COMMISSIONING
Vacon Plc Tel:+358-201-2121
Fax:+358-201-212 205On-call:+358-40-8371 150E-mail:vacon@https://www.360docs.net/doc/434425655.html,
Vacon Page 73 (90)8 COMMISSIONING
8.1 Safety precautions
Before the commissioning, observe the following warnings and instructions:
Commissioning 8.2 Sequence of operation
1Read and follow the safety precautions
2After installation ensure that:
-the frequency converter and motor are connected to ground.
-the mains and motor cables are comply with the installation
and connection instructions (chapter 6.1).
-control cables are located as far as possible from the power cables
(table 6.1.4-1), shields of the control cables are connected
to the protective earth and wires do not have contact with any electri-
cal components in the device.
-the common input of digital input groups is connected to +24 V or
ground of the I/O-terminal or external supply
Page 74 (90)Vacon Vacon Plc Tel:+358-201-2121
Fax:+358-201-212 205On-call:+358-40-8371 150E-mail:vacon@https://www.360docs.net/doc/434425655.html,
3Check the quantity and quality of the cooling air (chapters 5.1 and 5.2).
4Check that moisture has not condensed inside the frequency converter.
5Check that all Start/stop switches connected to the I/O terminals are in Stop position.6Connect the Vacon frequency converter to the mains and switch the power ON.7Ensure that the parameters of the Group 1 match the application.
Set the following parameters to match the motor nameplate:
- nominal voltage of the motor
- nominal frequency of the motor
- nominal speed of the motor
- nominal current of the motor
- supply voltage
See values on the rating plate of the motor.
8Start-up test without the motor
Make either test A or B:
A Controls from the I/O terminals:
-turn Start/Stop switch to ON position
-change the frequency reference
-check in the control panel's Monitoring menu that the
output frequency follows the frequency reference
-turn Start/Stop switch to position OFF
B Controls from the Control Panel:
-change controls from the I/O terminals to the Control Panel with
the programmable button #2, see Chapter 7.6.
-push the Start button
-go to the Reference menu and change the frequency reference
with the buttons , see Chapter 7.5
-go to the Monitoring menu and check that the output frequency
follows the reference, see Chapter 7.3.
-push the Stop button
Commissioning
Vacon Plc Tel:+358-201-2121
Fax:+358-201-212 205On-call:+358-40-8371 150E-mail:vacon@https://www.360docs.net/doc/434425655.html, Vacon Page 75 (90)9If possible, make a start-up test with a motor which is not connected to the process.
If the inverter has to be tested on a motor connected to the process, ensure it is safe to be powered up. Inform your co-workers about the tests.
-switch the mains OFF and wait until the Vacon frequency converter
has powered down according to Chapter 8.1/ point 4
-connect the motor cable to the motor and the power terminals of
the Vacon frequency converter
-check that all start/stop switches connected to the I/O terminals
are in OFF position
-switch the mains ON
-repeat the test A or B of the start-up test #8.
10Connect the motor to the process (if the previous tests were done without the process)
-ensure that the inverter is safe to be powered up
-inform your co-workers about the tests.
-repeat the test A or B of the start-up test #8.
Commissioning