、安装和试验等方面的技术要求。 1.1.2本技术规范书只规定了主要原则和适用范围,提出的是最低限度的要求,并未对一切细节作出具体规定,也未充分引述有关标准和规范的条文。投标方应保证提供符合本技术规范和工业标准的功能齐全的全新的优质产品及其相应服务。对国家有关安全、环保等强制性标准,满足其要求。 1.1.3投标方提供的产品应满足招标方的要求。 1.1.4在签订合同之后,招标方保留对本技术规范提出补充要求和修改的权力,投标方承诺予以配合。如提出修改,具体项目和条件由投标方、招标方双方商定。 1.1.5 本技术规范书所使用的标准如与投标方所执行的标准水平不一致时,按较高标准执行。 1.1.6本技术规范书经双方签字认可后作为订货合同的附件,与合同正文具有同等效力。 1.1.7本工程采用KKS标识系统。投标方在中标后提供的技术文件(包括相关设备资料、图纸)须有KKS编写,KKS编码采用GB/T50549-2010《电厂标识系统编码标准》。具体标识要求由设计院提出,在设计联络会上确定。 1.1.8在投标方所确定设备装置的选型范围内,招标方选择其中任何一种品牌都不会出现商务问题;为满足电厂对同类型设备的选型尽量统一的技术原则要求,投标方不可以任何理由拒绝招标方对热控设备选型的统一协调。外购设备的采购需接到招标方的书面确认通知后方可进行,同时重要设备或批量设备的技术协议签署时需邀请招标方有关人员参加并