方舱电磁屏蔽处理工艺

方舱电磁屏蔽处理工艺
方舱电磁屏蔽处理工艺

方舱电磁屏蔽处理工艺

摘要本文就方舱电磁屏蔽处理方面有关舱体拼装、门安装、屏蔽固定窗、壁盒(通风壁盒、电源或信号壁盒)安装、空调安装、暖风机安装、过舱导体等方面施工方法、工艺参数及工艺质量要求进行了说明;并归纳了一般屏蔽方舱的“屏蔽处理工序及检验流程图”。

关键词屏蔽方舱屏蔽材料缝隙处理质量检验

一前言

电磁屏蔽方舱是一种用来有效屏蔽电磁干扰和电磁脉冲的方舱,确保舱内作战功能设备不被电磁干扰和破坏,破坏使其发挥正常的作战功能;当然也能屏蔽舱内电子电气设备发出的电磁信号,使敌方的电磁信号探测装置无法侦察和探测己方的军用设备及其位置。方舱电磁屏蔽处理的根本目的是确保屏蔽方舱的电气连续性,主要着手点是缝隙处理,包括组舱缝隙、门(窗、壁盒)等孔口与舱壁间的缝隙及贯穿舱体导体等。

二设备、工具及辅助材料

CO2气体保护焊机氩弧焊机压缩空气电钻或风钻手提磨光机拉铆枪钻头毫欧表小板刷毛笔

导电保护液(胶)0#砂布180#砂纸丙酮白细纱手套

三施工工艺

1舱体拼装

在舱体拼装时,在其角部用弯角件将组成舱体的板片进行焊装(见图1)。钢骨架进行CO2气体保护焊,铝骨架进行氩弧焊(TIG 或MIG)。焊接前应去除板片方管和弯角件上的油污、氧化膜。为保证舱体的电气连续性,焊接应尽量采用连续焊。如采用断续焊,当连接面长度L≤50时用连续焊;当连接面长度大于50小于300时用断续焊,焊缝长度应≥50,焊缝间距≤200,且两端必须焊接;当连接面长度大于300断续焊时,焊缝长度≥50,焊缝间距≤300,且两端必须焊接。对材料厚度小于6mm的构件,应采用完全穿透焊接。

当舱体的电磁屏蔽效能SE≥40db时,舱体各片壁板外蒙板之间需用整条铝板条、角顶处(三片壁板交汇处)用铝罩(专用件)进行连焊。焊前应清除铝板条、铝罩及外蒙板上的油污、氧化膜,且使铝板条、铝罩与外蒙板接触处平整,有良好的导电接触面及焊接工艺性。焊接应采用连续焊,焊后应对焊缝进行修整及清理,且在所有焊缝处粘贴屏蔽胶带(铜箔)进行电磁密封(见图1、图2)。

如果舱体角部处需布暗线,应将线缆布设整齐、扎制、固定;应将导线用隔热材料进行包裹,以防焊接电连接板时烧伤导线(见图3)。

舱体内壁角接处(包括隔道壁与顶、底、侧相连处),用角型铝压条连接。连接前需将内蒙板及铝压条间相接触处的油污、油漆和氧

化膜去除;清理后立即涂敷铝及铝合金导电保护液;在衬垫导电衬垫(如定向金属丝等)或粘贴屏蔽胶带后,用螺钉或铆钉将压条进行固定(见图1、图4)。衬垫材料要平整、平直,不允许露出压条外。

油污、氧化层等的去除方法为:先用手提磨光机轻轻打磨需清理的表面,再用0#砂布或180#砂纸砂磨至光亮,最后用丙酮擦洗干净。 电连接铝板定向金属丝或屏蔽胶带

内包角铝压条

外包角

弯角件屏蔽胶带

(铜箔)

图1 舱体内外角部屏蔽处理

电连接铝板

屏蔽胶带(铜箔)

铝 罩

图2 舱体角顶处屏蔽处理

图3 暗线保护

图4 隔道壁屏蔽处理

2门安装

将门框装入舱壁门孔内,调整其左、右、上、下间隙均匀后,根据门框上预制孔配钻舱壁铆钉孔;去除门框与舱壁外蒙板间接触面处的油污、氧化膜后涂敷铝及铝合金导电保护液;在门框内沿四周安装导电衬垫(如定向金属丝等)及外沿四周涂AM-130聚氨酯密封胶后,将其与舱体铆装;从舱内向外用防波套填充门框四周与舱体门孔间的缝隙后,粘贴屏蔽胶带(铜箔)并用压条或弯角件固定压紧(见图5)。

门框装配后,测量门框与舱壁内外蒙板间的电阻,应符合R≤2.5mΩ。

图5 门安装屏蔽处理

门与门框配装时也应做到上下左右间隙均匀,开关灵活,铰链处用金属软编织防波套进行电连接。门与门框间水汽密封用橡胶密封条,电磁密封用双层金属橡胶芯屏蔽条或四层丝网镀锡磷青铜等衬垫

材料。凡门框、门安装屏蔽条处,都需去除油污、氧化膜,并涂敷铝及铝合金导电保护液后及时安装屏蔽条。屏蔽条接头处(只允许有一处且在门或门框的下沿)应贴紧,其屏蔽网重叠长度应大于15mm。门与门框安装屏蔽条后应保证,门关闭时其互相的止口都应与对方的屏蔽条压紧,如发现不紧,应在屏蔽条下垫导电法兰等衬垫材料。

门安装后关闭,测量门与舱体内外蒙板之间的电阻,应符合R≤2.5mΩ。

3屏蔽固定窗安装

应在空气比较干燥清洁的环境中,进行屏蔽固定窗装配作业。用丙酮清除窗框与屏蔽玻璃接触处的油污、杂物,将屏蔽玻璃四周予留的夹层屏蔽网向内合上窗框的止口(见图6),用小板刷或毛笔刷导电胶使屏蔽网裙边与窗框止口粘接牢固,导电胶涂抹应均匀、连续、不间断,使夹层屏蔽网与窗止口具有良好的电气连接。

去除窗框与舱壁外蒙板间接触处的油污、氧化膜后涂敷铝及铝合金导电保护液;在窗框内沿四周安装屏蔽衬垫及外沿四周涂AM-130聚氨酯密封胶后,将屏蔽固定窗与舱体铆装(见图6)。

图6 屏蔽固定窗安装

4通风壁盒安装

将壁盒框装入孔口内,调整其左、右、上、下间隙均匀后,根据壁盒框预制孔在舱壁上配钻孔;清除壁盒框与舱壁外蒙板间接触处的油污、氧化膜后涂敷铝及铝合金导电保护液、粘贴定向金属丝衬垫(定向金属丝安装时宽度不超过铆钉孔);在壁盒框外沿四周涂AM-130聚氨酯密封胶后与舱体铆装(见图7),铆钉间距L≤30mm。

