题目:君山二期工程施工组织设计

一、外文原文:

1. Design project management

1.1 Choosing the planning practice

Choosing a suitable planning practice is extremely important. Introducing a pre-qualification process provides essential insights about efficiency, specialist knowledge and quality: three to five applicants receive preliminary design documents and the building programme. Then interviews are held, reference evidence examined and the practices visited on the spot. But the key features are planning quality, knowledge of materials, degree of detail, and CAD and office equipment. The ability to coordinate building and technical planning is particularly relevant.

1.2 Design and authorization planning

Coordination and control of the planning process and content are particularly important in this planning phase. In no circumstances should planning in China be left to the design institute alone. Regular planning and coordination meetings examine the planning process in its entirety to ensure that guidelines and standards are being met. It is important to coordinate routing and to check for collision points.

1.3 Working plans

Regular coordination, control and support are also required at the final planning stage. Coordinating building and technical workers within the planning team is often a weak point as well. Important details and technical specifications have to be demanded. It is not usual in China to present details on a scale of 1:20 to 1:5, and these planning features have to be insisted on; a great deal of convincing argument will be needed.

1.4 Invitation to tender and tender awards

Tender documents drawn up to Chinese standards are less detailed than comparable Western tender documents. Considerable importance should be attached to detailed working drawings. Drawings should be ranked before tender documents. It is not permissible to insist on specific product makes. Materials must be described neutrally

in terms of product. This means that the building firm is able to use inferior materials without the client's agreement. This often results in buildings with serious deficiencies in quality and execution. To avoid these negative consequences, architects try to go beyond the standard guidelines to prevent the use of inferior quality materials. Also, Chinese planning and industrial standards are antiquated and do not yet meet national or international standards.

As a rule, five to ten firms (general contractors or firms offering individual services) are invited to tender. Often foreign firms with branches in China are invited as well. Bids from such firms come out well above those of their Chinese competitors.

After the bids have been evaluated, negotiations are conducted with the most reasonable bidders. Awards are decided on the basis of reference projects, quality of execution and evaluations of special proposals. Because the subsoil is so poor, the use of deep foundations on alluvial land is widespread. To gain time, the underground engineering work can be put out to earlier tender and award to specialist building

firms.

1.5 Building and completion phase

The legislation requires using local site supervision and a quantity surveyor (see Chapter B 2.2). Site supervision requirements are not the same as the standard German site supervision requirements laid down in HOAI, Phase 8. Chinese site supervision practices offer the following service pattern under the headings "quality monitoring" and "safety management":

- examining the working plans

- quality control for building materials

- quality control for building plant and equipment

- building site safety

- checking current building progress

- examining the qualifications of the building site personnel

- demanding and examining inventory documents

Only building sites that also convey an impression of an orderly approach can produce quality and work effectively. This includes cleanliness and safety. Chinese building sites need pioneering work in this field. It does not make any sense to compel the contractor to adopt a particular working programme that runs counter to his own ideas. It is in fact advisable to make concessions in order to make best use of the available production and fitting methods. Quality control starts even in the planning phase. In the actual building phase, care should be taken to ensure that the required materials are really used, and that product-specific fitting requirements are met.

The contractor can make alternative proposals to the tender standards. These are examined and approved on the basis of specimens and references. It has turned out to be worthwhile to build specimen rooms before the actual building phase starts, to test the guidelines for details and materials and introduce improvements to materials and details in good time. It is essential to check and approve the quality of finish in the form of mock-ups before production begins for facades, roof areas and other critical

parts of the building.

1.6 Documentation

The quality control process ends with the correction of faults and the start-up phase. Buildings are officially accepted in China at the point of final acceptance. The quality bureau, the fire prevention department and the environmental health office have to approve in order to ensure successful acceptance. The as-complete plans should be drawn up by the planning practice, as the building firm usually delivers these too late, and in poor quality.

1.7 Communication

It is a characteristic feature of Chinese building projects that a large number of participants have to work together, under pressure from deadlines and cost factors, on the basis of differing information from various locations. This creates the necessity for a "digital platform" that gives those involved in the project access to up-to-date documents and the ability to communicate with the same aims in mind and to keep up with the work as it needs to be done. But the project management team should have access to central scheduling and work monitoring, including reporting. These systems link those involved in the project, control the workflow, and distribute news, documents and information.

2 Planning and building costs

2.1 Quantity surveying

Chinese quantity surveyors provide the same services as their English model. Quantity surveying is the generic term for cost planning and cost control. Quantity surveying includes tender award and contract management, both of which are part of the cost control process. The quantity surveyor is commissioned by the client directly and assists with planning and controlling project investment. He represents the client's financial interests throughout the entire course of the project. During the realization phase the quantity surveyor evaluates the level of work completed so that part payments and supplementary demands can be fixed, assists in warding off complaints, or evaluates and negotiates with the company over justifiable additional demands.

Effective cost control is carried out within the project management framework. All the costings are noted in a cost monitoring system. Cost monitoring is not a passive system. Precise project control means that cost changes can be identified even in the initial phase. Causes and effects of measures affecting costs are conveyed to the project management team at an early stage so that counter-measures can be introduced where necessary.

Cost reduction opportunities are largely exhausted by the end of the planning phase.

The diagram makes it clear that realization decisions made in the early planning phases crucially influence fixing the cost framework. The importance of control increases when planning is concluded and during the realization phase.

Despite the overwhelming volume of investment by Western standards, professional cost and schedule control rarely occurs in China. Moreover, clients who are commercially successful and put a great deal of money into building projects often have no knowledge of how to implement and control planning and building work, and often rely on their experience in other industries. Even though the predominant Chinese enterprise culture is not comparable with the Western world, professional project management will be indispensable in future if building investment is to accomplish its aims.

