模具及工装验收单
Autoliv:ok nok NA Remarks:
Checking list before trial 试模前检查清单
Danger of injure 伤害的危险物
Sharp edges 尖锐的边缘
Whether there are no damage in equipment 是否没有设备损伤
Parting line surface fit well 分型面贴合良好
Smooth texture of cavity,crackfree 型腔光滑、无裂缝
Surface roughness 光洁度要求
The circuit of water system is correct without leaking 冷却系统进出回路正确
Check the quality of polishing on all ribs 、bosses 检查所有筋、褡子的抛光质量
Fluent action of the ejection pin 顶出系统动作流畅
Complete components 零件是否装齐
Whether the size fit request 尺寸是否符合要求
Whether the components match with the drawing(eg.radius of the sprue bush 、location
ring 、mold plate 、all kinds of connectors, etc)
是否零件尺寸与图纸相匹配(如浇口套R 、定位圈、模板、各类接头等)
Label the die height and weight on the mold 将模重标识于模具上
Parting line surface fit well 模具型面质量是否达到要求
The pouring intake of mould is ok(Size,Position) 模具的浇注系统是否合理(尺寸,位置)
The type of water tie-in answer our need 水接头型号符合要求,无干涉
Position and size of the annectent plate or screw 安全连接板的尺寸、安装合适
Whether the position of exhaust is good 模具排气口位置是否合理
It is firm and safe when suspensory 起吊平稳、安全、无干涉
Nameplate of mould 模具铭牌
Stability of mould when it is moving on the mould carrier 模具开合模平稳
Checking list for the tool after trial 模具试模后检查清单:
Whether lt can move smoothly 是否能平稳动作
Whether it have no negative effect to the other equipment 对其他设备是否无影响
No air bubble,No drape,No mark by pulling,No distortion
是否无气泡、无褶皱、无拉伤和变形
Whether the flash fit request 飞边厚度是否符合要求
Whether the mushion is easy to take out 蘑菇头是否容易取出
Achieve the require of product size 产品尺寸达到要求
The texture of products is clear 产品纹理是否清晰
Reaction time 模具发泡周期( )秒
Whether it is easy to extraction products 产品取件是否方便
Documentation 文件:
Assembly drawing (Paper)组装图纸
Assembly drawing (CAD)组装图纸
Single part drawing (CAD)单个零件图纸
BOM mechanic 机械设备清单
Supplier index 供应商一览
Spare part listing 备件清单
Wearing part listing 易损件清单
Maintenace instructions 维修手册
Adjustment instructions 调整手册
Operation instructions 操作指导书
Environment influence evaluation 环境影响评估:
Risk assessment 风险评估
environment aspect 环境因素Supplier Mould & Frock approval 模具工装验收单
Project:
Date:Autoliv:
Pre-Finalapproval:Supplier:
Signiture
Location:Druck: 2017/4/6423199493.xls / 模具工装验收单1/2