在壁盒框止口处,用丙酮清洗止口处的油污、杂质后涂敷铝及铝合金导电保护液;将蜂窝板导电衬垫裙边与壁盒止口贴紧后,采用焊接或螺钉固定(见图7)。蜂窝板采用焊接固定时应采用分段焊接,待前一段焊缝冷却后再焊下一段;蜂窝板采用螺钉固定时,螺钉间距L≤50mm,应对称、分步、逐渐拧紧螺钉。

图6 通风孔口屏蔽处理

5电源(信号)壁盒安装

电源(信号)壁盒框安装工艺同通风壁盒框。

装置板装配插座(接线柱)前,应将装置板与插座相接触表面油漆、油污、氧化膜去除,涂敷铝及铝合金导电保护液后用螺钉紧固插座(接线柱)等。

装置板安装前,将与装置板贴合的壁盒框止口处的油污、油漆、氧化膜去除并涂敷铝及铝合金导电保护液;在加装导电衬垫后,用螺钉以间距L≤50mm固定装置板。

壁盒内罩安装前,去除内罩与舱体接触范围内的波音软片或油漆、氧化膜并涂敷铝及铝合金导电保护液,在舱体与金属罩之间衬垫导电衬垫后用螺钉以间距L≤30mm进行固定。

滤波器与壁盒内罩安装前,应去除其接触表面处的油漆、油污、

氧化膜,在两者间垫两层100目以上的铜网(铜网周边与罩采用锡焊连续焊连接);滤波器输出端用螺母从舱内压紧并进行连续焊接(见图8);滤波器两端的电源输入、输出线均应采用屏蔽线并确保可靠接地;输出端的电源线在舱内布设在金属走线槽内。

图8 电源孔口屏蔽处理

6空调安装

6.1分体式空调安装

所有穿越舱壁的电源线、控制线都应按图9进行处理。去除法兰与舱壁外蒙板间接触处的油污、氧化膜后涂敷铝及铝合金导电保护液;在法兰内沿四周安装导电衬垫及外沿四周涂AM-130聚氨酯密封胶后,将法兰与舱体铆装;去除法兰与防波套接触面处的油污、杂质后,将防波套与法兰装配并涂敷导电密封胶后,用卡箍将其固定。

排水管穿越舱壁时应加装排水接头。排水接头的安装法兰与舱壁

接触面(经清理)应涂导电胶或安装导电衬垫,铆钉应密集、均布。

连接空调内外机的冷凝管、回路管通过连接管穿越舱壁。连接管的安装法兰与舱壁接触面(经清理)应涂导电胶或安装导电衬垫,铆钉应密集、均布。

图9 空调电源或信号线过舱处理

6.2整体式空调安装

去除外蒙板与蜂窝板接触面处的油污、氧化物膜并涂敷铝及铝合金导电保护液;在衬垫导电衬垫(如定向金属丝)后,将蜂窝板与外蒙板进行铆装(见图10)。导电衬垫安装时其宽度不超过螺钉孔,螺钉间距L≤30mm。

所有穿越舱壁的电源线、控制线都应按6.1进行处理。

图10 整体空调进、出风孔口屏蔽处理

7暖风机安装

在进行暖风机安装时,其进、出风口的屏蔽处理同于整体空调安装的进、出风口(见图11),按6.2进行处理。所有穿越舱壁的电源线、控制线都应按6.1进行处理。

图11 暖风机安装

四工序质量检验

屏蔽方舱在舱体拼装、孔口(门、窗、壁盒)处理及设备安装过程中,设置三个工序质量停止点(详见附件1:《方舱屏蔽处理工序及检验流程图》中检验1~检验3),予以控制有关屏蔽技术措施落实及工艺处理质量。