二、外文译文:

1.1选择一个切实可行的规划方式

选择一个切实可行的规划方式是很重要的。采用一种资格预审的方式能够给工作效率、专业知识和产品质量提供必要的洞察力:三到五个投标人能够获得项目的初步设计文件和项目规划方案。接着进行面谈,以实证考察和现场勘探表现为依据。但是最关键的因素是单位的规划质量、具备的材料知识、注重细节的程度、以及计算机辅助设计和办公设备。毕竟协调建设和技术规划的能力相当密切的。

1.2设计和授权规划

协调和控制规划过程及内容在规划阶段当中是相当重要的。在中国,任何情况

下都不能把设计工作单独留给设计院。定期进行规划和开展协调会议以此检查整个规划过程,这样才能确保指导方针和标准真正能够起到作用。这对协调指定的工艺流程路线和检查出产生矛盾的点是很重要的。

1.3工作计划

在规划的最后阶段,仍然需要常规协调、控制管理、各种技术支持。协调建设过程进度和技术工人的工作往往是整个规划队伍里面的薄弱环节。对于比较重要的细节和技术规范都必须作出严格地要求。1:20到1:5这样的一个细节方面的比例在目前的中国是很少见的,我们必须坚持这样的规划特点,鼓励团队成员们积极进行这方面的讨论。

1.4邀请投标和投标奖励

在起草的投标文件方面,中国的文件详细程度远远比不上西方国家做得好。值得考虑的一个重要的方面是,应该对工作图纸的详细程度给于足够的关注。在投标之前,应该对工程图纸的详细好坏程度进行排名。不能允许一意孤行地坚持使用特殊产品的决定。在所有列入考虑的材料当中,都要对任何一种材料进行客观中立的描述。这就是说,在文件详细程度上做得不够的话,可能建设单位在没有经过业主的同意,就可以使用劣质材料进行建设。这往往会导致建筑物在质量和使用方面存在严重的缺陷。要避免这些不良影响,建筑师需要跳出标准的指导方针的限制,进行适当变通,以此来避免建设过程中使用劣等材料的行为。因为中国的很多建设规划和行业标准都显得滞后,跟不上国家标准更跟不上国际标准。

邀请投标和奖励的流程图

这方面有个规定,一般邀请五到十架建设单位(传统的承包商或者是能够提供独立完整建设服务的个体团队)进行投标。当然了,国外的建设公司在中国的分支机构也会得到邀请。通常这些国外公司的报价往往会高于国内的其他竞争者。在对所有的投标进行评估后,选出几个个最合理的投标者进行详细谈判。是否中标取决于他们对项目的质量评估和给出的特殊建议。因为建筑的基础很差,而在冲积土地上使用深基础是很普遍的。为了能够争取时间,地下工程部分可以让早期的且这方面的专家较多的建设单位进行建设。

1.5建设和竣工阶段

法律上规定,这两个阶段需要监理进行现场监督,也需要一定数量的测量人员(详见B章2.2节)。现场监督的标准不同于德国的所要求的,坐标符合HOAI、相位8。中国的现场监督活动要提供以下的服务模式,正如下列标题所说的“质量监控”和“安全管理”:

-检查工作计划

-建筑材料的质量控制

-建设生产厂房和设备的质量控制

-建设施工现场的安全工作

-检查控制当前的项目进度

-检查施工现场工作人员的从业资格

-严格按要求检查相关库存文件

施工现场只有建筑用地,这会给人传达一种思想:一个井然有序的方法能够生产出有质量保证的产品并且高效率工作。这也包括清洁和安全。中国的建筑行业领域需要先驱者为其注入新鲜血液。强迫承包商采用一种与自己意愿相违背的特殊方法是没有意义的。实际上,做出这方面的让步是及其明智的,这样能够使现有的生产作业方法和施工模式得到最充分的利用。项目的质量控制在规划阶段就应该开始了。在建设进行阶段,要小心谨慎细心把关,确保需要的建材是真材实料,需要的特殊部件能够合适的安装到位。

对于承包商来说,他们可以提出能够替代投标标准的建议。这些建议需要审核,在承包商提供的样本和参考资料的基础上决定是否批准。事实证明,在建设阶段进行之前很有必要设立一个样本养护室,以便更详细的测试材料的细部性能,在合适的时间提出改善材料的方法。在开始进行的建筑的外墙、屋顶和其他关键部位的施工前,对部件模型的质量进行检查和审核是很游戏要的。

1.6文件材料

随着故障的纠正和项目的正式投入使用,质量控制阶段也就结束了。在中国,建筑只有在最终验收完成后才能被人们所接受。为了顺利完成验收,质量监督局、消防中心和环保办公室都不得不批准。随着计划的实施,完整的规划书应该尽早起草并完善结束,不能指望施工单位,因为在这方面他们的动作是在是太慢了。

1.7交流

中国的项目建设有一大显著的特点:有很多的参与者在为同一个项目共同工作着,他们顶着工期进度和成本费用的压力,可是却接收着来自不同地区的不同信息。这就为数字交流平台的产生创造了条件,数字平台给所有的参与者提供了最新的文档材料信息,也让大家能够在上面自由交流,为了共同的目标做应该做的事。但是该项目的管理团队要接受统一调控和工作监督,包括所有的报告。这个系统把所有参与进项目的人都连接起来,控制着工作流程、及时发布新闻、文档

