基坑降排水施工方案
基坑降排水施工方案
_s e c r e t(总6页) -CAL-FENGHAI.-(YICAI)-Company One1
-CAL-本页仅作为文档封面,使用请直接删除
随州碧桂园云山竹语D-2区二标段537#、538#、539#楼
基坑降、排水施工方案技术负责人:
编制单位:湖北三箭建筑有限公司
编制日期:二〇一三年十月十二日
目录
1. 工程概况···································································································错误!未指定书签。
2.场地工程地质情况·····················································································错误!未指定书签。
2.1.地层结构及岩性特征 ························································································错误!未指定书签。
2.2. 场地水文及气象情况 ·······································································错误!未指定书签。
3. 基坑降排水设计 ························································································错误!未指定书签。
3.1. 降水设计·························································································错误!未指定书签。
3.2.排水设计·············································································································错误!未指定书签。
4. 施工··········································································································错误!未指定书签。
4.1施工顺序及方法 ···················································································错误!未指定书签。
施工注意事项 ···························································································错误!未指定书签。
5. 基坑降水对周边环境影响及处理方案 ························································错误!未指定书签。
6. 抽水监测与管理 ························································································错误!未指定书签。
7. 安全文明施工措施·····················································································错误!未指定书签。
7.1安全保证措施·······················································································错误!未指定书签。
7.2文明施工措施·······················································································错误!未指定书签。
1.工程概况
本工程场地交通方便。场地地形复杂,绝对标高变化范围为99.8~105.36。
本工程基坑采用放坡开挖,从自然土面挖承台和基础梁,最深处为6m。
由于基坑深度不大,基坑采用放坡开挖,开挖时以进行坑内集水明排,降水深度在基底不小于0.5m。
2.场地工程地质情况
以下数据均引自《随州碧桂园云山竹语D区高层岩土工程勘察报告》。
2.1. 地层结构及岩性特征
场地在深度11米范围内,自上而下依次为:①杂填土;②粉质粘土;③强风化橄榄辉长岩;④中风化橄榄辉长岩。
2.2. 场地水文及气象情况
本工程地下水位为赋存于杂填土中的上层地表水,主要受大气降水下渗补给,没有统一的自由水位,随季节而变化。
根据水质分析结果判定,场地地下水对混凝土结构,对混凝土及混凝土中的钢筋具有微腐蚀性。
3.基坑降排水设计
3.1. 降水设计
3.1.1方案选择
沿基坑下口周边设计集水井,形成明沟排水的方法进行降水,保证降水的可靠性和安全性。
3.1.2水泵选取