1检验1——舱体拼装

1.1蒙板与电连接铝板、铝罩焊接前应去除油污、氧化膜等,采用点固定位焊、分段焊、跳焊等方法进行连续焊并焊后修整。焊缝应连续、均匀,无漏焊、虚焊、沙眼等缺陷。

1.2所有电连接焊缝处都要粘贴屏蔽胶带;屏蔽胶带粘贴应平服、无汽泡。

电磁屏蔽方舱的优化设计研究

电磁屏蔽方舱的优化设计研究 发表时间:2019-02-22T11:00:28.110Z 来源:《防护工程》2018年第32期作者:张利军成丁雨宋甲宁牛海峰王晋会 [导读] 电磁屏蔽方舱不管从设计方面还是工艺方面都是一项实践性非常强的工程技术,但是容易在施工的过程中影响系统的整体屏蔽效能。 山西中电科技特种装备有限公司山西太原 030032 摘要:电磁屏蔽方舱具有良好的防护性能与封闭性能,是一种各方面性能都较好的电磁保护载体,被广泛应用于武器系统、指挥中心以及医疗保护体系中。要想提升战斗力,需要保证方舱良好的电磁屏蔽性能。对电磁屏蔽方舱的基本原理进行研究,对电磁屏蔽方舱的生产流程进行了分析,对提高动态范围的方法进行总结,以提高系统的准确性。 关键词:电磁屏蔽方舱;屏蔽效能;优化设计 自海湾战争、阿富汗战争以来,在高技术的条件下,现代战争中的发展趋势逐渐凸显。在信息化发展如此迅速的年代,战争电磁环境变得越来越复杂,如果不能采取有效的措施,将会导致战场指挥紊乱,影响装备性能,从而造成战争的失败。电子设备需要在电磁环境中得以工作,当电磁辐射超过一定的设定时,电子设备将会失去它的功能。在战争环境中,各种电子设备都处于十分恶劣的环境中,屏蔽条件容易遭到破坏,目前的电子设备防护容易受到攻击。电磁屏蔽在现代战争中有着非常重要的意义,一旦受到电磁干扰,将会造成通讯终端、武器失灵,战争将会以失败告终。因此,提高方舱的电磁屏蔽性能非常有必要。 1.方舱电磁屏蔽的原理 利用金属屏蔽体对外部产生的辐射进行屏蔽,还可以使用相同的屏蔽量对内部产生的电磁泄露进行屏蔽。不管是简单的配置还是复杂的配置,发生电磁干扰需要有干扰源、途径与设备。传导耦合与辐射耦合作为两种重要的传播方式,在进行方舱设计时,以控制辐射传播为主。电磁屏蔽的静电屏蔽,用于防止静电场带来的影响;非静电屏蔽是为了防止电磁场带来的影响。方舱舱体的电磁屏蔽则是采用的非静电屏蔽[1],用于防止发生交变电场。对方舱进行电场屏蔽设计时,要注意选材、舱体接地是否良好、较少屏蔽体的开孔数量。磁场屏蔽分为低频与高频之分,低频主要是利用高导磁材料,构成一种低磁阻,沿屏蔽体通过,屏蔽体的材料越厚说明屏蔽性能越好;高屏蔽是利用涡流作用进行外部的电磁屏蔽,当交变电磁场被金属材料的孔洞包围时,金属材料就会形成一种涡流作用,产生的磁场将会与原有磁场相反,从而将部分的磁场进行消除,通过这样的方式达到电磁屏蔽的效果。 2.对电磁屏蔽方舱的屏蔽效能进行优化设计 电磁屏蔽方舱与普通的方舱区别在于技术要求不同,在组装的过程中要考虑到舱体中每一个组成部分的电气连续性,从而满足屏蔽效能的指标。因此在进行电磁屏蔽方舱设计时,从零部件开始,每一道工序都是严格按照工艺流程进行,零部件的加工质量决定了方舱电磁屏蔽效能的好坏。如果零部件在制造的过程中出现失误,将直接影响到方舱的屏蔽效能,影响屏蔽的等级[2]。 2.1机柜优化 随着信息化的不断推进,电磁屏蔽方舱内部的空间越来越紧张,现有的舱内空间已经无法满足电磁屏蔽效能的相关测试标准,需要对方舱的内部进行优化设计。对整个方舱的内部进行电磁屏蔽效能的测试时在有一定的限制情况下,要保证相应的标准。利用电磁场的相关知识进行推断,机柜的反射条件会影响舱内的接收信号,这会影响屏蔽效能的效果。电子方舱具有电磁屏蔽的功能,结构完全封闭,为了解决设备的散热问题,需要采用大功率的制冷空调进行降温,直接向舱内送冷风。在方舱的内部设置了三个机柜,空调回风孔口设置在方灿高的高端,另外两个是高功放机柜。单个高功放的机柜上安装了六个发射机,发射方舱中安装了两台制冷空调,方舱的顶端设置了制冷风道。高功放机柜从上到下分布了六个发射机单元,发射机的热量需要通过轴流风机排到高功放机柜的后面,从整体的制冷量和发热量进行分析,空调制冷完全可以满足散热要求。 对方舱整体进行优化,设备在自然条件写需要通过环境测试和验收,在使用的过程中,如果太阳直射将会使方舱的内部温度升高,将方舱移到有遮挡条件的环境下,方舱的温度可以保持正常。虽然使用大功率的空调进行降温可以为方舱中注入冷空气,但是从热设计理论进行分析,设备需要有合理的风道设计进行降温。对于方舱整体的风道设计是具有优化空间的,方舱高的制冷空调可以设置在前端,高功放机柜的热量会通过发射机排到柜体的后面,不利于风道的设置。基于此,可以通过三个方面优化设计,改善方舱的散热:(1)增加壁板的厚度;(2)优化方舱的布局;(3)增加隔离板,优化散热风道。优化设计后,方舱内机柜的环境温度得到了有效的改善,为方舱内提供了良好的环境。 2.2屏蔽舱门的优化设计 舱门作为方舱舱体电磁泄露的主要途径,舱门的性能高低对整个舱体的屏蔽效能非常重要,在设计的过程中要充分考虑影响舱门屏蔽效能的因素。屏蔽舱门的材料选择要格外注意,尽量选择良导体,比如铜、铝;屏蔽方舱的舱体需要有较好的接地性;考虑到制作工艺和使用成本,选择高磁导率的钢,铜和铝需要有较高的电导率,这样才可以实现较好的屏蔽功能。针对舱门的位置需要有较高的电磁屏蔽功能,可以采用涂覆的方式增加屏蔽效能。采用双刀指簧屏蔽门,门刀和门框要采用钢板,将其拼焊成型,再进行镀铜处理;屏蔽舱门缝隙也要格外注意,簧片是舱门设计优化中一个重要的要素,簧片的材料表面要有足够的硬度,压缩量以及门体的连接方式都会给舱门的屏蔽效能带来较大的影响。可以采用铍青铜簧片实现弹性变化,簧片与其他的金属构件有一定的接触压力,可以实现高弹性的性能,从而消除门框和门之间的缝隙,达到良好的接触性能,从而实现高性能的电磁屏蔽效能。 2.3方舱孔口优化设计 方舱孔口是方舱与外界进行数据交换的重要通道,是导致电子屏蔽效能出现泄露的薄弱环节,对方舱孔口进行优化设计是保证孔口电磁屏蔽效能的关键。孔口框架与转接板的加工质量决定了方舱孔口的电气连续性,强化孔口框架和转接板的质量可以保证方舱孔口的电磁屏蔽效能不受破坏。对孔口进行装配的过程中要注意电气的连续性,孔口的框架与方舱的蒙皮在进行铆接之前,要清理铆接面,并安装弹性导电,导电衬垫要具有良好的电接触功能,导电衬垫的压缩量要进行合理控制,以保证较好的屏蔽效果。 结束语 电磁屏蔽方舱不管从设计方面还是工艺方面都是一项实践性非常强的工程技术,但是容易在施工的过程中影响系统的整体屏蔽效能。

方舱医院系统中的电磁兼容设计

方舱医院系统中的电磁兼容设计 Design of Electromagnetic Compatibility in the Shelter Hospital System 黄鹏,刘志国,祁建城 (军事医学科学院卫生装备研究所,天津,300161) 摘要:目的:对方舱医院系统进行了一系列的电磁兼容设计,用于对抗未来复杂电磁环境下的电磁干扰问题。方法:采取系统布局分开放置干扰源与敏感设备,设置屏蔽空间隔离不同设备,利用良好接地保护敏感设备,使用滤波技术去除骚扰信号等措施,为方舱医院系统的电磁兼容提出了设计思想和解决方法。结果:通过电磁兼容仿真和试验检测,该方舱医院系统基本消除了由电磁干扰所引起各分系统或设备的故障及不容许的响应,达到了系统的电磁兼容。结论:该方舱医院系统的电磁兼容设计方案,可满足野战条件下应急医疗救治机构电磁安全防护的需要。 关键词:方舱医院, 电磁兼容, 电磁干扰, 系统布局, 屏蔽 Abstract:Objective: On the shelter hospital system conducted a series of electromagnetic compatibility (EMC) design, used against the electromagnetic interference (EMI) under complicated electromagnetic environment problem in the future. Methods: For the shelter hospital system of EMC design ideas and solutions methods are put forward, such as take the system layout placed separate sources of interference and sensitive equipment, set up the shield spatial segregation of different devices, apply a good grounding to protect sensitive equipment, use filtering techniques to remove the disturbance signal and other measures. Results: Through the EMC simulation and experimental testing, the impermissible response and faults of each system or equipment caused by the electromagnetism interference are eliminated,to achieve the EMC of the system. Conclusion: The application of shelter hospital system EMC design, can satisfy the electromagnetic field under the condition of emergency medical treatment institution security needs. Key words:shelter hospital, EMC, EMI, system layout, shield 1 引言 未来信息化战争,将是一场争夺电磁空间的战争,能否取得制电磁权将成为战争胜负的关键。由于电子信息设备的使用不断加大,战场空间中的电磁信号非常密集,使得战场电磁