和信息。

2规划和建设成本

2.1工程造价估算

中国的造价师提供着与榜样(英国测算员)相同的服务。造价估算是成本计划和成本控制的专业术语。造价估算包括招标奖励和合同管理,这些都是成本费用的组成部分。造价员直接接受业主的委托并协助控制规划和项目投资。在整个项目建设过程中,造价员代表了业主的财务利益。在即将完工阶段,造价员需要评估项目的完成程度,这样方便控制部分付款和额外支出,使之稳定不增长。这也有助于避免争端,与有额外补偿要求的公司进行协商。有效的成本控制是建立在成本管理框架上的。所有的支出款项在成本控制系统里面都有记录。成本控制是一个主动过程。真正精确地项目控制,即使在项目的最初阶段就能够识别出后续将要发生变动的成本。影响成本的因素和措施尽早地传递到项目管理团队当中的话,有助于及时有效地采取相对应的措施。

随着规划阶段的结束,降低成本的机会也大大地减少了。通过图表,可以很清楚地看出在早期规划阶段做出的实践决定对固定成本框架起到了很大程度的影响。

随着规划阶段的结束和实施阶段的开始,成本控制变得越来越重要。尽管受到西方国家巨额投资标准的影响,但是我国的项目管理还是不重视成本和进度控制。更糟糕的是,在生意上取得成功的业主,他们把大量的资金投入到了项目当中,但是却不知道如何实施计划和管理建设工作,还天真的用他们在生意上的经验来处理问题。虽然主要的中国企业文化同西方国家没有可比性,但是在接下来的建设当中,我们若想要实现投资的真正价值,那么专业化的项目管理是必不可少的。

土木工程外文翻译

转型衰退时期的土木工程研究 Sergios Lambropoulosa[1], John-Paris Pantouvakisb, Marina Marinellic 摘要 最近的全球经济和金融危机导致许多国家的经济陷入衰退,特别是在欧盟的周边。这些国家目前面临的民用建筑基础设施的公共投资和私人投资显著收缩,导致在民事特别是在民用建筑方向的失业。因此,在所有国家在经济衰退的专业发展对于土木工程应届毕业生来说是努力和资历的不相称的研究,因为他们很少有机会在实践中积累经验和知识,这些逐渐成为过时的经验和知识。在这种情况下,对于技术性大学在国家经济衰退的计划和实施的土木工程研究大纲的一个实质性的改革势在必行。目的是使毕业生拓宽他们的专业活动的范围,提高他们的就业能力。 在本文中,提出了土木工程研究课程的不断扩大,特别是在发展的光毕业生的潜在的项目,计划和投资组合管理。在这个方向上,一个全面的文献回顾,包括ASCE体为第二十一世纪,IPMA的能力的基础知识,建议在其他:显著增加所提供的模块和项目管理在战略管理中添加新的模块,领导行为,配送管理,组织和环境等;提供足够的专业训练五年的大学的研究;并由专业机构促进应届大学生认证。建议通过改革教学大纲为土木工程研究目前由国家技术提供了例证雅典大学。 1引言 土木工程研究(CES)蓬勃发展,是在第二次世界大战后。土木工程师的出现最初是由重建被摧毁的巨大需求所致,目的是更多和更好的社会追求。但是很快,这种演变一个长期的趋势,因为政府为了努力实现经济发展,采取了全世界的凯恩斯主义的理论,即公共基础设施投资作为动力。首先积极的结果导致公民为了更好的生活条件(住房,旅游等)和增加私人投资基础设施而创造机会。这些现象再国家的发展中尤为为明显。虽然前景并不明朗(例如,世界石油危机在70年代),在80年代领先的国家采用新自由主义经济的方法(如里根经济政策),这是最近的金融危机及金融危机造成的后果(即收缩的基础设施投资,在技术部门的高失业率),消除发展前途无限的误区。 技术教育的大学所认可的大量研究土木工程部。旧学校拓展专业并且新的学校建成,并招收许多学生。由于高的职业声望,薪酬,吸引高质量的学校的学生。在工程量的增加和科学技术的发展,导致到极强的专业性,无论是在研究还是工作当中。结构工程师,液压工程师,交通工程师等,都属于土木工程。试图在不同的国家采用专业性的权利,不同的解决方案,,从一个统一的大学学历和广泛的专业化的一般职业许可证。这个问题在许多其他行业成为关键。国际专业协会的专家和机构所确定的国家性检查机构,经过考试后,他们证明不仅是行业的新来者,而且专家通过时间来确定进展情况。尽管在很多情况下,这些证书虽然没有国家接受,他们赞赏和公认的世界。 在试图改革大学研究(不仅在土木工程)更接近市场需求的过程中,欧盟确定了1999博洛尼亚宣言,它引入了一个二能级系统。第一级度(例如,一个三年的学士)是进入