根据实际情况选择4台潜水泵,其技术参数如下所示。
潜水泵技术性能表6-124
3.2. 排水设计
基坑中地下地表水渗出后用潜水泵抽到排水明沟中,再到集水井。然后由水泵抽至城市雨污水系统中。集水井及明沟的位置见附图一
4.施工
4.1施工顺序及方法
为确保地基不被水破坏,土方的开挖要同排水方案紧密结合,做到先排水、降水,再进行分层开挖。
根据现场实际情况,对基坑进行排水、降水分为两个阶段:挖土期间降排水和土方回填之前降排水。
4.1.1挖土期间降排水
根据土方在平面上的开挖顺序和开挖分区,在基坑四周分区设置连通的排水明沟,并在各区内渗水量大的部位留设集水井,在集水井内安放潜水泵排水,以达到排水、降水的目的。
具体做法为如下:
a.在挖掘机承台基础梁的时候发现有地表水渗处时,将挖掘机移至基坑角部边缘,开挖基坑周边的集水井。开挖范围为1m宽。放入潜水泵和滤水笼,进行抽水。
b.继续土方开挖,重复上述工作,直至土方挖至设计标高。
4.1.2土方回填之前降排水
土方挖至设计标高后,开挖集水井和排水沟。.然后以集水井为起点,向外开挖排水沟,挖至预定标高后,用标准砖砌筑排水沟沟底用砂浆找坡,避免建筑垃圾堵塞明沟,而导致排水不畅通。
集水井井底比承台底标高低500mm,排水沟沟底比主楼底板底标高低600mm。排水沟必须设有一定的坡度,以利于沟内积水顺利流入集水井内。准备4台潜水泵备用如遇雨雪天或局部承台基坑有地表水渗出时,确保基坑内无水浸泡。
集水井及盲沟应该视现场涌水量大小而决定其数量及位置,特殊地方经建设单位、监理、各施工单位联合讨论后再做决定,但一定要保证工程质量及施工安全。
5.2.1.4 施工注意事项
1.所有排水均直接排入城市雨污水系统中。
2.先开挖集水井,再从集水井开始逐渐向外开挖排水沟,始终保证地基处于干燥状态是关键;;
3.如果地下水涌水量大,除集水井和基坑中必须各设有一个潜水泵外,另外准备两个备用泵。并配备专人二十四小时值班,随时检查设备的运转状况,做到随时发现故障,随时排除故障,必须保证降水的连续性,从而保证底板浇筑前地基土的干燥;
4.所用电缆必须采用三相五线制,随时检查电缆线的有无破损,做到安全施工;
5.垫层浇筑时必须充分振捣密实,使其还要起到防水隔离的作用;
6.严格管理施工现场,禁止乱倒垃圾,以免造成堵塞盲沟,影响降水;
7.对场地外围要做好污水、雨水排水措施,禁止污水、雨水流入基坑内;
8.对基坑边缘位于底板下部的排水沟,所留排水沟截面尺寸深度不得大于600mm、宽度不得大于 200mm,以免影响底板的承载力。
9.以已有集水井为基准,向两侧开挖排水明沟,保证集水的畅通,使地基不致被水泡坏。
10.开挖不要盲目赶进度,一定要保证降水。
11.制作两部爬梯方便人员上下。
5.基坑降水对周边环境影响及处理方案
由于本工程基坑用水量较少,基坑降水对环境的影响很小。
6.抽水监测与管理
(1)对抽水设备应建立定期检修保养制度,保持设备的正常运行。
(2)抽出的水排至城市雨污水系统,不应产生回渗。遇有大雨或暴雨,应及时排除地面和基坑积水,以减少下渗,保证降水。
7.安全文明施工措施
7.1安全保证措施
7.1.1 工作人员,必须严格执行有关规范、操作规程和本施工组织设计。
7.1.2 施工人员必须戴安全帽上岗,爬高必须系安全带。
7.1.3 受建设方、监理公司及治安部门对现场质、治安、环卫等工作的管理和监督。
7.1.4 场供电线路的设计、安装要合理、牢固,移动性用电设备必须用电缆供电并安装漏电保护装置,主电线路必须由专职工员负责,任何人员不得随意推、拉闸刀。
7.1.5 照明电灯必须用低压供电,严禁使用220V 交流电手灯。
7.1.6 坑上口按安全要求搭设基坑围栏。
7.2文明施工措施
1)工地主要入口要设置大门,门旁必须设立明显的标牌,标出工程名称、施工单位和工程
负责人姓名。
2)建立文明施工责任制,划分区域,明确管理责任人,实行挂牌制,做到现场清洁整齐。
3)施工现场场地平整,道路坚实畅通。
4)施工现场临时水点应由专人管理,不得有常流水常明灯。
5)施工现场的临时设施,包括生产、办公、民用用房、仓库、料场,临时上下水管道及照
明动力线路,要严格遵循有关规定及施工设计确定的施工平面图布置,搭设整齐。
6)操作地点和周围必须清洁整齐,做到活完脚下清。
7)泥浆在运输过程中,不洒、不漏,丢洒在路上的泥浆及时清理。
8)施工现场不准乱堆垃圾及余物,应在适当地点设置监时堆放点,并定期清运或外运渣
上、垃圾及流体物品,并要采取遮盖防漏措施。
9)在钢筋制作场地、钻孔施工场地等处设置告示板,注明主要施工数据,以便于监督和检
查。
10)施工现场设置宣传标语和黑板报,并适时更换内容,做到鼓舞土气,表扬先进鞭策后
进。
11)进入施工现场的人员必须配戴胸卡和安全帽,严格穿插鞋、凉鞋、高根鞋及带钉后根
鞋,严禁酒后进入施工现场。
12)现场使用的钻机、钢筋加工机等应按平面图位置摆放,遵守机械安全技术规程,经常保
持机身周围环境的清洁,机械的标记、编号明显,安全装置可靠。
13)清洁机械排出的污水要有排放措施,不得随地流淌。
14)所有机械必须根据的性能,分期分阶段定期检修、保养,并记录备案。
15)建立健全机械设备定机、定人、定岗位责任的三定制度,操作证制度,交接班制度和奖
罚制度。