移动方舱医院医学设备的保障

41创伤与急诊电子杂志 2018年1月第6卷第1期 J TRAUMA EMERG ,Jan.2018,vol.6,No.1 移动方舱医院医学设备的保障 何武兵1,2,朱晓婧1,林孟波1,许玮1,2,喻海燕1,陈锋1,2(1.福建省立医院?福建 省急救中心,福州?350001;2.福建医科大学省立临床医学院,福州?350001) [关键词]灾害救援;移动方舱医院;设备 DOI:10.16746/https://www.360docs.net/doc/9b5635235.html,ki.11-9332/r.2018.01.009 灾害救援行动的成功与否,很大程度上取决于救援装备的先进性和实用性,救援队一般会配置搜索、营救、医疗、保障四大类专用设备。其中的医疗设备是医学救援装备的核心,代表着医学救援的能力和水平,主要配备轻便、防水、防潮、抗摔打、易于操作、便于维修、适应实战需求的设备[1]。携行医疗设备从2005年前的急救行囊与心肺复苏装备,发展到野战医院、移动帐篷医院、移动车载医院和目前研制的灾害救援专用方舱医院。作为福建省委省政府2015年为民办实事项目之一,福建省紧急医学救援队省立医院队于2015年4月正式立项,目前已经投资完成了8台特种车辆所构成的移动方舱医院系统和紧急医学后勤保障中心。目前移动方舱医院是刚研制建设的,国内外关于移动方舱医院的硬件配置尚无公开标准,如何做好医学装备的保障也无标准的方案,为了更好应对灾难环境下的医学救援,笔者通过文献回顾研究、演练、专家小组讨论等方法,进行总结,报告如下。 1 资料与方法 1.1 一般资料由院领导班子抽取本院临床、护理、行政管理、后勤保障等63人组成救援队,并从中抽取临床、手术室、设备和院感人员20人组成专家组。 1.2 方法通过广泛的文献回顾,灾难医学书籍复习,了解临床医疗设备配置和保障情况,结合本院紧急医学救援经验总结,在移动方舱医院系统基本配置的前提下,补充和完善手术车的硬件装备;梳理临床颅脑、心胸外科、腹部外科(基本外科、肝胆外科、胃肠外科)、泌尿和骨科的常用手术器械,并通过专家小组讨论形式确定手术器械通用基本包、单独工具包、专科专用包的器械基数;通过文献检索和专家小组讨论确定检伤分类区使用的设备清单;通过文献检索和专家小组讨论确定方舱医院的医疗设备保障方案。 2 结果 2.1 移动方舱医院系统手术装备手术车已经装备了多功能手术床1台、高频电刀1台、吸引器1台、清创台1台、麻醉呼吸机1台、监护仪1台、无影灯1台、移动轻便器械台2台、超声器械清洗机1台、高压蒸气灭菌器1台、空气净化系统1台。为了更好满足野外作业的需要,我们增加脉冲手术清创冲洗机1台、石膏车1台、移动简易手术床1台、野外洗手装置1台、自体血回输装置1台和手术器材补给箱2个。 2.2 手术器械清创缝合包20个(3#刀柄1个,弯组织剪1个,持针器1个,弯蚊钳2个,有齿镊1个,弯盘1个,酒杯+针盒3个,卵圆钳1个,大方纱5条,小方纱5条,擦手巾1条,腹布5条)。 换药包10个(无齿镊2个,弯盘1个,无菌碗1个),一次性换药包30个。 导尿包10个(一次性,带F o l l e y s双腔导尿管)。 气管切开包3个(清创缝合基数,甲状腺拉钩2个,小直角拉钩2个)。 静脉切开包2个(清创缝合基数)。 颅脑外科器械包2个(鹰嘴咬骨钳1个,7#刀柄1个,组织钳1个,有齿爱迪生镊1个,组织剪1个,次弯钳4个,无齿爱迪生镊1个,线剪1个,次直钳2个,枪状镊1个,脑膜剪1个,甲状腺拉钩2个,海绵钳1个,手摇钻柄1个,有齿解剖镊1个,手摇钻钻头1个,无齿解剖镊1个,4.5#吸引器头1个,脑棉1包, 灾害救援 基金项目:国家临床重点专科建设项目(闽卫科教[2012]149号)通信作者:陈锋,E-mail:cf9066@https://www.360docs.net/doc/9b5635235.html,

电磁屏蔽机房技术方案知识讲解

电磁屏蔽机房设计方案 一、工程概述 用途:该机房用于无线电设备的检测。 本方案是根据工程招标文件,设计研究确定的屏蔽工程设计方案。 二、设计依据 1.《招标文件》 2.《处理涉密信息的电磁屏蔽室的技术要求和测试方法》BMB3-1999 3. 《电磁屏蔽室屏蔽效能的检测方法》GB12190-2006 4. 《电磁屏蔽室工程施工及验收规范》SJ31470-2002 5. 《电子信息系统机房设计规范》GB 50174-2008 6. 《电子计算机场地通用规范》GB/T-2887-2000 7. 《电子信息系统机房施工和验收规范》GB 50462-2008 8. 《电子计算机机房施工及验收规范》SJ/T30003-93 9. 《计算站场地安全要求》GB 9361-88 10. 《计算机房用活动地板技术条件》GB 6650-86 11.《计算机机房工程设计与施工》人民邮电出版社1997.2 12.《计算机机房配电系统设计要求》ZY1997-99 13.《高层民用建筑设计防火规范》GB 50045-95(2005版) 14.《建筑内部装修设计防火规范》GB 50222-95 15.《室内装饰工程质量规范》QB 1838-93 16.《民用建筑电气设计规范》JGJ/T16-92 17.《低压配电设计规范》GB50054 18.《建筑防雷设计规范》GB50057-94 19.《通风与空调工程施工及验收规范》GB50243-97 20.《供配电系统设计规范》GB50052-92 21.《火灾自动报警系统设计规范》GB50116-98 其他国家、行业相关标准、规范