施工组织设计外文翻译

摘要: 建筑工程在施工过程中,施工组织方案的优劣不仅直接影响工程的质量,对工期及施工过程中的人员安全也有重要影响。施工组织是项目建设和指导工程施工的重要技术经济文件。能调节施工中人员、机器、原料、环境、工艺、设备、土建、安装、管理、生产等矛盾,要对施工组织设计进行监督和控制,才能科学合理的保证工程项目高质量、低成本、少耗能的完成。 关键词: 项目管理施工组织方案重要性 施工组织设计就是对工程建设项目整个施工过程的构思设想和具体安排,是施工组织管理工作的核心和灵魂。其目的是使工程速度快、质量好、效益高。使整个工程在施工中获得相对的最优效果。 1.编制施工组织设计重要性的原因 建筑工程及其施工具有固定性与流动性、多样性与单件性、形体庞大与施工周期长这三对特点。所以,每一建筑工程的施工都必须进行施工组织设计。这是因为:其它一般工业产品的生产都有着自己固定的、长期适用的工厂。而建筑施工具有流动性的特点,不可能建立这样的工厂,只能是当每一个建筑工程施工时,建立一个相应的、临时性的,如同工厂作用性质的施工现场准备,即工地。施工单件性特点与施工流动性特点,决定了每一建筑工程施工都要选择相应的机具和劳动力组织。选择施工方法、拟定施工技术方案及其劳动力组织和机具配置,统称为施工作业能力配置。施工周期的特点,决定了各种劳动力、机具和众多材料物资技术的供应时间也比较长,这就产生了与施工总进度计划相适应的物资技术的施工组织设计内容。由此可见,施工组织设计在项目管理中是相当重要的。 2.施工组织设计方案的重要性 建筑产品作为一种商品,在项目管理中工程质量在整个施工过程中起着极其重要的作用。工程建设项目的施工组织设计与其工程造价有着密切的关系。施工组织设计基本的内容有:工程概况和施工条件的分析、施工方案、施工工艺、施工进度计划、施工总平面图。还有经济分析和施工准备工作计划。其中,施工方案及施工工艺的确定更为重要,如:施工机械的选择、水平运输方法的选择、土方的施工方法及主体结构的施工方法和施工工艺的选择等等,均直接影响着工程预算价格的变化。在保证工程质量和满足业主使用要求及工期要求的前提下,优化施工方案及施工工艺是控制投资和降低工程项目造价的重要措施和手段。 2.1施工组织方案在很大程度上影响着工程质量,因此合理的施工组织方案不仅是确保工程顺利完成的基础,也是工程安全的依据。施工组织设计是建筑工

工程管理专业毕业设计外文翻译(外文+翻译)

Study on Project Cost Control of Construction Enterprises By: R. Max Wideman Abstract With the increasing maturity of construction market, the competition between construction enterprises is becoming fierce. The project profit is gradually decreasing. It demands that all construction enterprises enhance their cost control, lower costs, improve management efficiency and gain maximal profits. This paper analyses the existing problems on project cost control of Chinese construction enterprises, and proposes some suggestions to improve project cost control system. Key Words :Construction enterprises, Project management, Cost control After joining the WTO, with Chinese construction market becoming integrated, the competition among architectural enterprises is turning more intense. Construction enterprises must continually enhance the overall competitiveness if they want to develop further at home and abroad construction market. Construction Enterprises basically adopt the "project management-centered" model, therefore, it is particularly important to strengthen project cost control. 1.The Current Domestic Project Cost Classification and Control Methods Cost refers to the consumption from producing and selling of certain products, with the performance of various monetary standing for materialized labor and labor-consuming. Direct and indirect costs constitute the total cost, also known as production cost or manufacturing cost. Enterprise product cost is the comprehensive indicator to measure enterprise quality of all aspects. It is not only the fund compensation scale, but also the basis to examine the implementation of cost plan. Besides, it can provide reference for product pricing According to the above-mentioned definition and current domestic cost classification, construction project cost can be divided into direct costs and indirect costs. Direct costs include material cost, personnel cost, construction machinery cost, material transportation cost, temporarily facility cost, engineering cost and other direct cost. Indirect costs mainly result from project management and company's cost-sharing, covering project operating costs (covering the commission of foreign projects), project's management costs (including exchange losses of

土木工程外文翻译.doc

项目成本控制 一、引言 项目是企业形象的窗口和效益的源泉。随着市场竞争日趋激烈,工程质量、文明施工要求不断提高,材料价格波动起伏,以及其他种种不确定因素的影响,使得项目运作处于较为严峻的环境之中。由此可见项目的成本控制是贯穿在工程建设自招投标阶段直到竣工验收的全过程,它是企业全面成本管理的重要环节,必须在组织和控制措施上给于高度的重视,以期达到提高企业经济效益的目的。 二、概述 工程施工项目成本控制,指在项目成本在成本发生和形成过程中,对生产经营所消耗的人力资源、物资资源和费用开支,进行指导、监督、调节和限制,及时预防、发现和纠正偏差从而把各项费用控制在计划成本的预定目标之内,以达到保证企业生产经营效益的目的。 三、施工企业成本控制原则 施工企业的成本控制是以施工项目成本控制为中心,施工项目成本控制原则是企业成本管理的基础和核心,施工企业项目经理部在对项目施工过程进行成本控制时,必须遵循以下基本原则。 3.1 成本最低化原则。施工项目成本控制的根本目的,在于通过成本管理的各种手段,促进不断降低施工项目成本,以达到可能实现最低的目标成本的要求。在实行成本最低化原则时,应注意降低成本的可能性和合理的成本最低化。一方面挖掘各种降低成本的能力,使可能性变为现实;另一方面要从实际出发,制定通过主观努力可能达到合理的最低成本水平。 3.2 全面成本控制原则。全面成本管理是全企业、全员和全过程的管理,亦称“三全”管理。项目成本的全员控制有一个系统的实质性内容,包括各部门、各单位的责任网络和班组经济核算等等,应防止成本控制人人有责,人人不管。项目成本的全过程控制要求成本控制工作要随着项目施工进展的各个阶段连续 进行,既不能疏漏,又不能时紧时松,应使施工项目成本自始至终置于有效的控制之下。 3.3 动态控制原则。施工项目是一次性的,成本控制应强调项目的中间控制,即动态控制。因为施工准备阶段的成本控制只是根据施工组织设计的具体内容确

施工组织设计外文翻译

XXXXXXXXX 毕业设计(论文)外文翻译 学生姓名: 院(系): 专业班级: 指导教师: 完成日期:

