COMMISSIONING

Vacon Plc Tel:+358-201-2121

Fax:+358-201-212 205On-call:+358-40-8371 150E-mail:vacon@https://www.360docs.net/doc/434425655.html,

Vacon Page 73 (90)8 COMMISSIONING

8.1 Safety precautions

Before the commissioning, observe the following warnings and instructions:

Commissioning 8.2 Sequence of operation

1Read and follow the safety precautions

2After installation ensure that:

-the frequency converter and motor are connected to ground.

-the mains and motor cables are comply with the installation

and connection instructions (chapter 6.1).

-control cables are located as far as possible from the power cables

(table 6.1.4-1), shields of the control cables are connected

to the protective earth and wires do not have contact with any electri-

cal components in the device.

-the common input of digital input groups is connected to +24 V or

ground of the I/O-terminal or external supply

Page 74 (90)Vacon Vacon Plc Tel:+358-201-2121

Fax:+358-201-212 205On-call:+358-40-8371 150E-mail:vacon@https://www.360docs.net/doc/434425655.html,

3Check the quantity and quality of the cooling air (chapters 5.1 and 5.2).

4Check that moisture has not condensed inside the frequency converter.

5Check that all Start/stop switches connected to the I/O terminals are in Stop position.6Connect the Vacon frequency converter to the mains and switch the power ON.7Ensure that the parameters of the Group 1 match the application.

Set the following parameters to match the motor nameplate:

- nominal voltage of the motor

- nominal frequency of the motor

- nominal speed of the motor

- nominal current of the motor

- supply voltage

See values on the rating plate of the motor.

8Start-up test without the motor

Make either test A or B:

A Controls from the I/O terminals:

-turn Start/Stop switch to ON position

-change the frequency reference

-check in the control panel's Monitoring menu that the

output frequency follows the frequency reference

-turn Start/Stop switch to position OFF

B Controls from the Control Panel:

-change controls from the I/O terminals to the Control Panel with

the programmable button #2, see Chapter 7.6.

-push the Start button

-go to the Reference menu and change the frequency reference

with the buttons , see Chapter 7.5

-go to the Monitoring menu and check that the output frequency

follows the reference, see Chapter 7.3.

-push the Stop button

Commissioning

Vacon Plc Tel:+358-201-2121

Fax:+358-201-212 205On-call:+358-40-8371 150E-mail:vacon@https://www.360docs.net/doc/434425655.html, Vacon Page 75 (90)9If possible, make a start-up test with a motor which is not connected to the process.

If the inverter has to be tested on a motor connected to the process, ensure it is safe to be powered up. Inform your co-workers about the tests.

-switch the mains OFF and wait until the Vacon frequency converter

has powered down according to Chapter 8.1/ point 4

-connect the motor cable to the motor and the power terminals of

the Vacon frequency converter

-check that all start/stop switches connected to the I/O terminals

are in OFF position

-switch the mains ON

-repeat the test A or B of the start-up test #8.

10Connect the motor to the process (if the previous tests were done without the process)

-ensure that the inverter is safe to be powered up

-inform your co-workers about the tests.

-repeat the test A or B of the start-up test #8.