三、屏蔽室总体结构 本项目工程建设面积为32m2,屏蔽室面积为28 m2.。建造规模为8m(长)x4m(宽)x2.6(高)。屏蔽室安装1樘1500X2000mm屏蔽门。 四、屏蔽工程 1.屏蔽效能指标: 磁场 14kHZ >=63dB 200kHZ >=93dB 平面波 450MHz >=100dB 平面波 1-10GHz >=100dB 屏蔽室为多点接地,接地电阻不大于1欧姆。 2屏蔽工程主要内容: 1).屏蔽工程主要包括屏蔽主体和屏蔽设备。 屏蔽主体包括:屏蔽壳体、屏蔽门、通风截止波导窗。 屏蔽设备包括:电源滤波器、信号滤波器、光电转换设备、空调信号转换设备、空调进出风、光纤截止波导管。 2).系统设计中充分利用金属板材对电磁波的吸收和反射的作 用,并结合滤波、隔离、接地等屏蔽技术,满足屏蔽效能指标要求。屏蔽壳体材料 ①.屏蔽指标的计算: 对屏蔽指标的设计计算如下: 透射R(屏效)=20lg 环境场强屏蔽后场强 ②.屏蔽材料的选择: 当电磁波E垂直穿过金属屏蔽体时,屏蔽体的屏蔽效能与屏蔽体的结构、屏蔽材料的电导率、磁导率、电磁场频率、场源性质和距场源距离等有关,如下图所示:

“方舱医院”-语法填空

一、读时事新闻做语法填空题--------“方舱医院” The (1)________ (construct) of three mobile cabin hospitals in Wuhan, Hubei province has picked up steam on Monday night. The temporary hospitals will be equipped(2)________ beddings, tables and chairs, electric blankets and other essentials. Medical staff will (3)________(dispatch vt.派遣,派出)to the three hospitals to take care of patients (4)_______ test positive for the virus — but show no severe symptoms — as soon as they are completed. (5)_______a patient's symptoms worsen, he or she will be transferred to Jinyintan Hospital, one of the city's designated (6)_______ (hospital) to admit patients infected with the virus. "Putting into operation temporary hospitals with a large number of beds inside a giant space is a major public health measure China has taken," said Wang Chen, a renowned respiratory expert and president of the Chinese Academy of Medical Sciences. "It is a key measure taken by the authorities at a critical time," said Wang. "(7)_______(like) field hospitals during wartime or quake-relief efforts, the makeshift hospitals in Wuhan are unprecedented in China." Wang said the new measure is (8)_______(specifical) designed to address the pressing issue of virus transmission in households and communities. "If (9)_______ large number of patients with mild symptoms live at home or suspected patients roam around in the community, they will become the main source to spread the virus," Wang said. Moreover, (10)_______hospital beds are in short supply, their lives could be in danger if they are not effectively treated, the expert added.

方舱医院的起源

方舱医院的起源 方舱医院源于越战,兴于海湾战争,服务于人民。 在上个世纪60年代的越南战场上,美军营地里出现了一个个巨大的方形铁疙瘩,它们就是美军为了应对越战需要投入的轻便野战医院——MUST。 这是战场上野战卫生装备新的手段,在这些轻便的野战医院里能实现伤员分类、外科处置、紧急手术、急救护理、卫勤指挥、药材供应等功能,野战医院由此开始方舱化。 此后,多国都开始研制方舱医院,并且开发出以越野汽车载运的各类组合单元。除了越战,方舱医院在海湾战争时期又得到了快速发展。 海湾战争牵涉到多个国家,各国都进一步研制、装备和采购了类型各异、规模不同的方舱医院,在战争中,方舱医院又增加了X射线诊断、临床检验、卫生器材灭菌、远程会诊等新的功能模块,为伤员救治提供了可靠的保障。 战争结束后,方舱医院以其良好的应用性继续成为发展热点,使用范围和面积进一步扩大,方舱医院不再局限于军用,它开始更多应用于非军事行动的保障任务。 我军的方舱医院,在上世纪90年代初就已开始建设。目前为止,所有战区都装备了野战方舱医院,并且技术处于国际先进行列。 所谓“方舱医院”,简单地说是一个可以活动的“房子”,其特点就是组装快、功能全、机动性强,由其构成的野战机动方舱医院功能不可小觑。 方舱医院与野战机动医院类似,通俗地说由活动的“房子”建成,在野战条件下以医疗方舱、技术保障方舱、病房单元、生活保障单元及运力等为主要组成,依托成套的装备保障完成伤员救治等任务,在我国抗震救灾等公共卫生应急保障中发挥巨大作用。 方舱医院内不仅具备流动水手卫生设施、药品及无菌物品存储、器械消毒灭菌、持续的电源供应等条件,还可开展急救、手术,进行

野战方舱医院中心治疗室布局

野战方舱医院中心治疗室布局 发表时间:2010-11-02T11:38:35.247Z 来源:《中外健康文摘》2010年第29期供稿作者:郭利郑红莉[导读] 护士在此给病人安排床位,测量基本生命体征。郭利郑红莉(北京军区第255医院河北唐山 063000)【中图分类号】R197.38 【文献标识码】A 【文章编号】1672-5085 (2010)29-0326-02 【摘要】野战方舱医院在两次抗震救灾中发挥了重大的作用,而野战中心治疗室是我北京军区野战方舱医院首创,为适应野战条件下救治大批量伤员而设,经过抗震救灾的实践发现存在一定的不足,本文从野战中心治疗室的布局及应用,探讨了其优点及不足,并对下一步的改进措施提出一些前瞻性观点。 【关键词】野战医院中心治疗室布局改进 野战中心治疗室是我野战方舱医院首创,为适应野战条件下救治大批量伤员而设。在2008年赴四川绵竹和2010年赴玉树抗震救灾中,经过300多天的实践,发挥了重大的作用,在极短的时间内,保证了大批量伤员安全有序的治疗工作,现将此野战治疗室的布局简单介绍如下: 1 野战中心治疗室布局图及说明 。野战中心治疗室设在网架式帐篷内,由于野战条件下地理环境及帐篷短缺等条件的限制,此中心治疗室一室多用,在充当正常医院治疗室的同时,也同时担负着医生办公室、护理站二室的作用。现对内置布局分述如下: 1.1 治疗台中心治疗室的治疗台是野战专用治疗台,长约4米,可以同时满足100多位病人的配液工作。2008年绵竹灾区受灾较严重,医疗系统基本瘫痪。自我院到绵竹后,大批量伤病员涌入,本中心治疗室快速展开工作,基本满足了大批量伤员的收容、治疗工作。治疗台的作用是摆放病人的输液液体,由专人对液体进行配制,每日配液量平均70人次,280瓶次。此次赴玉树救灾同样发挥了重要作用。 1.2 工作台由专用野战运输箱及专用野战台面搭成,可以满足医生及护士的医疗文书书写需求。 1.3 病历车存放所有在野战医院住院病人的病历,上面可放置野战医院病人一览表,方便查找病人。 1.4 野战运血箱可以存放必需冷藏保存的药品。 1.5 接诊台负责接诊新入院伤病员及医院病员办理住院手续。护士在此给病人安排床位,测量基本生命体征。 2 优缺点 2.1优点 2.1.1 集中治疗、集中配药、专人负责、便于查对,防止发生医疗差错。 2.1.2 节省人力此中心治疗室只配备2人,治疗班护士1人,专门负责所有病人液体的配制,一次性物品的清领及存品的清领及治疗室的清洁、卫生、消毒工作。办公班护士1人,负责所有医嘱的处理、画体温单及病历的整理、归档、病人的日报、出入院登统计工作。 2.1.3 一室多用,节省空间此治疗室兼医生办公室及护士站的功能。 2.1.4由于工作集中,因此便于管理,便于沟通,资料程序化、有条不紊。 2.2 存在问题 2.2.1 一室多用在有利的情况下也有一些弊端,易造成空气环境的污染,与治疗室的无菌要求不符。 2.2.2 治疗区及办公区分区不明确。 2.2.3 缺乏自动化工作设备。 3 改进措施 经过两次抗震救灾实践,中心治疗室发挥了重大的作用,使流程科学化、快捷化、有序化,但存在一定不足,针对两次实践中发现的问题,可在以后的工作中做如下改进: 3.1布局重新安排,治疗区和办公区相对分开如下图。。