施工组织设计的重要性 摘要: 建筑工程在施工过程中,施工组织方案的优劣不仅直接影响工程的质量,对工期及施工过程中的人员安全也有重要影响。施工组织是项目建设和指导工程施工的重要技术经济文件。能调节施工中人员、机器、原料、环境、工艺、设备、土建、安装、管理、生产等矛盾,要对施工组织设计进行监督和控制,才能科学合理的保证工程项目高质量、低成本、少耗能的完成。 关键词: 项目管理施工组织方案重要性 施工组织设计就是对工程建设项目整个施工过程的构思设想和具体安排,是施工组织管理工作的核心和灵魂。其目的是使工程速度快、质量好、效益高。使整个工程在施工中获得相对的最优效果。 1.编制施工组织设计重要性的原因 建筑工程及其施工具有固定性与流动性、多样性与单件性、形体庞大与施工周期长这三对特点。所以,每一建筑工程的施工都必须进行施工组织设计。这是因为:其它一般工业产品的生产都有着自己固定的、长期适用的工厂。而建筑施工具有流动性的特点,不可能建立这样的工厂,只能是当每一个建筑工程施工时,建立一个相应的、临时性的,如同工厂作用性质的施工现场准备,即工地。施工单件性特点与施工流动性特点,决定了每一建筑工程施工都要选择相应的机具和劳动力组织。选择施工方法、拟定施工技术方案及其劳动力组织和机具配置,统称为施工作业能力配置。施工周期的特点,决定了各种劳动力、机具和众多材料物资技术的供应时间也比较长,这就产生了与施工总进度计划相适应的物资技术的施工组织设计内容。由此可见,施工组织设计在项目管理中是相当重要的。 2.施工组织设计方案的重要性 建筑产品作为一种商品,在项目管理中工程质量在整个施工过程中起着极其重要的作用。工程建设项目的施工组织设计与其工程造价有着密切的关系。施工组织设计基本的内容有:工程概况和施工条件的分析、施工方案、施工工艺、施工进度计划、施工总平面图。还有经济分析和施工准备工作计划。其中,施工方案及施工工艺的确定更为重要,如:施工机械的选择、水平运输方法的选择、土方的施工方法及主体结构的施工方法和施工工艺的选择等等,均直接影响着工程预算价格的变化。在保证工程质量和满足业主使用要求及工期要求的前提下,优化施工方案及施工工艺是控制投资和降低工程项目造价的重要措施和手段。 2.1施工组织方案在很大程度上影响着工程质量,因此合理的施工组织方案 不仅是确保工程顺利完成的基础,也是工程安全的依据。施工组织设计是建筑工程设计文件的重要组成部分,是编制工程投资概预算的主要依据和编制招投标文件的

工程管理工程造价中英文对照外文翻译文献

中英文资料对照外文翻译 Design phase of the project cost management Abstract Project cost management is the basic contents to determine reasonable and effective control of the project cost. Described the current stage of the project cost management situation on the strengthening of the various stages of construction cost management of the importance of and raised a number of key initiatives. Keywords:cost of the construction project cost management status investment decision phase of the design phase of the implementation phase of the cost management in a market economy, Even under the WTO and China's accession to the world community, China's construction industry how to effectively control construction cost of the construction and management of an important component part. However, the current budget for the construction projects - estimate, budget, Super budget accounts for the "super three" is still widespread and that eventually led to a serious loss of control of project investment. Project cost management is the basic contents to determine reasonable and effective control of the project cost. As the project cost to the project runs through the entire process, stage by stage can be divided into Investment Decision stage, the design and implementation phases. The so-called Project Cost effective control is the optimization of the construction plans and design programs on the basis of in the building process at all stages, use of certain methods and measures to reduce the cost of the projects have a reasonable control on the scope and cost of the approved limits.

土木工程毕业设计外文文献翻译修订版

土木工程毕业设计外文文献翻译修订版 IBMT standardization office【IBMT5AB-IBMT08-IBMT2C-ZZT18】

外文文献翻译 Reinforced Concrete (来自《土木工程英语》) Concrete and reinforced concrete are used as building materials in every country. In many, including the United States and Canada, reinforced concrete is a dominant structural material in engineered construction. The universal nature of reinforced concrete construction stems from the wide availability of reinforcing bars and the constituents of concrete, gravel, sand, and cement, the relatively simple skills required in concrete construction, and the economy of reinforced concrete compared to other forms of construction. Concrete and reinforced concrete are used in bridges, buildings of all sorts underground structures, water tanks, television towers, offshore oil exploration and production structures, dams, and even in ships. Reinforced concrete structures may be cast-in-place concrete, constructed in their final location, or they may be precast concrete produced in a factory and erected at the construction site. Concrete structures may be severe and functional in design, or the shape and layout and be whimsical and artistic. Few other building materials off the architect and engineer such versatility and scope. Concrete is strong in compression but weak in tension. As a result, cracks develop whenever loads, or restrained shrinkage of temperature changes, give rise to tensile stresses in excess of the tensile strength of the concrete. In

土木工程外文文献翻译

专业资料 学院: 专业:土木工程 姓名: 学号: 外文出处:Structural Systems to resist (用外文写) Lateral loads 附件:1.外文资料翻译译文;2.外文原文。