屏蔽机房系统设计方案

军用屏蔽机房系统设计方案 第一章工程概述 1、工程概述 随着信息技术的发展,互联网已经成为人们日常生活中必不可少的一部分,越来越多的人利用网络进行沟通、工作甚至购物。对于网络中的信息,其安全性和保密性显得尤为重要。 计算机及其外围设备在进行信息处理时会产生电磁泄漏,即电磁辐射。现有的一些探测设备,能在一公里以外收集计算机站的电磁辐射信息,并且能区分不同计算机终端的信息。如“黑客”们利用电磁泄漏或搭线窃听等方式可截获机密信息,或通过对信息流向、流量、通信频度和长度等参数的分析,推出有用信息,如用户口令、帐号等重要信息。 机房是网络设备比较集中放置的地方,是放置重要数据交换设备和服务器设备的地方,网络中的大部分数据均会汇集到这些设备中进行数据交换。所以,机房基础设施的建设对于保护内部设备及数据有着举足轻重的作用。 根据电磁原理,我们可以知道,作为数据传输的通信线路,工作时都会在线缆周围形成不同强度的磁场,并向四面传播,我们可以利用相关的设备和仪器对其进行探测,再经过进一步处理,就可以获得线缆中传输的数据信息。整个过程我们可以称之为电磁泄漏。所以,网络和数据机房作为网络信息汇聚的中心,应该有较好的安全措施来确保各类信息的安全。 为了满足网络机房的信息保密、防止电磁泄漏。防干扰、防辐射要求,本工程针对对网络机房的使用需求,现场实现情况,并结合国家的标准规范,本方案设计了此网络机房屏蔽系统工程设计方案。本网络机房净高3.8米,梁下高3.3米,面积约20平方米。 2、工程内容与范围 计算机屏蔽工程是一种涉及到屏蔽室抗干扰技术、空调技术、供配电技术、自动检测与控制技术、综合布线技术以及净化、消防、建筑和装饰等多种专业的综合性工程。本网络机房净高3.8米,梁下高3.3米,面积约******平方米。根据客户要求,本工程机房屏蔽系统主要包括机房基础环境屏蔽部分,主要内容如下: 机房整体屏蔽环境:包括地面、墙面、吊顶、通风口、出入口、窗户等作C级机房屏蔽系统。机房接地:包括屏蔽体的接地,防雷带接地,以及系统工作接地。 机房屏蔽设备柜:预留两台机房屏蔽设备柜,供以后设备使用 3、设计依据 1、技术依据 GB12190-90<高性能屏蔽室屏蔽效能设计方案>; BMB3-1999《处理涉密信息的电磁屏蔽室的技术要求和测试方法》 GB50222-95<建筑物内部装修设计防火规范>; GB8702-88<电磁辐射防护规定>; GB9361-88<计算机场地安全要求>; GB2887-89《计算机场地技术条件》; GJB20219-94《军用屏蔽机房通用技术要求检测》; GB6650-86<计算机机房用活动地板技术条件>; GB 2887:《电子计算机场地通用规范》 GB 50019:《采暖通风与空气调节设计规范》 GB 50054:《低压配电设计规范》 GB 50174:《电子计算机机房设计规范》 GB 50325:《民用建筑工程室内环境污染控制规范》

方舱电磁屏蔽处理工艺

方舱电磁屏蔽处理工艺 摘要本文就方舱电磁屏蔽处理方面有关舱体拼装、门安装、屏蔽固定窗、壁盒(通风壁盒、电源或信号壁盒)安装、空调安装、暖风机安装、过舱导体等方面施工方法、工艺参数及工艺质量要求进行了说明;并归纳了一般屏蔽方舱的“屏蔽处理工序及检验流程图”。 关键词屏蔽方舱屏蔽材料缝隙处理质量检验 一前言 电磁屏蔽方舱是一种用来有效屏蔽电磁干扰和电磁脉冲的方舱,确保舱内作战功能设备不被电磁干扰和破坏,破坏使其发挥正常的作战功能;当然也能屏蔽舱内电子电气设备发出的电磁信号,使敌方的电磁信号探测装置无法侦察和探测己方的军用设备及其位置。方舱电磁屏蔽处理的根本目的是确保屏蔽方舱的电气连续性,主要着手点是缝隙处理,包括组舱缝隙、门(窗、壁盒)等孔口与舱壁间的缝隙及贯穿舱体导体等。 二设备、工具及辅助材料 CO2气体保护焊机氩弧焊机压缩空气电钻或风钻手提 磨光机拉铆枪钻头毫欧表小板刷毛笔