附件1:外文资料翻译译文 抗侧向荷载的结构体系 常用的结构体系 若已测出荷载量达数千万磅重,那么在高层建筑设计中就没有多少可以进行极其复杂的构思余地了。确实,较好的高层建筑普遍具有构思简单、表现明晰的特点。 这并不是说没有进行宏观构思的余地。实际上,正是因为有了这种宏观的构思,新奇的高层建筑体系才得以发展,可能更重要的是:几年以前才出现的一些新概念在今天的技术中已经变得平常了。 如果忽略一些与建筑材料密切相关的概念不谈,高层建筑里最为常用的结构体系便可分为如下几类: 1.抗弯矩框架。 2.支撑框架,包括偏心支撑框架。 3.剪力墙,包括钢板剪力墙。 4.筒中框架。 5.筒中筒结构。 6.核心交互结构。 7. 框格体系或束筒体系。 特别是由于最近趋向于更复杂的建筑形式,同时也需要增加刚度以抵抗几力和地震力,大多数高层建筑都具有由框架、支撑构架、剪力墙和相关体系相结合而构成的体系。而且,就较高的建筑物而言,大多数都是由交互式构件组成三维陈列。 将这些构件结合起来的方法正是高层建筑设计方法的本质。其结合方式需要在考虑环境、功能和费用后再发展,以便提供促使建筑发展达到新高度的有效结构。这并

不是说富于想象力的结构设计就能够创造出伟大建筑。正相反,有许多例优美的建筑仅得到结构工程师适当的支持就被创造出来了,然而,如果没有天赋甚厚的建筑师的创造力的指导,那么,得以发展的就只能是好的结构,并非是伟大的建筑。无论如何,要想创造出高层建筑真正非凡的设计,两者都需要最好的。 虽然在文献中通常可以见到有关这七种体系的全面性讨论,但是在这里还值得进一步讨论。设计方法的本质贯穿于整个讨论。设计方法的本质贯穿于整个讨论中。 抗弯矩框架 抗弯矩框架也许是低,中高度的建筑中常用的体系,它具有线性水平构件和垂直构件在接头处基本刚接之特点。这种框架用作独立的体系,或者和其他体系结合起来使用,以便提供所需要水平荷载抵抗力。对于较高的高层建筑,可能会发现该本系不宜作为独立体系,这是因为在侧向力的作用下难以调动足够的刚度。 我们可以利用STRESS,STRUDL 或者其他大量合适的计算机程序进行结构分析。所谓的门架法分析或悬臂法分析在当今的技术中无一席之地,由于柱梁节点固有柔性,并且由于初步设计应该力求突出体系的弱点,所以在初析中使用框架的中心距尺寸设计是司空惯的。当然,在设计的后期阶段,实际地评价结点的变形很有必要。 支撑框架 支撑框架实际上刚度比抗弯矩框架强,在高层建筑中也得到更广泛的应用。这种体系以其结点处铰接或则接的线性水平构件、垂直构件和斜撑构件而具特色,它通常与其他体系共同用于较高的建筑,并且作为一种独立的体系用在低、中高度的建筑中。

施工组织设计外文文献翻译最新译文

文献出处: Phillip Yetton. The Study of Construction Organization Design [J]. International Journal of Project Management, 2015, 9(2): 33-43. 原文 The Study of Construction Organization Design Author: Phillip Yetton Abstract Building construction is a complex work, huge building products, the production cycle is long, is a collection of architectural art, architecture, function, structure, decoration, water supply, power supply, intelligent system for a wind. Need to complete a project unit, type of work well together, and in the process of implementing, also under the influence of various subjective and objective conditions around. In order to meet the quality, cost, time limit for a project, under the premise of safety goal task to complete a project, must according to the requirement of the construction unit and the characteristics of the proposed construction project, the various raw materials on the basis of full investigation, compile an used to guide the whole process of technology, economy and management of project construction comprehensive document, this document is the construction organization Keywords: Construction; Organization design; Project cost 1 Introduction Construction organization design is a construction project for the object establishment, to guide the project bidding, construction contracts, construction preparation, construction installation until the whole process of the final acceptance of the technology, economy and management comprehensive document, is to ensure that project smooth implementation effective programmatic document. Construction organization design is proper or not, will directly relate to the quality of the proposed construction project, cost, time limit, safety, etc. The smooth realization of the intended target. With the development of The Times, modern engineering project scale and the demand is higher and higher, project management has become increasingly complex, and the construction organization design also put forward higher requirements. The construction organization design, construction organization

工程管理专业研究建设项目的工程造价大学毕业论文外文文献翻译及原文

毕业设计(论文) 外文文献翻译 文献、资料中文题目:研究建设项目的工程造价 文献、资料英文题目: 文献、资料来源: 文献、资料发表(出版)日期: 院(部): 专业:工程管理 班级: 姓名: 学号: 指导教师: 翻译日期: 2017.02.14

科技文献翻译 题目:研究建设项目的工程造价 研究建设项目的工程造价 摘要 在工程建设中,中国是拥有世界最大投资金额和具有最多建设项目的国家。它是一 项在建设项目管理上可以为广泛的工程管理人员进行有效的工程造价管理,并合理 确定和保证施工质量和工期的条件控制施工成本的重要课题。 在失去了中国建筑的投资和技术经济工程,分离的控制现状的基础上,通过建设成 本控制的基本理论为指导,探讨控制方法和施工成本的应用,阐述了存在的问题在 施工成本控制和对决心和施工成本的控制这些问题的影响,提出了建设成本控制应 体现在施工前期,整个施工过程中的成本控制,然后介绍了一些程序和应用价值工 程造价的方法在控制建设项目的所有阶段。 关键词:建设成本,成本控制,项目 1.研究的意义 在中国,现有的工程造价管理体系是20世纪50年代制定的,并在1980s.Traditional 施工成本管理方法改进是根据国家统一的配额,从原苏联引进的一种方法。它的特 点是建设成本的计划经济的管理方法,这决定了它无法适应当前市场经济的要求。 在中国传统建筑成本管理方法主要包括两个方面,即建设成本和施工成本控制方法 的测定方法。工程造价的确定传统的主要做法生搬硬套国家或地方统一的配额数量 来确定一个建设项目的成本。虽然这种方法已经历了20多年的改革,到现在为止,计划经济管理模式的影响仍然有已经存在在许多地区。我们传统的工程造价控制的

土木工程外文翻译参考3篇

学校 毕业设计(论文)附件 外文文献翻译 学号: xxxxx 姓名: xxx 所在系别: xxxxx 专业班级: xxx 指导教师: xxxx 原文标题: Building construction concrete crack of prevention and processing 2012年月日 .