导电保护液(胶)0#砂布180#砂纸丙酮白细纱手套 三施工工艺 舱体拼装 1 在舱体拼装时,在其角部用弯角件将组成舱体的板片进行焊装(见图1)。钢骨架进行CO2气体保护焊,铝骨架进行氩弧焊(TIG 或MIG)。焊接前应去除板片方管和弯角件上的油污、氧化膜。为保证舱体的电气连续性,焊接应尽量采用连续焊。如采用断续焊,当连接面长度L≤50时用连续焊;当连接面长度大于50小于300时用断续焊,焊缝长度应≥50,焊缝间距≤200,且两端必须焊接;当连接面长度大于300断续焊时,焊缝长度≥50,焊缝间距≤300,且两端必须焊接。对材料厚度小于6mm的构件,应采用完全穿透焊接。 当舱体的电磁屏蔽效能SE≥40db时,舱体各片壁板外蒙板之间需用整条铝板条、角顶处(三片壁板交汇处)用铝罩(专用件)进行连焊。焊前应清除铝板条、铝罩及外蒙板上的油污、氧化膜,且使铝板条、铝罩与外蒙板接触处平整,有良好的导电接触面及焊接工艺性。焊接应采用连续焊,焊后应对焊缝进行修整及清理,且在所有焊缝处粘贴屏蔽胶带(铜箔)进行电磁密封(见图1、图2)。 如果舱体角部处需布暗线,应将线缆布设整齐、扎制、固定;应将导线用隔热材料进行包裹,以防焊接电连接板时烧伤导线(见图3)。 舱体内壁角接处(包括隔道壁与顶、底、侧相连处),用角型铝压条连接。连接前需将内蒙板及铝压条间相接触处的油污、油漆和氧

屏蔽机房(电磁屏蔽室)建设工程设计解决方案

一、工程主要包括以下几部分 1、屏蔽机房壳体及关键部位 2、屏蔽机房内部装饰(包括综合布线、接地、防雷、门禁、消防报警灭火、数字视频监控、环境监控、空调新风) 3、屏蔽机房内部供配电及照明 4、工期安排、工程验收和售后服务 二、机房设计建设要求 总体要求:依据国家军用有关屏蔽机房建设标准并结合现场实地环境,屏蔽机房工程设计应遵循标准性、可靠性、先进性、实用性、可扩展原则,具有设计规范安全可靠、功能齐全、使用管理方便等特点,机房的配电、布线、安全监控、防静电、防电磁信息泄漏、防水、降噪、抗干扰、空气质量等符合国家相关规范标准。系统设计方面要求整个屏蔽机房安全可靠,根据场地情况,尽可能扩大屏蔽机房的使用面积。功能设计方面,体现出先进的管理思想,尖端的科技含量,并在系统维护上体现方便、简单的原则。为保证设备或配件发生失效时立即更换,应考虑关键设备及配件上的一定冗余。机房做为保密数据处理、传输中心,要达到长期不间断工作要求。装修材料要采用高档环保新潮产品。 屏蔽机房主要技术指标: (1)满足国军标《密码机屏蔽机房的安装、使用和检测》(GJBz20219-94)、 (GJB5792-2006)的C级(最高标准)要求。 (2)满足国家保密标准BMB3-1999《处理涉密信息的电磁屏蔽室技术要求和测试方式》的C级要求。 (3)场地设计达到《计算机场地技术条件》(GB2887-89)和《计算机场地安全条件》(GB9361-88)的要求。 (4)机房设计符合《电子计算机机房设计规范》(GB50222-93)的相关要求。 (5)机房防火达到《建筑内部装修设计防火规范》(GB50222-95)和《建筑设计防火规范》(GBJ45-87)要求。 (6)地板设计达到《计算机机房用活动地板技术条件》(GB6650-86)要求。 (7)配电设计符合《低压配电装置及线路设计规范》(GBJ54-83)规范。 (8)机房施工及验收符合《计算机机房施工及验收规范》(SJ/30003-94)相关标准要求。 1、屏蔽机房壳体及关键部件: (2)屏蔽机房壳体 ①屏蔽机房壳体外形尺寸:按机房实际测量大小为准。 ②电磁屏蔽壳体的结构形式及工艺要求:电磁屏蔽壳体选用2-3毫米优质 冷轧板,经过专业设备及人员加工成标准模块拼接而成。内部进行防电 磁波泄漏检查、防潮、防腐防锈处理。 ③电磁屏蔽壳体的结构应尽可能确保机房内径高度、实用空间。一般装修 好的净高为2.6米。

方舱医院设计和改建的有关技术要求

方舱医院设计和改建的有关技术要求 方舱医院是以解放军野战机动医疗系统为模板,为解决 当前大量新型冠状病毒感染的肺炎确诊轻症患者的收治问题,充分利用既有建筑,在最短的时间内,以最小的成本建设和 改造的临时收治场所,从而实现有效控制传染源、最大限度 救治患者的目标。方舱医院具有大空间、大容量的特点,设计 和改建要遵循安全至上的原则,确保医护人员和患者的安全、建筑结构安全、设施设备运行安全、消防安全和环境安全。 一、选择被改造建筑的要求 1、用于改造为方舱医院的建筑宜为单层或多层建筑, 耐火等级不应低于二级,防火分区、安全疏散、建筑结构、消 防设施和消防车道等均能满足国家标准规范相关要求。 2、选址应尽量避开高密度居民区、幼儿园、小学校等 城市人群密集活动区。确实无法避开的下风向少数附近居民可 以考虑暂时搬离,可在医院外围设置显著危险标识或隔离带。 既有建筑与周边建筑物之间应有不小于20 米的绿化隔 离间距。当不具备绿化条件时,其隔离间距应不小于30 米。 3、被改建建筑入口处应有停车以及回车场地,能满足 救护车辆的快速抵达以及快速撤离,做到对外交通便捷、内部 联系顺畅、基本医疗保障设施齐备、无障碍设施齐全、并

为临时停车和物资周转留出场地,用地周边有较为完备的安防设施。场地宜有宽敞的室外空间,可搭建帐篷,安装相关医疗设备,用于病患的诊断治疗、检测监护,完善医疗配套设施。建筑内部空间便于迅速改建隔断,可选择如会展中心、 体育馆、新建的公租房、空置宿舍、酒店、党校等设施设备及消防基础条件较好的公共建筑。 4、既有建筑物周边的给排水、供配电、通讯信息等市 政配套设施能够满足方舱医院的使用要求或具备改造条件。 5、既有建筑物的平面布置、层高、结构形式、给排水、供配电等设施设备应能够满足方舱医院的使用要求或具备改造条件。 6、应选择结构状况良好的既有建筑,宜采用简便方法 对房屋结构状况进行评估。宜为框架结构或大跨度结构,便于内部拆改。 二、方舱医院改建内容要求 1、方舱医院的改造内容包括:室外市政设施、污水处 理设施、建筑内部分隔、建筑内部设施设备、对外交通通道、 人员物资进出运输通道、相邻环境防护与改善、卫生防疫、生物安全、安全防护等方面。 2、改造后至征用结束期间该建筑只能作为方舱医院使用,不得兼作他用。 3、改建后的方舱医院应满足各级卫健部门、疾控部门