建筑施工混凝土裂缝的预防与处理1 摘要 混凝土的裂缝问题是一个普遍存在而又难于解决的工程实际问题,本文对混凝土工程中常见的一些裂缝问题进行了探讨分析,并针对具体情况提出了一些预防、处理措施。 关键词:混凝土裂缝预防处理 前言 混凝土是一种由砂石骨料、水泥、水及其他外加材料混合而形成的非均质脆性材料。由于混凝土施工和本身变形、约束等一系列问题,硬化成型的混凝土中存在着众多的微孔隙、气穴和微裂缝,正是由于这些初始缺陷的存在才使混凝土呈现出一些非均质的特性。微裂缝通常是一种无害裂缝,对混凝土的承重、防渗及其他一些使用功能不产生危害。但是在混凝土受到荷载、温差等作用之后,微裂缝就会不断的扩展和连通,最终形成我们肉眼可见的宏观裂缝,也就是混凝土工程中常说的裂缝。 混凝土建筑和构件通常都是带缝工作的,由于裂缝的存在和发展通常会使内部的钢筋等材料产生腐蚀,降低钢筋混凝土材料的承载能力、耐久性及抗渗能力,影响建筑物的外观、使用寿命,严重者将会威胁到人们的生命和财产安全。很多工程的失事都是由于裂缝的不稳定发展所致。近代科学研究和大量的混凝土工程实践证明,在混凝土工程中裂缝问题是不可避免的,在一定的范围内也是可以接受的,只是要采取有效的措施将其危害程度控制在一定的范围之内。钢筋混凝土规范也明确规定:有些结构在所处的不同条件下,允许存在一定宽度的裂缝。但在施工中应尽量采取有效措施控制裂缝产生,使结构尽可能不出现裂缝或尽量减少裂缝的数量和宽度,尤其要尽量避免有害裂缝的出现,从而确保工程质量。 混凝土裂缝产生的原因很多,有变形引起的裂缝:如温度变化、收缩、膨胀、不均匀沉陷等原因引起的裂缝;有外载作用引起的裂缝;有养护环境不当和化学作用引起的裂缝等等。在实际工程中要区别对待,根据实际情况解决问题。 混凝土工程中常见裂缝及预防: 1.干缩裂缝及预防 干缩裂缝多出现在混凝土养护结束后的一段时间或是混凝土浇筑完毕后的一周左右。水泥浆中水分的蒸发会产生干缩,且这种收缩是不可逆的。干缩裂缝的产生主要是由于混凝土内外水分蒸发程度不同而导致变形不同的结果:混凝土受外部条件的影响,表面水分损失过快,变形较大,内部湿度变化较小变形较小,较大的表面干缩变形受到混凝土内部约束,产生较大拉应力而产生裂缝。相对湿度越低,水泥浆体干缩越大,干缩裂缝越易产 1原文出处及作者:《加拿大土木工程学报》

施工组织设计中英文对照外文翻译文献

施工组织设计中英文对照外文翻译文献(文档含英文原文和中文翻译)

施工组织设计的重要性 摘要: 建筑工程在施工过程中,施工组织方案的优劣不仅直接影响工程的质量,对工期及施工过程中的人员安全也有重要影响。施工组织是项目建设和指导工程施工的重要技术经济文件。能调节施工中人员、机器、原料、环境、工艺、设备、土建、安装、管理、生产等矛盾,要对施工组织设计进行监督和控制,才能科学合理的保证工程项目高质量、低成本、少耗能的完成。 关键词: 项目管理施工组织方案重要性 施工组织设计就是对工程建设项目整个施工过程的构思设想和具体安排,是施工组织管理工作的核心和灵魂。其目的是使工程速度快、质量好、效益高。使整个工程在施工中获得相对的最优效果。 1.编制施工组织设计重要性的原因 建筑工程及其施工具有固定性与流动性、多样性与单件性、形体庞大与施工周期长这三对特点。所以,每一建筑工程的施工都必须进行施工组织设计。这是因为:其它一般工业产品的生产都有着自己固定的、长期适用的工厂。而建筑施工具有流动性的特点,不可能建立这样的工厂,只能是当每一个建筑工程施工时,建立一个相应的、临时性的,如同工厂作用性质的施工现场准备,即工地。施工单件性特点与施工流动性特点,决定了每一建筑工程施工都要选择相应的机具和劳动力组织。选择施工方法、拟定施工技术方案及其劳动力组织和机具配置,统称为施工作业能力配置。施工周期的特点,决定了各种劳动力、机具和众多材料物资技术的供应时间也比较长,这就产生了与施工总进度计划相适应的物资技术的施工组织设计内容。由此可见,施工组织设计在项目管理中是相当重要的。 2.施工组织设计方案的重要性 建筑产品作为一种商品,在项目管理中工程质量在整个施工过程中起着极其重要的作用。工程建设项目的施工组织设计与其工程造价有着密切的关系。施工组织设计基本的内容有:工程概况和施工条件的分析、施工方案、施工工艺、施工进度计划、施工总平面图。还有经济分析和施工准备工作计划。其中,施工方案及施工工艺的确定更为重要,如:施工机械的选择、水平运输方法的选择、土方的施工方法及主体结构的施工方法和施工工艺的选择等等,均直接影响着工程预算价格的变化。在保证工程质量和满足业主使用要求及工期要求的前提下,优化施工方案及施工工艺是控制投资和降低工程项目造价的重要措施和手段。

工程管理专业建筑项目招投标Building-engineering-bidding毕业论文外文文献翻译及原文

毕业设计(论文)外文文献翻译 文献、资料中文题目:建筑项目招投标 文献、资料英文题目:Building engineering bidding 文献、资料来源: 文献、资料发表(出版)日期: 院(部): 专业:工程管理 班级: 姓名: 学号: 指导教师: 翻译日期: 2017.02.14

本科毕业设计外文翻译 Building engineering bidding Yang Cao a,*, Shuhua Wang b, Heng Li a aDepartment of Building and Real Estate, Hong Kong Polytechnic University, Hong Kong, China bState Key Laboratory of Novel Software Technology, Nanjing University, Nanjing 210093, China Abstract Nowadays in the engineering construction industry, the market which is characteristic for project bidding, has formed. The construction companies,which want to create good benefits, have to control their cost and improve management to enhance the capacity of adapting and competing in this market. This article focuses on how to decrease cost and increase income so as to control the construction cost effectively. bidding documents should be well formulated ,which is the improtment to a successful bidding and direct influence the success or failure of the bidding work.Becasue the success or failure of the bidding for the survival and development of enterprise has a direct impact, so we have a high quality, improve the bid documents of the unit, prevent invalid and successful pass mark appear, become a research topic. [key] : bidding drawbacks of unfair competition countermeasures Bidding is a form of project transactions, project bidding process is to determine the successful bidder and the cost of the process and the price of the project, project bidding work of a very important link, do a good job bidding to determine the price, we can effectively control construction costs, and create a fair and equitable market environment, create orderly competition mechanism. Bidding in construction activities, construction enterprises in order to tender invincible works to be successful, And from the contracted projects profitable, it needs to integrate various subjective and objective conditions, the tender research strategy determine tender. Tender

土木工程岩土类毕业设计外文翻译

姓名: 学号: 10447425 X X 大学 毕业设计(论文)外文翻译 (2014届) 外文题目Developments in excavation bracing systems 译文题目开挖工程支撑体系的发展 外文出处Tunnelling and Underground Space Technology 31 (2012) 107–116 学生XXX 学院XXXX 专业班级XXXXX 校内指导教师XXX 专业技术职务XXXXX 校外指导老师专业技术职务 二○一三年十二月

开挖工程支撑体系的发展 1.引言 几乎所有土木工程建设项目(如建筑物,道路,隧道,桥梁,污水处理厂,管道,下水道)都涉及泥土挖掘的一些工程量。往往由于由相邻的结构,特性线,或使用权空间的限制,必须要一个土地固定系统,以允许土壤被挖掘到所需的深度。历史上,许多挖掘支撑系统已经开发出来。其中,现在比较常见的几种方法是:板桩,钻孔桩墙,泥浆墙。 土地固定系统的选择是由技术性能要求和施工可行性(例如手段,方法)决定的,包括执行的可靠性,而成本考虑了这些之后,其他问题也得到解决。通常环境后果(用于处理废泥浆和钻井液如监管要求)也非常被关注(邱阳、1998)。 土地固定系统通常是建设项目的较大的一个组成部分。如果不能按时完成项目,将极大地影响总成本。通常首先建造支撑,在许多情况下,临时支撑系统是用于支持在挖掘以允许进行不断施工,直到永久系统被构造。临时系统可以被去除或留在原处。 打桩时,因撞击或振动它们可能会被赶入到位。在一般情况下,振动是最昂贵的方法,但只适合于松散颗粒材料,土壤中具有较高电阻(例如,通过鹅卵石)的不能使用。采用打入桩系统通常是中间的成本和适合于软沉积物(包括粘性和非粘性),只要该矿床是免费的鹅卵石或更大的岩石。 通常,垂直元素(例如桩)的前安装挖掘工程和水平元件(如内部支撑或绑回)被安装为挖掘工程的进行下去,从而限制了跨距长度,以便减少在垂直开发弯矩元素。在填充情况下,桩可先设置,从在斜坡的底部其嵌入悬挑起来,安装作为填充进步水平元素(如搭背或土钉)。如果滞后是用来保持垂直元素之间的土壤中,它被安装为挖掘工程的进行下去,或之前以填补位置。 吉尔- 马丁等人(2010)提供了一个数值计算程序,以获取圆形桩承受轴向载荷和统一标志(如悬臂桩)的单轴弯矩的最佳纵筋。他们开发的两种优化流程:用一个或两个直径为纵向钢筋。优化增强模式允许大量减少的设计要求钢筋的用量,这些减少纵向钢筋可达到50%相对传统的,均匀分布的加固方案。 加固桩集中纵向钢筋最佳的位置在受拉区。除了节约钢筋,所述非对称加强钢筋图案提高抗弯刚度,通过增加转动惯量的转化部分的时刻。这种增加的刚性可能会在一段时间内增加的变形与蠕变相关的费用。评估相对于传统的非对称加强桩的优点,对称,钢筋桩被服务的条件下全面测试来完成的,这种试验是为了验证结构的可行性和取得的变形的原位测量。 基于现场试验中,用于优化的加强图案的优点浇铸钻出孔(CIDH)在巴塞罗那的