屏蔽机房解决方案

数据机房在没有做屏蔽的情况下,电子设备会受到直击雷或间接雷等强电磁干扰源的影响导致设备无法工作或工作出现异常,最严重时出现损坏,这是比较常见的电磁干扰显现,另外一种现象就是,在打雷的时候听收音机,看电视,使用电脑,收音机会出现"吱啦"的噪音,电视机,电脑会出现图像抖动等等,这些都是雷电产生的干扰造成的电磁干扰。具体的措施能够使用屏蔽产品,并可靠接地,将外接的电磁干扰阻隔在外,把内部的设备产生的电磁波阻隔在内,这样构成一个等电位体,能够有效屏蔽电磁干扰。 屏蔽机房建设规则 影响屏蔽机房效能主要有以下因素: 1、屏蔽室所用材料 2、屏蔽材料的接缝处理 3、屏蔽门

4、通风窗 5、屏蔽窗 6、电源线的滤波处理 7、信号线的屏蔽处理 机房电磁屏蔽工程的保护 1.在施工中不得在屏蔽壳体内喷洒水或其它有腐蚀性的液体。 2.对施工结束的机房屏蔽体及其它安装附件要及时做防腐处理。防腐要求应符合《建筑防腐工程施工及验收规范》(TJ212-76 )中的有关规定的要求。3.对于焊接缝应按规定检查焊接效果,合格后对焊缝应及时作防腐处理。4.对电磁屏蔽体有关的各种管道、电缆等应按有关规定进行保护处理。 机房电磁屏蔽工程的测试 1.机房屏蔽壳体与原建筑的地面、墙体、楼板的绝缘性能测试应符合要求2.机房屏蔽效能的测试 3.电磁屏蔽效能的测试应按设计要求确定.测试的方法应按《高效能屏蔽室屏蔽效能测试方法》执行。

屏蔽机房整体建设步骤 屏蔽机房整体建设一般包括以下几个方面:综合布线、抗静电地板铺设、棚顶墙体装修、隔断装修、UPS电源、专用恒温恒湿空调、机房环境及动力设备监控系统、新风系统、漏水检测、地线系统、防雷系统、门禁、监控、消防、报警、屏蔽工程等。 一、防静电地板铺设 机房工程的技术施工中,机房地面工程是一个很重要的组成部分。机房地板一般采用防静电活动地板-屏蔽室。活动地板具有可拆卸的特点,因此,所有设备的导线电缆的连接、管道的连接及检修更换都很方便。 二、隔断装修 为了保证机房内不出现内柱,机房建筑常采用大跨度结构。争对计算机系统的不同设备对环境的不同要求,便于空调控制、灰尘控制、噪音控制和机房管理,往往采用隔断墙将大的机房空间分隔成较小的功能区域。隔断墙要既轻又薄,还能隔

高考英语语法填空:解读武汉“方舱医院”

2020年高考英语热点:专家解读武汉“方舱医院” 2月4日,武汉全面着手将会展中心、体育场馆等改造为“方舱医院”,集中收治新型冠状病毒感染的肺炎轻症患者。全市将建设13家“方舱医院”。初步统计增加床位上万个。如果入住患者病情转重,将转院诊疗。 今天带来一篇关于方舱医院的英文语法填空内容,老师可以让学生们学习一下。 The (1)________ (construct) of three mobile cabin hospitals in Wuhan, Hubei province has picked up steam on Monday night.The temporary hospitals will be equipped(2)________ beddings, tables and chairs, electric blankets and other essentials.Medical staff will (3)________(dispatch) to the three hospitals to take care of patients (4)_______ test positive for the virus — but show no severe symptoms — as soon as they are completed. (5)_______a patient's symptoms worsen, he or she will be transferred to Jinyintan Hospital, one of the city's designated (6)_______ (hospital) to admit patients infected with the virus."Putting into operation temporary hospitals with a large number of beds inside a giant space is a major public health measure China has taken," said Wang Chen, a renowned respiratory expert and president of the Chinese Academy of Medical Sciences. "It is a key measure taken by the authorities at a critical time," said Wang. "(7)_______(like) field hospitals during wartime or quake-relief efforts, the makeshift hospitals in Wuhan are unprecedented in China." Wang said the new measure is (8)_______(specifical) designed to address

电磁屏蔽机房(屏蔽室)接地系统方案

电磁屏蔽机房接地系统总体设计方案 1、工程概况 接地系统是电磁屏蔽机房(屏蔽室)建设的非常重要的一个环节,接地系统好坏不仅直接关系到电磁屏蔽机房内部设备的运行安全,更关系到使用人员的生命财产安全。本项目位于湖北省屏蔽机房建设接地项目,共计12个县局,每个县局各建设一套防雷接地系统。接地系统采用独立接地,接地电阻小于1欧姆,屏蔽机房内电子设备采用三级防雷措施,并且每个点安装一级防雷器和二级防雷器各一套。 2、施工现场人员组织结构 3、施工工艺流程 3.1接地体安装: 根据各县局具体情况进行地网选址定位→地网开挖,深度达到1米以上→敷设垂直接地体,垂直接地体要打入到深度位于2.5米处→敷设水平接地体→水平接地体和垂直接地体连接→对所有焊点进行防腐处理(刷防锈漆)→用扁钢引出至合适位置制作断接卡→用降阻剂均匀覆盖地网的水平接地体→对地网进行预检验合格后对地网进行回填并恢复→从断接卡处进行接地测量接地电阻<1Ω。

3.2机房等电位排敷设 从机房内部选择合适位置安装等电位铜排箱体。 3.3防雷引下线敷设 支架安装→引下线调直→引下线固定→连接测试断接卡预留端子。 3.4防雷器的安装 在机房内部选择合适位置进行防雷器的固定安装→防雷器和电源部分的连接以及和接地等电位连接

安全控制措施及危险源分析 4.1进行接地装置施工时,如位于较深的基槽内应注意高空坠物并做好护坡处理 4.2进行电焊作业时,电焊机应符合相关规定并使用专用开关,必须持证上岗,电焊作业时应采取防护措施,避免弧光伤害。 4.3遇到雷雨天气,禁止在室外作业。 地线建设用料清单及参数

地线建设遵循的标准、规范 (1)《建筑物防雷设计规范》(2010版)GB50057-2010 (2)《电子计算机机房设计规范》GB50174-93 (3)《雷电电磁脉冲的防护》IEC 6I312 (4)《低压配电设计规范》GB 50054-95 (5)《电气装置安装工程接地装置施工及验收规范》GB 50169-92 (6)《建筑物电子信息系统防雷技术规范》GB50343-2012 ----版权所有 (莫克屏蔽--电磁屏蔽机房建设方案专家)转载请注明出处。

相关文档
最新文档